This document is Amendment Number 0006 to Solicitation 1305M326Q0262, issued by the National Weather Service (WAD-SAP) located in Boulder, Colorado, effective June 22, 2026.

The solicitation concerns preventive maintenance services for two emergency backup generators: a natural gas-fueled Cummins generator located at South Burlington, Vermont (Airport Location) and a diesel-fueled Kohler generator located at Colchester, Vermont (Camp Johnson Location, a military installation). The contractor must provide quarterly preventive maintenance visits and annual State of Vermont safety inspections compliant with NFPA 110 and NFPA 70 standards. Maintenance activities include fluid checks, filter replacements (per manufacturer specifications), visual inspections, and 30-minute generator load tests through the automatic transfer switch (ATS). The contractor's technicians must be licensed/certified for the specific equipment type and fuel type and possess appropriate electrician's licenses. Annual inspections may be conducted during any quarterly maintenance visit if timelines and state requirements are met. The South Burlington location permits direct vehicle access with locked generator access doors; the Camp Johnson location requires National Weather Service personnel escort due to military installation security protocols and is housed in an alarmed, locked building. Quotes must be received by 10:00 AM MDT on Wednesday, August 19, 2026. Previous amendment versions (0001 through 0005) extended quote due dates while the Statement of Work underwent revisions for clarification; contractors must reference the current ATTACHMENT 1 STATEMENT OF WORK_REVISED_081326 and disregard prior versions, as non-responsive quotes may be excluded from evaluation without notification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

KERRI COFFEY

See continuation page

WAD-SAP

325 BROADWAY, SOU6

BOULDER CO 80305

WAD-SAP-B

1305M326Q0262

06/22/2026

06/22/2026

1 7

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

1305M326Q0262/0006

AMENDMENT NUMBER 0006 (08/13/2026):

THE STATEMENT OF WORK HAS BEEN UPDATED.

QUOTERS SHOULD DISREGARD ANY PREVIOUS VERSIONS

OF ATTACHMENT 1 STATEMENT OF WORK. QUOTERS

SHOULD REFERENCE ATTACHMENT 1 STATEMENT OF

WORK_REVISED_081326.

QUOTES RECEIVED THAT ARE NOT RESPONSIVE TO

ATTACHMENT 1 STATEMENT OF WORK_REVISED_081326

MAY BE EXCLUDED FROM EVALUATION WITHOUT

NOTIFICATION TO THE QUOTER.

QUOTES ARE REQUIRED TO BE RECEIVED NO LATER

THAN 10:00AM MDT ON WEDNESDAY, AUGUST 19,

2026.

VENDOR QUESTIONS

1) The Statement of Work states that the contractor is to complete the “State of VT

Inspection” for both the Cummins generator and the Kohler generator. Can the Government please clarify what specific State of Vermont inspection is being referenced?

RESPONSE:

Commercial and municipal emergency units require annual state inspections to meet NFPA

110 and NFPA 70 rules. Complete Annual State of

Vermont Safety Inspection for both the Cummins generator and Kohler generator per NFPA rules.

The Contractor shall obtain the State of

Vermont’s generator inspection information and requirements at the Official Vermont Government website.

2) Is there a specific State of Vermont form, checklist, inspection certificate, testing record, or agency-required document that must be completed and submitted for each generator?

RESPONSE: There is no State of

Vermont-specific form for the preventive maintenance. However, Commercial and municipal emergency units require annual state inspections to meet NFPA 110 and NFPA 70 rules.

Complete Annual State of Vermont Safety

Continued...

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

Inspection for both the Cummins generator and

Kohler generator per NFPA rules. The Contractor shall obtain the State of Vermont’s generator inspection information and requirements at the

Official Vermont Government website.

3) Does the State of Vermont inspection require the technician or company performing the inspection to hold a specific Vermont license, certification, TQP credential, fire-safety qualification, or other state-recognized credential?

RESPONSE: The Contractor’s technicians and personnel performing the work shall be licensed/certified on the specific type of equipment (e.g., natural gas, diesel) and/or hold the appropriate level of electrician's license as required and experienced in servicing generators.

4) Should the State of Vermont inspection be completed once annually during the major preventive maintenance visit, or is it required during each quarterly preventive maintenance visit?

RESPONSE: The annual inspection may be conducted during a quarterly preventive maintenance visit as long as the inspection meets timelines and the other requirements by the State of Vermont.

5) The Statement of Work requires the generator to run for 30 minutes under load. Is a 30-minute generator run/load test through the

ATS acceptable, provided utility power is not intentionally interrupted and the service report documents the run time, operating readings, and findings?

RESPONSE: Yes, a 30-minute generator run/load test through the ATS is acceptable, provided it is documented on the annual and quarterly service reports.

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

6) The Statement of Work includes oil and filter change in the maintenance checklist.

Should oil and filter changes be performed once annually during the major preventive maintenance visit, or during every quarterly preventive maintenance visit?

RESPONSE: Replace in accordance with the

Cummins and Kohler Service Manuals for the specific generator requirements for oil and filter changes and respective intervals.

