Attachment_1_-_Statement_of_Work_-_Manchester_80-ton_Chiller_Replacement_with_Exhibit.pdf

PDF 860 KB Posted

Attached to
80-ton Chiller Replacement, Port Orchard, WA
Solicitation number
1305M326Q0175
Issued by

About this file

This is a Statement of Work for the National Oceanic and Atmospheric Administration (NOAA), National Marine Fisheries Service (NMFS), Northwest Fisheries Science Center (NWFSC) located in Manchester, Washington.

The contractor shall remove an existing Century 80-ton chiller (installed in 2005, R22 refrigerant) and install a new air-cooled 80-ton chiller that maintains equivalent performance using existing infrastructure. The new chiller must be corrosion-resistant for the marine/coastal environment with copper tubes, aluminum fins, hermetically sealed scroll-type compressors, galvanized steel frame with powder-coat finish, and be constructed per UL 1995 and NEC standards with AHRI 550/590 & 551/591 ratings and ANSI/ASHRAE 15 compliance. The new system shall operate in ambient temperatures from –18°C to 46°C, integrate with the existing 3000-gallon glycol tank (20–25% propylene glycol), and utilize existing seawater heat exchangers from Clam Bay providing two recirculating loops (Broodstock: 160 GPM at 5°C; Hatchery: 50 GPM at 4°C). The basis of design is a TRANE Model CGAM air-cooled chiller or approved equal, with single-point 3-phase 480VAC electrical service, BACnet-ready DDC components, and EPA-approved low-GWP refrigerant (e.g., R32 or equivalent).

Required deliverables include a detailed work plan (due 30 calendar days after Notice to Proceed), project schedule (7 days prior to start), OSHA-compliant safety plan, product substitution requests, commissioning report, training records within 5 days post-commissioning, one-year labor and craftsmanship warranty, as-built drawings (2 hard copies, 1 PDF, 1 CAD file), and operation & maintenance manual (2 hard copies, 1 PDF) prior to acceptance. Work shall be completed as soon as possible after NTP during standard campus hours (Monday–Friday, 7:00 AM–4:00 PM), with 24-hour advanced notice required for work outside these hours. Daily cleanup and debris removal at contractor expense are required. Points of contact include Thanh Minh Trinh (Contracting Officer Representative) and Shawn Katz (Task Monitor at Manchester Research Station).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work National Oceanic and Atmospheric Administration (NOAA)

National Marine Fisheries Service (NMFS) Northwest Fisheries Science Center (NWFSC)

Manchester 80-Ton Chiller Replacement

1.0 ORGANIZATION. The Northwest Fisheries Science Center (NWFSC) is a marine research organization owned and operated by the U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), National Marine Fisheries Service (NMFS). NWFSC has five

(5) major campuses located in Washington and Oregon with its regional headquarters located in Seattle, WA.

2.0 PROJECT LOCATION. The project described in this Statement of Work (SOW) is located at the Manchester Research Station located at 7305 Beach Drive, Port Orchard, WA 98366. See Figure 1 of Exhibit A.

3.0 REQUIRED SERVICES. The contractor shall provide all labor, materials, tools, equipment, supervision, and incidentals to remove the existing Century 80-ton chiller and install a new air-cooled 80-ton chiller. The new system shall maintain equivalent performance using existing infrastructure, including glycol tank, pumps, piping, concrete pad, electrical service, and seawater heat exchangers. All work shall meet applicable federal, state, and local requirements. If none exists, all work shall meet industry standards.

3.1 TASK 1. 80-TON CHILLER REPLACEMENT.

3.1.1 Existing Chiller Profile (see Figure 2 of Exhibit A).

3.1.1.1 Century 80-ton unit installed 2005, R22 refrigerant (ODS, no longer serviceable).

3.1.1.2 Electrical: 3-phase, 480VAC, 60 Hz (see Figure 5).

3.1.1.3 Concrete pad: 15’ x 30’, in good condition.

3.1.1.4 Connected to 3000-gal glycol tank (20–25% propylene glycol).

3.1.1.5 Glycol pump: 3 HP, 3-phase, 240VAC, 140 GPM.

3.1.1.6 Two seawater heat exchanger loops: 210 GPM total, temperatures 4–5°C.

3.1.1.7 Figures 3 & 4 in Exhibit A provide schematics and specifications.

3.1.2 Operating Environment

3.1.2.1 Ambient Air: –18°C to 46°C (0–115°F)

3.1.2.2 Seawater Source: Clam Bay, adjacent to facility

3.1.2.2.1 Seasonal temperature: 8-15°C (46-59°F)

3.1.2.2.2 Two recirculating loops (Broodstock: 160 GPM at 5°C; Hatchery: 50 GPM at 4°C)

3.1.2.2.3 20% make-up water for both loops

3.1.2.3 Glycol Loop: 3000-gal tank, 20–25% food-grade propylene glycol, 140 GPM flow, maintained –2°C to –1°C (28–30°F)

3.1.3 New Chiller Requirements

3.1.3.1 Capacity & Performance: Match existing cooling of two seawater loops (210 GPM total) via existing 3000-gal glycol tank.

