Statement_of_Work__-_Point_Adams_Electrical_Backup_Power_System_-_28_Jul_26.pdf
PDF 466 KB Posted
- Attached to
- Point Adams Backup Power System Federal contract opportunity
- Solicitation number
- 1305M326Q0423
About this file
This is a Statement of Work (SOW) for the National Oceanic and Atmospheric Administration's (NOAA) Northwest Fisheries Science Center (NWFSC) Point Adams Electrical Backup Power System project located in Hammond, Oregon.
The project consolidates two existing separate 200-amp utility services into a single 400-amp, 120/240-volt single-phase service entry to establish resilient power infrastructure. Task 1 requires electrical utility service consolidation, including new electrical panels, metering, and distribution systems utilizing existing empty 4-inch Schedule 40 underground conduits installed in 2024. The distribution architecture consists of a main 400-amp distribution panel supplying three branch feeders: 60-amp to the 2-Bay Building, 200-amp to the Main Building, and 200-amp to the 4-Bay Building, with a 150-amp sub-feed from the 4-Bay Building to the 1-Bay Building. Task 2, a mandatory design-build requirement, involves installing a hybrid inverter and battery energy storage system (BESS) capable of providing 72 hours of emergency backup power with microgrid islanding capabilities, smart load management for automatic shedding of non-critical loads, and a Microgrid Interconnection Device (MID) for automatic isolation during outages. Critical loads include freezers, security and facility lighting, and IT/computer network systems. Task 3 is an optional solar photovoltaic installation consisting of a 20-kilowatt DC ground-mounted array with DC-coupled topology, structural engineering for local wind conditions, and a 5-foot clearance with 4-foot chain-link perimeter fence. All work must comply with federal, state, and local codes, utility requirements (Pacific Power/PacificCorp), and the Buy American Act with no made-in-China products accepted.
Contractor execution requirements include submission of a comprehensive Work Plan within 30 calendar days after Notice to Proceed (NTP), including project schedule, utility application documentation, complete engineering submittals, manufacturer cut-sheets, product validation for marine coastal environments, and system testing protocols. Testing and commissioning by manufacturer-certified technician must be completed with a report submitted within seven calendar days, followed by comprehensive operational training within five working days. All deliverables including as-built drawings in AutoCAD format, operation and maintenance manuals, testing and commissioning reports, and warranty documentation must be submitted within seven calendar days of completion. The core scope (Tasks 1 and 2) must be completed within 180 calendar days of NTP. Workmanship warranty is one year, with manufacturer coverage on all equipment and Task 2-specific warranties requiring minimum one-year parts and labor coverage plus five-year warranty on inverters/chargers, remote automatic panels, and battery packs. The Contracting Officer Representative is Thanh Minh Trinh, P.E., at the NWFSC Seattle office.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A6_-_TechnicalReport-4_Redacted_0001.pdf | ||
| Sol_1305M326Q0423_Amd_0001.pdf | ||
| A1_-_Statement_of_Work__-_Point_Adams_Electrical_Backup_Power_System_-_18_Aug_26_0001.pdf | ||
| A4_-_Questions___Answers_Tracker_-_18_Aug_26_0001.pdf | ||
| Sol_1305M326Q0423.pdf | ||
| Past-Performance-Questionnaire.docx | DOCX document | |
| Point_Adams_Electrical_Specifications__-_28_Jul_26.pdf | ||
| Davis-Bacon_Act_WD___OR20260092_-_18_May_26.pdf | ||
| Questions___Answers_Tracker_-_Point_Adams_Electrical_Backup_Power_System.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work National Oceanic and Atmospheric Administration (NOAA)
National Marine Fisheries Service (NMFS) Northwest Fisheries Science Center (NWFSC) Point Adams Electrical Backup Power System
1.0 Project Background & Location. The Northwest Fisheries Science Center (NWFSC) is a marine research organization owned and operated by the U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), National Marine Fisheries Service (NMFS).
NWFSC has five (5) major campuses located in Washington and Oregon with its regional headquarters located in Seattle, WA.
1.1 Project Location: The Point Adams Research Station is located at 520 Heceta Place, Hammond, OR 97121. It was the location of a former U.S. Coast Guard facility in the early to mid-1900s. It is comprised of five major buildings sitting on approximately 5.8 acres, located along the shoreline near the mouth of the Columbia River.