7) The Statement of Work states that belts and hoses are to be replaced as needed. Should replacement parts, belts, hoses, coolant, and corrective repairs be included in the firm-fixed quarterly preventive maintenance price, or should those items be identified during PM and quoted separately for Government approval? Is the expectation to have belts and hoses on hand when we do each quarterly service? Are the belts and hoses to be immediately replace if needed, without the need for an approved repair estimate?

RESPONSE: The requirement to replace belts and hoses has been removed from the Statement of

Work_REVISED_081326.

8) What is the fuel type for each generator—liquid propane, natural gas, or diesel?

RESPONSE: South Burlington, VT - Airport

Location uses natural gas (Cummins) and the

Colchester, VT - Camp Johnson Location uses diesel (Kohler).

9) Are the generators located at ground level with direct drive-up access for service vehicles

RESPONSE: South Burlington, VT - Airport

Location (Cummins): Yes. The Colchester, VT -

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

Camp Johnson Location (Kohler): Yes, but it is on a military installation which will require a

National Weather Service personnel escort for security reasons.

10) Are any generators located within secured, gated, locked, or keyed-access areas

RESPONSE: South Burlington, VT - Airport

Location (Cummins): No, but the generator access doors are locked. The Colchester, VT -

Camp Johnson Location (Kohler): Yes, it is on a military installation which will require a

National Weather Service personnel escort for security reasons and the small building that the generator is located in is also alarmed and locked.

11) Are any of the generators located on a rooftop or inside a building or enclosed mechanical space

RESPONSE: South Burlington, VT - Airport

Location (Cummins): No. The Colchester, VT -

Camp Johnson Location (Kohler): Yes, it is on a military installation which will require a

National Weather Service personnel escort for security reasons and the small building that the generator is located in is also alarmed and locked.

12) Are photographs of each generator, including the nameplate, access route, and surrounding work area, available for review?

RESPONSE: The manufacturers' nameplates are included in Attachment 1 of the Statement of

Work_REVISED_081626. It is recommended that vendors make site visits to view geographical areas.

NO OTHER CHANGES.

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

AMENDMENT NUMBER 0005 (08/03/2026):

ATTACHMENT 1 STATEMENT OF WORK WILL BE REVISED

IN ORDER TO PROVIDE FURTHER CLARIFICATION AND

WILL BE POSTED AT SAM.GOV ONCE IT IS READY. THE

QUOTE DUE DATE HAS BEEN EXTENDED AND WILL BE

EXTENDED AGAIN, IF NEEDED, BASED ON WHEN THE

REVISED ATTACHMENT 1 STATEMENT OF WORK IS

POSTED.

QUOTES ARE REQUIRED TO BE RECEIVED NO LATER

THAN 10:00AM MDT ON THURSDAY, AUGUST 13, 2026.

NO OTHER CHANGES.

AMENDMENT NUMBER 0004 (07/28/2026):

ATTACHMENT 1 STATEMENT OF WORK WILL BE REVISED

IN ORDER TO PROVIDE FURTHER CLARIFICATION AND

WILL BE POSTED AT SAM.GOV ONCE IT IS READY. THE

QUOTE DUE DATE HAS BEEN EXTENDED AND WILL BE

EXTENDED AGAIN, IF NEEDED, BASED ON WHEN THE

REVISED ATTACHMENT 1 STATEMENT OF WORK IS

POSTED.

QUOTES ARE REQUIRED TO BE RECEIVED NO LATER

THAN 10:00AM MDT ON THURSDAY, AUGUST 6, 2026.

NO OTHER CHANGES.

AMENDMENT NUMBER 0003 (07/15/2026):

ATTACHMENT 1 STATEMENT OF WORK WILL BE REVISED

IN ORDER TO PROVIDE FURTHER CLARIFICATION AND

WILL BE POSTED AT SAM.GOV ONCE IT IS READY. THE

QUOTE DUE DATE HAS BEEN EXTENDED AND WILL BE

EXTENDED AGAIN, IF NEEDED, BASED ON WHEN THE

REVISED ATTACHMENT 1 STATEMENT OF WORK IS

POSTED.

QUOTES ARE REQUIRED TO BE RECEIVED NO LATER

THAN 10:00AM MDT ON WEDNESDAY, JULY 29, 2026.

NO OTHER CHANGES.

AMENDMENT NUMBER 0002 (07/02/2026):

ATTACHMENT 1 Statement of Work WILL BE REVISED

IN ORDER TO PROVIDE FURTHER CLARIFICATION AND

WILL BE POSTED AT SAM.GOV THE WEEK OF JULY 6,

2026; THEREFORE, THE QUOTE DUE DATE HAS BEEN

EXTENDED.

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

QUOTES ARE REQUIRED TO BE RECEIVED NO LATER

THAN 10:00AM MDT ON THURSDAY, JULY 16, 2026.

NO OTHER CHANGES.

AMENDMENT NUMBER 0001 (06/29/2026):

ATTACHMENT 1 Statement of Work WILL BE REVISED

IN ORDER TO PROVIDE FURTHER CLARIFICATION AND

WILL BE POSTED AT SAM.GOV ON JUNE 30, 2026;

THEREFORE, THE QUOTE DUE DATE HAS BEEN

EXTENDED.

QUOTES ARE REQUIRED TO BE RECEIVED NO LATER

THAN 10:00AM MDT ON TUESDAY, JULY 7, 2026.

NO OTHER CHANGES.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .