Attachment_1_-_Statement_of_Work_-_Manchester_80-ton_Chiller_(14_May_2026)_0001.pdf
PDF 545 KB Posted
- Attached to
- 80-ton Chiller Replacement, Port Orchard, WA
- Solicitation number
- 1305M326Q0175
About this file
This is a Statement of Work (SOW) issued by the National Oceanic and Atmospheric Administration (NOAA), National Marine Fisheries Service (NMFS), Northwest Fisheries Science Center (NWFSC) for the replacement of an 80-ton chiller at the Manchester Research Station in Port Orchard, Washington. The contractor must remove the existing Century 80-ton chiller (installed 2005, using R22 refrigerant) and install a new air-cooled 80-ton chiller that maintains equivalent performance using existing infrastructure including a 3,000-gallon glycol tank, pumps, piping, concrete pad, electrical service, and seawater heat exchangers. The project location is at 7305 Beach Drive, Port Orchard, WA 98366, and the estimated completion date is 270 days after Notice to Proceed (NTP).
The new chiller must meet specific performance requirements: 80-ton minimum capacity, full cooling capacity at 95°F ambient dry-bulb temperature, 25% propylene glycol solution, 28°F leaving and 32°F entering glycol temperature, and comply with UL 1995, NEC, AHRI 550/590 & 551/591, and ANSI/ASHRAE 15 standards. The system must be rated for 3-phase 480VAC 60Hz operation in a marine/coastal environment with ambient temperatures ranging from minus 18°C to 46°C. The chiller must use hermetically sealed scroll-type compressors with crankcase heaters, corrosion-resistant copper tubes with aluminum fins and epoxy coating, galvanized steel frame with powder-coat finish, and low-GWP, EPA-approved refrigerant (R32 or equivalent). Controls must include BACnet-compatible interface, digital display, alarm diagnostics, leaving fluid temperature control, freeze protection, low ambient temperature controls, and automatic lead/lag compressor staging. The contractor must provide a detailed work plan for NWFSC approval 30 calendar days after NTP, submit a safety plan, project schedule, and product substitution requests before procurement. Deliverables include removal of the existing chiller with proper EPA-compliant refrigerant disposal, installation and testing by a manufacturer-certified technician, a commissioning report, training for NWFSC personnel within five working days post-commissioning, one-year labor and craftsmanship warranty, as-built drawings (2 hard copies, 1 PDF, 1 CAD file), and an Operations & Maintenance manual (2 hard copies, 1 PDF). Standard work hours are 8:00 a.m. to 4:30 p.m., Monday through Friday, with 24-hour notice required for outside-hours work. The Contracting Officer Representative is Thanh Minh Trinh, P.E. (thanh.m.trinh@noaa.gov, 206-860-6798), and the Task Monitor at Manchester Research Station is Shawn Katz (shawn.katz@noaa.gov, 360-871-8306).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work National Oceanic and Atmospheric Administration (NOAA)
National Marine Fisheries Service (NMFS) Northwest Fisheries Science Center (NWFSC)
Manchester 80-Ton Chiller Replacement
1.0 ORGANIZATION. The Northwest Fisheries Science Center (NWFSC) is a marine research organization owned and operated by the U.S. Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), National Marine Fisheries Service (NMFS). NWFSC has five
(5) major campuses located in Washington and Oregon with its regional headquarters located in Seattle, WA.
2.0 PROJECT LOCATION. The project described in this Statement of Work (SOW) is located at the Manchester Research Station located at 7305 Beach Drive, Port Orchard, WA 98366. See Figure 1 of Exhibit A.
3.0 REQUIRED SERVICES. The contractor shall provide all labor, materials, tools, equipment, supervision, and incidentals to remove the existing Century 80-ton chiller and install a new air-cooled 80-ton chiller. The new system shall maintain equivalent performance using existing infrastructure, including glycol tank, pumps, piping, concrete pad, electrical service, and seawater heat exchangers. All work shall meet applicable federal, state, and local requirements. If none exists, all work shall meet industry standards.
