This is a Statement of Work (SOW) for the decommissioning of the NWFSC Radiation Program at the Montlake Laboratory in Seattle, Washington, with a period of performance through February 28, 2027.
The facility, operated by NOAA's National Marine Fisheries Service under NRC License No. 46-06377-04 Amendment 45, contains radioactive materials in multiple areas including Shipping & Receiving, Labs 309E, 311E, 421E, and 413E, along with a centralized waste storage shed. The contractor must manage legacy radioactive waste (tritium, carbon-14, and iodine-125) in five 55-gallon drums plus miscellaneous storage containers, and decommission equipment including two PerkinElmer TriCarb Liquid Scintillation Counters, one gamma counter, and a portable lead-based paint XRF analyzer. All waste drums are assumed at least 75 percent full with contact dose rates at ambient background levels, priced on a per-drum basis.
The four primary tasks require: (1) packaging, transport, and disposal of radioactive waste and equipment through licensed brokers; (2) extraction and management of internal radioactive sources from analytical equipment; (3) radiological surveys and swipe testing for release of use areas supporting NRC license termination, performed per 10 CFR Part 20 Subpart E and ALARA principles; and (4) preparation of manifests, certificates of disposal, survey reports, and NRC Form 314 for license termination. The contractor must possess all required federal, state, and local licenses, permits, and certifications for health physics services, waste handling, transportation, and storage. Proposals should include technical qualifications demonstrating licensing and insurance status, intended disposal sites, and technical knowledge of radioactive waste regulations, along with bid schedules addressing waste disposal and survey work either combined or separately. Technical merit is weighted more heavily than price in award determination.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work NWFSC Radiation Program Decommissioning
NWFSC, Seattle, WA 09-03-2026
1. BACKGROUND
1.1. Campus. The Montlake laboratory is a research laboratory owned and operated by the U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), National Marine Fisheries Service (NMFS), Northwest Fisheries Science Center (NWFSC). It is located at 2725 Montlake Blvd. E, Seattle, WA 98112.
1.2. NRC License. The facility operates under a radioactive materials license issued by the U.S. Nuclear Regulatory Commission (NRC); License No. 46-06377-04 Amendment 45.
1.3. Radioactive Materials Use Areas. Areas of the facility that were authorized for radioactive materials use and/or storage are as follows:
1.3.1. Shipping & Receiving Area. This space is approximately 216 SF and is designated as the shipping and receiving area for the Center. There is a safe in this room to secure radioactive materials for short-term storage. Packages were not opened in this area as it was only authorized as a storage area.
1.3.2. 309E/311E Horseshoe Lab. The area in each lab is 200 SF. Radiation work only occurs in 309E. 311E is labeled as a radiation area because there is a direct passage between these two laboratory spaces. See Photos 2 and 3 of Exhibit A. Historical use of radioactive material was limited to 309E. Room 309E contains a Perkin Elmer TriCarb Liquid Scintillation Counter (LSC), dot matrix printer, and Perkin Elmer LSC standards (H-3, C-14, Bkg).
1.3.3. 421E Lab. This area of this lab is 373SF and contains an unreleased liquid scintillation counter. See Photos 4 and 5 of Exhibit A. Historically this area was authorized for I-125 and H- 3 use. The 421E lab contains an Perkin Elmer TriCarb LSC with Perkin Elmer LSC standards (H-3, C-14, Bkg).
1.3.4. Radioactive Waste Storage Shed. This shed currently contains five 55-gallon metal waste drums and 1 acrylic and lead-lined wooden box utilized for beta emitter storage. The wooden box has only an empty lead pig inside.
1.3.5. 413E Lab. This lab was surveyed in preparation for submission to the NRC for formal release of the lab space June of 2023. Surveys were performed to identify potential areas of contamination and to release fixtures and equipment that previously were associated with radioactive material. NWFSC has not submitted documentation to release the use area for unrestricted use, so it must be included in the radioactive materials license termination. See Attachment 1 in Section 5.