1.2 Current Infrastructure: The Point Adams Main Campus does not have a central electrical backup system. It relies on staff to manually start portable gasoline power generators to energize critical loads during a power outage. Currently, two separate 200-amp single-phase services feed the site from power poles along the west boundary:
1.2.1 One 200-amp service feeds the 4-Bay Building from an overhead pole running west to east.
1.2.2 The second 200-amp service is located in the northwest corner of the site inside the Generator Building.
2.0 Objective: To establish a resilient and unified power infrastructure, the two existing separate utility services shall be consolidated into a single central service entry point for the campus. The consolidated service will establish a single point of utility interconnection supplying a 400-amp, 120/240V single-phase system with emergency battery backup capacity and integration capability for solar photovoltaic (PV) generation to increase resilience and reduce carbon emissions.
2.1 Order of Precedence: This SOW establishes the primary functional, technical, and performance requirements for the project. In the event of any conflict between this SOW and attached technical specifications referenced in Section 8 of this SOW, the terms and requirements of this SOW shall govern.
3.0 Technical Scope of Work. The contractor shall provide all required design, service, labor, parts, equipment, tools, and materials to complete the tasks described below. All work shall comply with applicable federal, state, local codes, and local electrical utility requirements (Pacific Power / PacificCorp).
3.1 TASK 1 – Electrical Utility Service Consolidation. The contractor shall perform all required work including new electrical panels, metering, high-voltage, low-voltage, and conduit systems to consolidate utility power:
3.1.1 Service Consolidation: Combine the two existing independent 200-amp utility services into a single 400-amp, 120/240-volt single-phase meter/main utility service entry supplying two 200-amp distribution panels.
3.1.2 Conduit Utilization: Utilize the existing empty 4-inch Schedule 40 underground feeder conduits installed in 2024, as indicated by the red lines on Figure 1 of Exhibit A.
3.1.3 Distribution Hierarchy: Build out the single-line distribution architecture as shown in Figure 8.1 of Exhibit A and Figure 8.2 of Exhibit A
3.1.3.1 Main Distribution: The single 400A single-phase service feeds a central 400A Main Distribution panel.
3.1.3.2 Branch Feeders: Route and connect three distinct feeder circuits from the 400A Main Distribution panel:
3.1.3.2.1 One 60A Feeder to the 2-Bay Building Panel.
3.1.3.2.2 One 200A Feeder to the Main Building Panel.
3.1.3.2.3 One 200A Feeder to the 4-Bay Building Panel.
3.1.3.3 Downstream Sub-Feeder: Install a 150A Sub-feed originating from the 4-Bay Building Panel to feed the 1-Bay Building Panel.
3.1.4 Component Restrictions: Brand references in design documents represent basis-of-design standards; equal or superior alternatives are acceptable upon review. All products must comply with the Buy American Act. Made-in-China products or components will not be accepted.
3.2 TASK 2 – Inverters and Battery Backup System with Remote Load Control. This is a mandatory design-build task to design, furnish, and install an intelligent hybrid inverter and battery energy storage system (BESS) capable of providing emergency power for a minimum of 72 hours for essential site functions. The installation must implement the microgrid architecture and sequence of operations detailed in Figure 8.2 of Exhibit A:
3.2.1 Microgrid & Islanding Capabilities: The 200-amp distribution panels supplying the Main Building and 4-Bay Building must operate both in parallel with the utility grid and as an islanded microgrid during power outages. To enable this, integrate a service-rated, UL-listed Microgrid Interconnection Device (MID / Backup Isolation Transfer Device) that automatically isolates the facility from the grid during outages.
3.2.2 Power Conversion & Inverters: Power conversion and backup shall be delivered by split-phase hybrid inverter/chargers with sufficient continuous islanded capacity and motor-surge headroom.
Inverter AC outputs must land on their respective panels via code-compliant circuit breakers and use utility AC for battery charging when grid power is present. Neutral-to-ground bonding must automatically shift so the bond resides at the main service under grid conditions and at the inverter system when islanded.
3.2.3 Smart Load Management: To minimize battery capacity requirements while achieving the 72-hour resiliency target, the system must automatically isolate and shed non-critical loads during an outage. The system shall utilize remotely controlled breakers, load-control relays, or smart load-shedding panels (e.g., Powerlink Panel Boards) controlled by a central Backup Controller.
