This document is a Pricing Schedule for a Request for Quote (RFQ) for the NEXRAD Signal Processor Interface Panel (SPIP) for the National Oceanic and Atmospheric Administration (NOAA).
The RFQ is for a firm-fixed price contract with a 5-year period of performance from 9/6/2024 to 9/5/2029, consisting of 5 ordering periods. The quantities provided are estimates only. The offeror is required to complete the pricing schedule with unit prices for the SPIPs to be delivered in each ordering period, as well as provide proposed delivery dates for the First Article Testing (FAT) and production quantities. The Grand Total for the 5-year period is $0.00. Offerors must submit their proposed pricing in the format provided in the Pricing Schedule.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_1305M224Q0239_Amd_0002.pdf | ||
| 2_Schedule_of_Deliverables_Amendment_0001_0001.docx | DOCX document | |
| Sol_1305M224Q0239_Amd_0001.pdf | ||
| Instructions_Amendment_0001_0001.docx | DOCX document | |
| SOW_Amendment_0001_0001.docx | DOCX document | |
| 1_Statement_of_Work-v2.docx | DOCX document | |
| B-1_Pricing_Schedule_Attachment-v2.xlsx | XLSX spreadsheet | |
| Instructions_for_Shipment.pdf | ||
| Sol_1305M224Q0239.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPIP Pricing Schedule
| PRICING SCHEDULE - The offeror shall complete and return the pricing schedule below, or otherwise provide all the pricing elements in the format provided with their quote. For estimating purposes only, please provide your pricing based on an award date of 9/6/2024 through 9/5/2029. The final dates for each ordering period will be included in the award contract. | |
| Period of Performance - 5 Ordering Periods for a Total of 5 Years (No Option years). The quantities are estimates only | |
| NEXRAD Signal Processor Interface Panel (SPIP) | |
| RFQ 1305M224Q0239 - Firm-Fixed Price (FFP) | |
| Grand Total | $0.00 |
AMENDMENT 0001 - Vendor to provide their proposed delivery dates for FAT and Production
CLIN # Item Description Quantity Unit Price Ordering Period 1 9/6/2024 -
| 9/5/2025 | Quantity | Unit Price | Ordering Period 2 |
| 9/6/2025 - 9/5/2026 | Quantity | Unit Price | Ordering Period 3 |
| 9/6/2026 - 9/5/2027 | Quantity | Unit Price | Ordering Period 4 |
| 9/6/2027 - 9/5/2028 | Quantity | Unit Price | Ordering Period 5 |
9/6/2028 - 9/5/2029
| 0001 | For Ordering Period 1 Only: First Article Testing (FAT) 2 Signal Processor Interface Panels (SPIPs), part number 239064, Bill of Material (BOM) and design package - delivery date to be determined (TBD) | 2 | $0.00 | $0.00 | X | X | X | X | X | X | X | X | X | X | X | X | |
| 0001 | Production: 48 SPIPs to be delivered after first article acceptance of CLIN 0001 for Ordering Period 1. | ||||||||||||||||
| Quote the quantities reflected for Ordering Periods 2, 3, 4 & 5 - delivery date to be determined (TBD) | 48 | $0.00 | $0.00 | 10 | $0.00 | $0.00 | 10 | $0.00 | $0.00 | 10 | $0.00 | $0.00 | 1 | $0.00 | $0.00 | ||
| TOTAL | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||||||||
| NOTE: The highlighted cells need to be completed by the offeror and those are the only cells that should be changed. |