3.1.3.2 Ambient Conditions: Operate in –18°C to 46°C (0–115°F).

3.1.3.3 Materials: Corrosion-resistant for marine/coastal environment.

3.1.3.4 Condenser Coils: Copper tubes, aluminum fins, corrosion-resistant epoxy coating.

3.1.3.5 Compressors: Hermetically sealed scroll type, with crankcase heaters and overload protection.

3.1.3.6 Frame: Heavy-gauge galvanized steel with powder-coat finish.

3.1.3.7 Standards: Constructed per UL 1995 and NEC; rated per AHRI 550/590 & 551/591;

ANSI/ASHRAE 15 compliance.

3.1.3.8 Electrical & Controls: Single-point 3-phase 480VAC; BACnet-ready DDC components.

3.1.3.9 Refrigerant: Low-GWP, EPA-approved (e.g., R32 or equivalent).

3.1.3.10 Basis of Design: TRANE Model CGAM air-cooled chiller, or approved equal (see Figure 4 of Exhibit A).

3.1.4 Work Plan. The contractor shall submit a detailed work plan for NWFSC review and approval prior to beginning fieldwork, including:

3.1.4.1 Project schedule, milestones, and coordination plan.

3.1.4.2 Removal and disposal of existing chiller and refrigerant.

3.1.4.3 Installation plan using existing mechanical systems and electrical service.

3.1.4.4 Verification of system performance as specified in 3.1.3.

3.1.5 Construction & Installation

3.1.5.1 Provide all labor, materials, tools, and equipment to install the approved chiller system.

3.1.5.2 Protect existing structures, piping, and equipment during installation.

3.1.5.3 Maintain work area free of debris; daily cleanup required.

3.1.5.4 Secure all openings and protect against weather intrusion.

3.1.6 Testing & Commissioning

3.1.6.1 Manufacturer-certified technician shall test and commission the system.

3.1.6.2 Provide commissioning report demonstrating system performance per 3.1.3.

3.1.7 Training

3.1.7.1 Provide NWFSC personnel training on system operation and preventive maintenance within 5 working days after commissioning.

3.1.7.2 Submit training records to NWFSC.

3.1.8 Warranty

3.1.8.1 Provide one-year labor and craftsmanship warranty.

3.1.8.2 Register manufacturer warranties for equipment and provide documentation to NWFSC.

3.1.9 As-Built Drawings

3.1.9.1 Submit 2 hard copies, 1 PDF, and 1 CAD file of all electrical, mechanical, and controls drawings.

3.1.10 Operation & Maintenance Manual

3.1.10.1 Submit 2 hard copies and 1 PDF of complete O&M manual.

4.0 DELIVERABLES.

Task Deliverable Due Date Notes Safety Plan OSHA-compliant plan 30 CD after NTP Prior to fieldwork Project Schedule Detailed schedule 7 days prior to start Updated weekly Product Substitution Requests Submittals for approval 7 days review Prior to procurement Work Plan Detailed installation plan 30 CD after NTP Must be approved before fieldwork Removal of Existing Chiller Completion Per approved plan Includes refrigerant disposal New Chiller Installation Completion Per approved plan Must meet specifications Testing & Commissioning Certified report Before turnover Must confirm performance Training Training records Within 5 days post-commissioning Operations & maintenance

As-Built Drawings 2 hard, 1 PDF, 1 CAD Prior to acceptance All system components O&M Manual 2 hard, 1 PDF Prior to acceptance Full operations & maintenance

5.0 GENERAL REQUIREMENTS

5.1.1 Safety & Coordination

5.1.1.1 Contractor shall maintain a safe work environment per OSHA and NWFSC requirements.

5.1.1.2 Coordinate schedule and weekly progress updates with NWFSC POC.

5.1.2 Site Protection

5.1.2.1 Minimize disruption to facility operations and research activities.

5.1.2.2 Maintain site cleanliness and secure openings daily.

5.1.3 Debris Management

5.1.3.1 Remove all debris daily; legally dispose at contractor expense.

5.1.4 Work Hours

5.1.4.1 Standard campus hours are Monday thru Friday from 7:00 AM to 4:00 PM. Staff will be on-site during these business hours. The contractor will not be able to work on Federal Holidays.

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=2026

5.1.4.2 Work outside standard hours requires 24-hour advanced notice and approval from the COR.

6.0 NOAA NWFSC POINT OF CONTACTS

6.1 Contracting Officer Representative (COR):

Thanh Minh Trinh, P.E.

NOAA/National Marine Fisheries Service/NWFSC 2725 Montlake Blvd E., Seattle, WA 98112 Office: 206-860-6798. Cell: 206-310-5468 Email: thanh.m.trinh@noaa.gov

6.2 Task Monitor (TM) at Manchester Research Station:

Shawn Katz Office: 360-871-8306. Cell: 206-798-0919.

Email: shawn.katz@noaa.gov

7.0 PERIOD OF PERFORMANCE

Task Task Description Estimated Completion Date 1 Manchester 80-T Chiller Replacement As Soon As Possible after NTP (Notice to Proceed)

END OF SOW

EXHIBIT A

Figure 2 - Existing Century 80-Ton Chiller

Figure 1 - Manchester General Site Layout

Figure 4 - Manchester 80-Ton Chiller System

Figure 5 - TRANE Model CGAM

Figure 5 – Existing 80-T Chiller and Electrical Power System

Figure 3 - Manchester 80-Ton Chiller System