1.4. General Radiation Program Waste. The Montlake Laboratory produces radioactive waste from the Physiology Program (Iodine-125 and Tritium) and Harmful Algal Blooms Program (Tritium). Low-level radioactive waste streams include:
1.4.1. Solidified liquid waste;
1.4.2. Iodine-125 dry waste;
1.4.3. Liquid scintillation vials containing Ecolume based scintillation cocktail;
1.4.4. Tritium/Carbon-14 dry waste;
1.5. Decommission Radioactive Waste. The decommissioning/closure-related wastes (or potential waste) are as follows:
1.5.1. Waste related to incidental decontamination efforts (as necessary)
1.5.2. Generally licensed sources contained within two Perkin-Elmer TriCarb liquid scintillation counters.
1.5.3. Two (2) LSC standard kits associated with the two LSC machines.
1.5.4. One (1) 55-gallon drum of dry solid waste (H-3) generated during previous lab closure activities.
1.5.5. Materials/equipment identified as containing radioactive material or radioactive contamination that cannot be reduced to levels for free release in accordance with 10 CFR
1.6. Decommission Equipment. The following equipment requires removal and disposition, including any associated equipment, racks, trays, sources, and standards. This equipment is associated with historical radiation work and is subject to release from radiological control in accordance with NUREG-1556 Vol 7 acceptable surface contamination levels.
1.6.1. One (1) Portable LBP Thermo Niton Lead-Based Paint XRF Analyzer: Model XLp series, Serial Number: 6562 (Manufacturer: Thermo NITON Analyzers LLC, Billerica, MA;
Isotope: Cd-109 [40 mCi as of 6/15/2007] or Am-241 [4.5 µCi as of 02/26/2004]; Last leak test:
05/23/2011).
1.6.2. Two (2) Perkin-Elmer TriCarb Liquid Scintillation Counters
1.6.2.1. Room 421E. PerkinElmer Parkard Tri-Carb Liquid Scintillation Counter: Model B1900, Serial Number: 103840
1.6.2.2. Room 307E. PerkinElmer Parkard Tri-Carb Liquid Scintillation Counter: Model 1600 TR, Serial Number: 422739.
1.6.3. One (1) Gamma Counter. PerkinElmer Parkard TopCount NXT Microplate Scintillation & Luminescence Counter: Model C9912V0, Serial Number: 429550. MFG Date: August 2002.
1.7. Survey for Release.. The following materials require surveys for release from radiological control.
1.7.1. Benchtop lead shielding (bricks, sheets, squares)
1.7.2. Shielded shipping containers associated with stock vials received from manufacturers.
1.7.3. Trays, racks, and accessories associated with LSC and Gamma Counter equipment in Section 1.6
1.8. Radioactive Waste Inventory. Table 1 summarizes the radioactivity levels on radioactive waste awaiting disposal. For estimation and proposal purposes, contractors shall assume each of the waste drums identified in the SOW/Inventory is at least 3/4 full. Contact dose rates for all containers are at ambient background levels (< 0.1 mR/hr), and disposal costs should be priced on a per-drum basis.
Table 1 - Radioactive Waste Inventory (stored in the Rad-Waste Shed – See Exhibit A, Photo 1)
55-Gal Drum
Date Closed
Description Isotope Initial Activity (mCi)
Liquid/Solid (L/S)
Primary Radiation
Expected Contact Radiation Dose Rate
1A 7/2019 Solidified Liquid Waste I-125 2.0975 S Gamma / X-ray Ambient Background (< 0.1/mR/hr)
2A 6/2023 Scintillation Vial Waste.
C-14 comes from standards.
H-3 C-14
1.8035
0.0001 L Low-energy
Beta (β-) Ambient Background (< 0.1/mR/hr)
5A 7/2019 Dry Solid Waste I-125 0.1902 S Gamma / X-ray Ambient Background (< 0.1/mR/hr)
6A 4/2023 Dry Waste H-3 0.7170 S Low-energy Beta (β-)
Ambient Background (< 0.1/mR/hr)
D&D 6/2023 Dry Solids / Equipment H-3 0.1 S Gamma / X-ray Ambient Background (< 0.1/mR/hr)
2. SCOPE
2.1. Contractor to Furnish. The Contractor shall furnish all labor, supervision, personnel, materials, equipment, tools, transportation, packaging, permits, licenses, services, and facilities necessary to support the decommissioning of the NWFSC Radiation Program at the Montlake Laboratory and the termination of the NWFSC Radioactive Materials License. The work includes:
2.1.1. Facilitating the disposal of legacy radioactive waste and equipment through a licensed radioactive waste broker, processor, or disposal site;
2.1.2. Removal and disposal of internal radioactive sources from analytical equipment;
2.1.3. Radiological surveys and swipe testing related to the release of all use/storage areas in support of license termination;
2.1.4. Facilitating the disposal of all radioactive waste/mixed waste generated during the license closure process; and
2.1.5. Preparation of manifests, disposal documentation, and decommissioning reports.
2.1.6. The Contractor shall provide technical support related to NRC facility decommissioning, termination of the NWFSC license, and the removal and disposition of licensed radioactive materials designated as radioactive waste.
2.2. Contractor Qualifications. The Contractor and subcontractors shall possess all licenses, permits, approvals, insurance, and certifications required to perform health physics services, radioactive waste handling, transportation, storage, treatment, and disposal activities under applicable federal, state, and local regulations.
2.3. Regulatory Compliance. All work shall be performed in accordance with applicable requirements of:
2.3.1. U.S. Nuclear Regulatory Commission (NRC)
2.3.2. U.S. Environmental Protection Agency (EPA)
2.3.3. Occupational Safety and Health Administration (OSHA)
2.3.4. Washington State Department of Ecology (WSDOE)
2.3.5. NRC License No. 46-06377-04 Amendment 45;
2.3.6. 10 CFR Part 20;
2.3.7. 10 CFR Part 30;
2.3.8. Applicable DOT hazardous materials transportation regulations; and
2.3.9. Applicable federal, state, and local regulations governing radioactive and mixed wastes.
3. APPLICABLE DOCUMENTS
3.1 Applicable requirement documents are as follows:
3.1.1. NRC License 46-06377-04 Amendment45
3.1.2. NWFSC Radiation Safety Program
3.1.3. 10 CFR Part 20 – Standards for Protection Against Radiation
3.1.4. 10 CFR Part 30 – Rules of General Applicability to Domestic Licensing of Byproduct Material
3.1.5. Applicable DOT Hazardous Materials Regulations (49 CFR)
3.1.6. Applicable Washington State hazardous waste regulations
4. SPECIFIC TASKS. In support of the following specific Tasks, the NWFSC will provide the Contractor with access to any relevant radiation program records and physical access to areas necessary to conduct radiological surveys.
4.1. TASK 1 - Disposal of Radioactive Waste, Equipment, and Incidental Survey Waste The Contractor shall facilitate packaging, transport, and disposal of the radioactive waste, radioactive standards, laboratory debris, and equipment identified in this SOW. The waste disposal work shall include, but not be limited to, the following:
4.1.1. Tritium (H-3), Carbon-14, and Iodine-125 wastes
4.1.2. Legacy radioactive standards and radioactive calibration sources
4.1.3. Radioactive waste identified/generated during equipment and program decommissioning
4.1.4. Disposal or recycling of laboratory equipment identified in Section 1.4 that requires disposal as radioactive waste.
4.1.5. The Contractor shall furnish all labor, packaging materials, shielding, containers, overpacks, transportation resources, manifests, and disposal documentation necessary to complete the work including any characterization, identification, or inventory information necessary to meet applicable acceptance criteria.
4.1.6. Radiation labels and markings associated with materials released as non-radioactive following decay-in-storage processing shall be removed or obliterated prior to disposal.
4.1.7. All handling, transportation, recycling, and disposal activities shall comply with applicable NRC, DOT, EPA, OSHA, and WSDOE requirements.
4.2. TASK 2 - Extraction and Management of Internal Radioactive Sources The Contractor shall extract, characterize, package, transport, and dispose of internal radioactive sources contained within laboratory equipment, including Liquid Scintillation Counters (LSCs) and associated instrumentation. The Contractor shall:
4.2.1. Identify internal radioactive components or contamination associated with the equipment;
4.2.2. Perform removal activities using appropriate radiological controls;
4.2.3. Package and transport extracted radioactive materials in accordance with applicable regulations; and
4.2.4. Provide arrangements for final disposition and ensure NWFSC receives any certifications of disposal and waste receipt acknowledgements.
4.2.5. The Contractor shall immediately notify the Radiation Safety Officer (RSO) of any previously unidentified radioactive materials, contamination, leaking sources, or radiological conditions discovered during execution of the work.
4.3. TASK 3 - Radiological Surveys
The Contractor shall perform radiological surveys associated with decommissioning activities.
Survey activities shall include:
4.3.1. Develop a survey plan to establish release limits that are acceptable to the RSO and US NRC for the release of fixtures/equipment and permanent building surfaces respectively.
4.3.2. Removable contamination swipe surveys, scanning, and direct radiation measurements required to demonstrate compliance with the applicable release limits;
4.3.3. Surveys of affected laboratory work areas, equipment, and waste handling locations;
4.3.4. Verification that no residual contamination attributable to Contractor activities remains.
4.3.5. All radiological work shall be performed in accordance with the As Low As Reasonably Achievable (ALARA) principle and the NWFSC Radiation Safety Program
4.3.6. Final radiological conditions shall support unrestricted release criteria in accordance with 10 CFR Part 20 Subpart E.
4.3.7. Survey documentation shall include:
4.3.7.1. Survey locations;
4.3.7.2. Instrument make, model, and serial number;
4.3.7.3. Instrument calibration dates;
4.3.7.4. Background measurements;
4.3.7.5. Survey methodology; and
4.3.7.6. Survey results.
4.3.8. Any contamination identified, resulting from Contractor activities, shall be remediated by the Contractor at no additional cost to the Government.
4.4. TASK 4 - Documentation and Reporting
The Contractor shall prepare, maintain, and submit all documentation necessary to perform the work and demonstrate compliance with applicable NRC, DOT, EPA, OSHA, WSDOE, disposal facility, and transportation requirements.
4.4.1. Documentation shall include, at a minimum:
4.4.1.1. Shipping papers and manifests;
4.4.1.2. Waste profiles;
4.4.1.3. Certificates of burial, destruction, recycling, treatment, or decay;
4.4.1.4. Hazardous waste manifests for mixed waste;
4.4.1.5. Equipment disposition records;
4.4.1.6. Radiological survey reports;
4.4.1.7. Waste inventory reconciliation records; and
4.4.1.8. Final status survey report.
4.4.2. For waste managed under decay-in-storage provisions, the Contractor shall provide records documenting:
4.4.2.1. radionuclides,
4.4.2.2. storage dates,
4.4.2.3. disposal dates,
4.4.2.4. survey instrument information,
4.4.2.5. background measurements,
4.4.2.6. final survey results, and
4.4.2.7. signature of the individual performing the release survey.
4.4.3. The Contractor shall provide work necessary to prepare and submit NRC Form 314, Certification of Disposition of Materials, by the licensee in addition to the request to terminate the NWFSC radioactive materials license.
4.4.4. All documentation shall be submitted electronically in searchable PDF format unless otherwise approved by the Government.
5. ATTACHMENT
5.1. FINAL STATUS SURVEY REPORT ROOM 413E – 6/26/2023
6. GENERAL REQUIREMENTS
6.1. Project manager
Promptly following award of the contract, the contractor shall designate a project manager. The project manager is responsible for maintaining coordination and execution of the contract.
Changes to the designated project manager can only be made upon prior approval of the RSO.
The project manager shall serve as liaison between the contractor and the RSO for all work required under this contract.
6.2. Project Coordination
The Contractor shall coordinate all work activities with the RSO and the facility point-of-contact.
The RSO will be employed by the National Oceanic and Atmospheric Administration (NOAA).
Work at the site shall not interfere with the on-site normal operating functions. If interference is unavoidable, every effort shall be made to keep disruption to a minimum.
6.3. Reporting
Contractor format is acceptable provided that it satisfies the aforementioned specific minimum requirements specified in Section 4.
7. GOVERNMENT-FURNISHED EQUIPMENT – None
8. DELIVERABLES AND SCHEDULE
Following is a schedule of all deliverables, including administrative deliverables, required during the period of performance of this contract:
1. Facility Release - Survey Plan
2. Facility Release - Final Status Survey Report (includes survey for release and permanent building surface results)
3. Waste Shipment Records (inventory, manifests, permits, and certifications)
4. US NRC License Termination request, including applicable forms and supporting documentation ready for submission.
SUBMITTAL ADDRESS. All submissions shall become property of the U.S. Government and shall be submitted to:
Thanh Minh Trinh, P.E.
Radiation Safety Officer 2725 Montlake Blvd. East Seattle, WA 98112
(206) 860-3316 Thanh.M.Trinh@noaa.gov
9. PERIOD OF PERFORMANCE
The Period of Performance for this contract is through February 28, 2027.
mailto:Thanh.M.Trinh@noaa.gov
Exhibit A
Photo 1 - Central Radiation Waste Storage Shed – Existing Rad Waste from legacy operations.
Photo 2 - Lab 309E
Photo 3 - Lab 309E Floor Plan – 200 SF
Photo 4 - Lab 421E
Photos 5 - Lab 421E Floor Plan - 373 SF
Photo 6 - 3rd Floor HVAC System with 307E highlighted
Photo 7 - 4th Floor HVAC System with highlighted 413E and 421E
End of SOW
413E
309E
421E
10. PROPOSAL FORMAT
The contractor’s proposal should be submitted in the following format:
10.1. Cover Letter
A cover letter may be submitted as part of the proposal package that identifies a Contractor representative and any other information the contractor wishes to include. (2-page limit).
10.2. Bid Schedule
The Contractor shall provide a bid schedule that addresses the tasks described in Section 4.
Specific Tasks 1 and 2 pertain the disposal of various radioactive material and legacy radioactive waste drums. Specific Tasks 3 and 4 pertain to the work required to formally release the NWFSC radiological use areas in support of US NRC license termination.
A bid schedule addressing the items in Table 1 shall be proposed by the Contractor.
Additionally, the contractor shall include any charges not listed in this table (e.g., fuel surcharges, truck time, flat base fee for each pick-up, documentation, etc.) for evaluation purposes.
The bid schedule may address the waste disposal work and the radiological survey work in support of license closure work either combined or separately, whichever is most economical efficient.
11. EVALUATION CRITERIA
The Government will award a purchase order resulting from this solicitation to the responsible offeror whose proposal, conforming to the requirements of the solicitation, is determined to be most advantageous to the Government, considering price and other relevant factors. The Government shall evaluate offers based on technical and pricing factors, with technical merit being more important than price. Proposals shall also include the following information.
11.1. Technical Knowledge
The Contractor shall furnish with offer submittal information establishing that the contractor is appropriately licensed, permitted, trained and insured for the performance of all required radiological surveys, waste packaging, instrument handling, transport, health physics services, and temporary storage of low-level radioactive waste involved in this contract and a list of intended temporary and final disposal sites for each category of waste.
In the case of subcontracting, the primary contractor shall also provide proof of licensing, permits, insurance, and list of intended temporary and final disposal sites of all subcontractors. Additionally, the contractor shall submit information in a written statement to allow the evaluation of the vendor’s knowledge of the technical requirements associated with the packaging, handling, transport and disposal of low-level radioactive waste in accordance with applicable local, state and federal policies, laws and regulations.
Price The pricing information shall be evaluated to determine fairness and reasonableness as compared to what is being offered.
12. Recommended Vendors
Thomas Gray and Associates 1205 West Barkley Ave.
Orange, CA 92868 ph: 714-997-8090 fax: 714-997-3561 Joe Skovron- local contact 206-417-1823 206-313-0607 (cell)
Clean Harbors 26328 79th Ave South Kent, WA 98032 www.cleanharbors.com John Bige Technical Services Account Manager 206-549-1597 bige.john@cleanharbors.com
Philotechnics 201 Renovare Blvd.
Oak Ridge, TN 37830 Phone: 865-285-3007 Toll Free: 1-888-RAD-WASTE Main Fax: 865-483-1530 Kimberly Page
Chase Environmental Group, Inc.
11450 Watterson Court Louisville, KY 40299-2389 Phone: 502-267-1455 Fax: 502-267-7299
DUNS 798229910 07CL6
Steven A. Sturdevant
File details come from the government source that posted it. Updated .