3.2.4 Load Classification: The contractor shall coordinate with NOAA operations staff to finalize load classifications:
3.2.4.1 Critical Loads (Must remain continuously powered): Freezers located in or near the 1-Bay
Building, indoor/outdoor security and facility lighting, and facility IT/computer network loads.
3.2.4.2 Non-Critical Loads (Automatically shed during grid outages): Comfort HVAC, standard receptacle circuits, water heating, and non-essential plug loads.
3.2.5 Automated Sequence of Operations: The system must execute the exact sequence detailed in Figure 8.2 of Exhibit A:
3.2.5.1 Step 1: Utility grid fails.
3.2.5.2 Step 2: MID opens and the system islands.
3.2.5.3 Step 3: Inverters form the islanded grid and energize the backup bus.
3.2.5.4 Step 4: Non-critical loads are automatically shed via controller signals.
3.2.5.5 Step 5: Critical loads remain powered uninterrupted.
3.2.5.6 Step 6: Solar PV seamlessly charges batteries and supports site loads while islanded.
3.3 OPTIONAL TASK 3 – Solar Panel Installation. Provide and install a ground-mounted 20 kWdc solar photovoltaic (PV) array, including panels, mounting rails, structural framing, wiring, and balance-of-system electrical equipment. This optional task integrates directly into the inverter/battery system as represented in Figure 8.2 of Exhibit A:
3.3.1 Electrical Configuration: Solar generation must be sized to total 20 kWdc and wired as 600 Vdc-class strings into properly configured Maximum Power Point Tracking (MPPT) charge controllers. The controllers shall connect to the battery/inverter system in a DC-coupled topology landing directly on the common 48V battery bus to maintain battery charging capability during grid outages.
3.3.2 Conduit Routing: Utilize the existing underground conduit path running from the Generator Building to the 1-Bay Building.
3.3.3 Safety & Compliance: Include PV/DC disconnects, overcurrent protection, equipment grounding, and module-level rapid-shutdown devices compliant with NEC Article 690 and utility standards.
3.3.4 Structural & Civil Engineering:
3.3.4.1 Structural Framing: Solar panels shall mount on an exterior metal structure engineered for local wind velocity and design pressures.
3.3.4.2 Pier Foundations: Mount structural framing on 16-inch round concrete pier foundations installed to a depth below the local frost line.
3.3.4.3 Footprint: Array footprint requires approximately 1,500 sq. ft. (measuring 25 ft. by 60 ft.).
3.3.4.4 Enclosure & Clearance: Provide a 5-foot clearance around the array and install a 4-foot-high chain-link perimeter fence around the solar installation.
4.0 Contractor Execution & Submittal Requirements. The following execution requirements apply uniformly to Task 1, Task 2, and Optional Task 3.
4.1 Work Plan Requirements. Prior to starting physical fieldwork on any task, the contractor must submit a comprehensive Work Plan to NWFSC for review and approval. The plan shall include:
4.1.1 Project schedule (Gantt chart format) and staff coordination workflows.
4.1.2 Documentation verifying utility application, engineering review, and approval from the local electric utility (Pacific Power).
4.1.3 Complete engineering submittals including conductor sizing, voltage drop, and Ampere Interrupting Capacity (AIC) short-circuit calculations.
4.1.4 Manufacturer cut-sheets and submittals confirming design compliance with Section 3.0 and utility interconnection rules.
4.1.5 Product validation proving all equipment installed outdoors is rated for marine coastal environments.
4.1.6 System testing protocols, commissioning plans, maintenance schedules, and personnel training outlines.
4.2 Construction Phase & Site Operations
4.2.1 Downtime Coordination: The contractor shall schedule and coordinate all service interruptions with NOAA staff at least 3 weeks in advance and provide temporary power if necessary to maintain facility critical operations.
4.2.2 Labor & Materials: Provide all necessary labor, materials, equipment, and tools to execute the approved work plan.
4.2.3 Weatherproofing: Protect all interior spaces and building penetrations from weather elements daily; secure all building openings at the end of each workday.
4.3 Testing, Commissioning, & Project Closeout Deliverables
4.3.1 Testing & Commissioning: A manufacturer-certified technician shall test and commission all equipment. The contractor shall submit a comprehensive Testing and Commissioning Report within seven (7) calendar days of completion.
