8/17/2022
RFQ 1333-22-Q-01124
Abrasive Blasting and Bottom Painting R/V Chesapeake
Questions and Answers
1. QUESTION: There is a 12-week Leadtime on the Sherwin Williams Sea Voyager paint listed in the
Statement of Work. Please advise as this will extend the date of completion past the November
1, 2022.
ANSWER: The date for completion will be extended to May 1, 2023
2. QUESTION: Will you allow other paint coating alternatives other than Sherwin Williams?
ANSWER: The Government will allow an alternative to Sherwin Williams marine coatings as long as the vendor can provide confirmation and take ownership of the paints compatibility with
Sherwin Williams marine paints.