3.1 TASK 1. 80-TON CHILLER REPLACEMENT.
3.1.1 Existing Chiller Profile (see Figure 2 of Exhibit A).
3.1.1.1 Century 80-ton unit installed 2005, R22 refrigerant (ODS, no longer serviceable).
3.1.1.2 Electrical: 3-phase, 480VAC, 60 Hz (see Figure 4).
3.1.1.3 Concrete pad: 15’ x 30’, in good condition.
3.1.1.4 Connected to 3000-gal glycol tank (20–25% propylene glycol).
3.1.1.5 Glycol pump: 3 HP, 3-phase, 240VAC, 140 GPM.
3.1.1.6 Two seawater heat exchanger loops: 210 GPM total, temperatures 4–5°C.
3.1.1.7 Figures 3 & 4 in Exhibit A provide schematics and specifications.
3.1.2 Site Operating Environment
3.1.2.1 Ambient Conditions: The chiller shall be capable of reliable operation within the following ambient outdoor temperature range:
3.1.2.1.1 Minus 18°C to 46°C (0°F to 115°F)
3.1.2.1.2 Unit shall provide full cooling capacity at: 35°C (95°F) ambient dry-bulb temperature.
3.1.2.2 Seawater Source: The installation location is within a marine/coastal environment adjacent to Clam Bay. Equipment shall be suitable for corrosive coastal exposure.
3.1.2.2.1 Seasonal temperature: 8-15°C (46-59°F)
3.1.2.2.2 Two (2) recirculating loops (Broodstock: 160 GPM at 5°C; Hatchery: 50 GPM at 4°C)
3.1.2.2.3 Approximately 20% make-up water for both loops
3.1.2.3 Glycol Loop: 3000-gal tank, 20–25% food-grade propylene glycol, 140 GPM flow, maintained –2°C to –1°C (28–30°F)
3.1.3 New Chiller Requirements
3.1.3.1 Capacity & Performance: Match existing cooling of two seawater loops (210 GPM total) via existing 3000-gal glycol tank.
3.1.3.2 Nominal Capacity: 80 tons minimum
3.1.3.3 Full Cooling Capacity available at:
3.1.3.3.1 95°F ambient dry bulb
3.1.3.3.2 25% propylene glycol solution
3.1.3.3.3 28°F leaving glycol temperature
3.1.3.3.4 32°F entering glycol temperature
3.1.3.4 Materials: Corrosion-resistant for marine/coastal environment.
3.1.3.5 Condenser Coils: Copper tubes, aluminum fins, corrosion-resistant epoxy coating.
3.1.3.6 Compressors: Hermetically sealed scroll type, with crankcase heaters and overload protection.
3.1.3.7 Frame: Heavy-gauge galvanized steel with powder-coat finish.
3.1.3.8 Standards: Constructed per UL 1995 and NEC; rated per AHRI 550/590 & 551/591;
ANSI/ASHRAE 15 compliance.
3.1.3.9 Electrical Power: 3-phase, 480VAC, 60 Hz.
3.1.3.10 Controls shall meet the following requirements:
3.1.3.10.1 BACnet-compatible interface
3.1.3.10.2 Digital display
3.1.3.10.3 Alarm diagnostics
3.1.3.10.4 Leaving fluid temperature control
3.1.3.10.5 Freeze protection
3.1.3.10.6 Low ambient temperature controls
3.1.3.10.7 Automatic lead/lag compressor staging.
3.1.3.11 Refrigerant: Low-GWP, EPA-approved (e.g., R32 or equivalent).
3.1.4 Work Plan. The contractor shall submit a detailed work plan for NWFSC review and approval prior to beginning fieldwork, including:
3.1.4.1 Project schedule, milestones, and coordination plan.
3.1.4.2 Removal and disposal of existing chiller
3.1.4.3 Recovery and disposal of existing refrigerant in accordance with EPA regulations
3.1.4.4 Demolition and disposal of associated materials
3.1.4.5 Rigging and crane services
3.1.4.6 Delivery and installation of new chiller
3.1.4.7 Reconnection to existing piping systems
3.1.4.8 Electrical reconnection
3.1.4.9 Control integration
3.1.4.10 Glycol draining and refill as required
3.1.4.11 Pressure testing
3.1.4.12 Startup and commissioning
3.1.4.13 Operator training
3.1.4.14 Final cleanup
3.1.4.15 Verification of system performance as specified in 3.1.3.
3.1.5 Construction & Installation
3.1.5.1 Provide all labor, materials, tools, and equipment to install the approved chiller system.
3.1.5.2 Protect existing structures, piping, and equipment during installation.
Charles Kendall Highlight
Charles Kendall Highlight
3.1.5.3 Maintain work area free of debris; daily cleanup required.
3.1.5.4 Secure all openings and protect against weather intrusion.
3.1.6 Testing & Commissioning
3.1.6.1 Manufacturer-certified technician shall test and commission the system.
3.1.6.2 Provide commissioning report demonstrating system performance per 3.1.3.
3.1.7 Training
3.1.7.1 Provide NWFSC personnel training on system operation and preventive maintenance within 5 working days after commissioning.
3.1.7.2 Submit training records to NWFSC.
3.1.8 Warranty
3.1.8.1 Provide one-year labor and craftsmanship warranty.
3.1.8.2 Register manufacturer warranties for equipment and provide documentation to NWFSC.
3.1.9 As-Built Drawings
3.1.9.1 Submit 2 hard copies, 1 PDF, and 1 CAD file of all electrical, mechanical, and controls drawings.
3.1.10 Operation & Maintenance Manual
3.1.10.1 Submit 2 hard copies and 1 PDF of complete O&M manual.
4.0 DELIVERABLES.
Task Deliverable Due Date Notes Safety Plan OSHA-compliant plan 30 CD after NTP Prior to fieldwork Project Schedule Detailed schedule 7 days prior to start Updated weekly Product Substitution Requests Submittals for approval 7 days review Prior to procurement Work Plan Detailed installation plan 30 CD after NTP Must be approved before fieldwork Removal of Existing Chiller Completion Per approved plan Includes refrigerant disposal New Chiller Installation Completion Per approved plan Must meet specifications Testing & Commissioning Certified report Before turnover Must confirm performance Training Training records Within 5 days post-commissioning Operations & maintenance
As-Built Drawings 2 hard, 1 PDF, 1 CAD Prior to acceptance All system components O&M Manual 2 hard, 1 PDF Prior to acceptance Full operations & maintenance
5.0 GENERAL REQUIREMENTS
5.1.1 Safety & Coordination
5.1.1.1 Contractor shall maintain a safe work environment per OSHA and NWFSC requirements.
5.1.1.2 Coordinate schedule and weekly progress updates with NWFSC POC.
5.1.2 Site Protection
5.1.2.1 Minimize disruption to facility operations and research activities.
5.1.2.2 Maintain site cleanliness and secure openings daily.
5.1.3 Debris Management
5.1.3.1 Remove all debris daily; legally dispose at contractor expense.
5.1.4 Work Hours
5.1.4.1 Standard: 8:00 a.m. – 4:30 p.m., Mon–Fri.
5.1.4.2 Work outside standard hours requires 24-hour notice to COR.
6.0 NOAA NWFSC POINT OF CONTACTS
6.1 Contracting Officer Representative (COR):
Thanh Minh Trinh, P.E.
NOAA/National Marine Fisheries Service/NWFSC 2725 Montlake Blvd E., Seattle, WA 98112 Office: 206-860-6798. Cell: 206-310-5468 Email: thanh.m.trinh@noaa.gov
6.2 Task Monitor (TM) at Manchester Research Station:
Shawn Katz Office: 360-871-8306. Cell: 206-798-0919.
Email: shawn.katz@noaa.gov
7.0 PERIOD OF PERFORMANCE
Task Task Description Estimated Completion Date
1 Manchester 80-T Chiller Replacement 270 days after NTP (Notice to Proceed)
END OF SOW
mailto:thanh.m.trinh@noaa.gov
EXHIBIT A
Figure 2 - Existing Century 80-Ton Chiller
Figure 1 - Manchester General Site Layout
EXHIBIT A
Figure 3 - Manchester 80-Ton Chiller System
Figure 4 – Existing 80-T Chiller and Electrical Power System
Figure 3 Manchester 80 Ton Chiller System