4.3.2 Operational Training: Provide comprehensive system operation and preventive maintenance training to NWFSC personnel within five (5) working days following system commissioning. Submit completion logs within seven (7) calendar days.
4.3.3 As-Built Drawings: Submit two (2) hard copies and one (1) PDF copy of as-built drawings for review. Upon approval, deliver finalized electronic files in AutoCAD (ACAD) format within seven (7) calendar days.
4.3.4 Operation & Maintenance Manuals: Deliver two (2) hard copies and one (1) electronic PDF copy of complete O&M manuals within seven (7) calendar days of system commissioning.
5.0 General Project Management & Administration
5.1 Safety Plans & Project Schedules.
5.1.1 OSHA Safety Plan: Submit a site-specific OSHA Safety Plan within thirty (30) calendar days after Notice to Proceed (NTP) and prior to field start, incorporating hot work/welding protocols if required.
5.1.2 Project Schedule: Submit a Gantt chart project schedule within thirty (30) calendar days after NTP; update and review weekly with the NWFSC Point of Contact (POC).
5.1.3 Substitution Requests: Submit product substitution requests to the NOAA POC; allow seven
(7) calendar days for government review.
5.2 Comprehensive Project Warranties. Register all system components and deliver warranty coverage within seven (7) calendar days of commissioning:
5.2.1 Workmanship: Guarantee all labor and craftsmanship against defects for one (1) year following final government acceptance.
5.2.2 Manufacturer Coverage: Provide standard manufacturer warranties on all equipment and components.
5.2.3 Task 2 Specific Warranties: The core inverter and battery system must include a minimum of a 1-year warranty on parts and labor and a 5-year warranty on inverters/chargers, remote automatic panels, and battery packs.
5.3 Special Site Requirements (Point Adams).
5.3.1 Site Disruption: Execute work to minimize operational impact on scientific research activities.
5.3.2 Work Hours: Regular hours are 8:00 a.m. to 4:30 p.m., Monday through Friday. Off-hour work requires 24-hour advance notice to the COR.
5.3.3 Housekeeping: Do not allow construction waste to accumulate; haul away debris daily for legal disposal at contractor expense.
6.0 Deliverables. All deliverables shall be submitted in accordance with the aligned section references below:
Task Reference Description Deliverable
Reference Due Date PDF
General OSHA Safety Plan Section 5.1 Thirty (30) CD after NTP General Project Schedule (Gantt Chart) Section 5.1 Thirty (30) CD after NTP General Product Substitution Requests Section 5.1 Allow Seven (7) Days to review Task 1 Utility Service Upgrade Work Plan Section 4.1 Thirty (30) CD after NTP Task 2 Inverters & Battery System Work Plan Section 4.1 Thirty (30) CD after NTP Task 3 Solar Panels Work Plan (Optional Task) Section 4.1 Thirty (30) CD after NTP
General Testing & Commissioning Report Section 4.3 Seven (7) CD after completion of testing General System Training & Attendance Logs Section 4.3 Seven (7) CD after training completion General Component & Equipment Warranties Section 5.2 Seven (7) CD after commissioning General As-Built Drawings (PDF & AutoCAD) Section 4.3 Seven (7) CD after hard-copy approval General Operation & Maintenance (O&M) Manuals Section 4.3 Seven (7) CD after commissioning
7.0 Contact Information
7.1 Contracting Officer Representative (COR):
Thanh Minh Trinh, P.E.
National Marine Fisheries Service/NWFSC 2725 Montlake Blvd E., Seattle, WA 98112 Office: 206-860-6798. Cell: 206-310-5468 Email: thanh.m.trinh@noaa.gov
8.0 Attachment
8.1 Point Adams Electrical Specifications (Attached)
9.0 Place of Performance: Point Adams Research Station, 520 Heceta Place, Hammond, OR 97121.
10.0 Period of Performance (POP):
10.1 Core Scope (Tasks 1 & 2): Complete all work within 180 calendar days following issuance of Notice to Proceed (NTP).
10.2 Optional Scope (Task 3): Option may be exercised by the Government at any time during the active period of performance.
-----------------------End of SOW----------------------mailto:thanh.m.trinh@noaa.gov
EXHIBIT A
Figure 8.1 - Point Adams New Electrical Service Layout
Figure 8.2 - Point Adams New Backup Inverter System
Figure 1 – Site Plan Empty 4-inch SCH40 in Red Line
File details come from the government source that posted it. Updated .