PISCES_FY20_DS_Specification_Rev_2_Sept19.pdf
PDF 2 MB Posted
- Attached to
- FY 2020 DOCKSIDE REPAIRS TO NOAA SHIP PISCES
- Solicitation number
- 1305M219RNMAN0049
About this file
TORFP Attachment D.1, Revised per Amendment 0002
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA SHIP PISCES (R 226)
FY2020
DOCKSIDE REPAIRS
DETAIL SPECIFICATION
September, 2019
Marine Engineering Division - MOA2 Marine Operation Center, Atlantic
439 West York Street Norfolk, VA 23510
Stephen Spindler____________ 20 September 2019 Written By Date
NOAA Ship PISCES FY20 Dockside Repairs Rev 2 – September 2019
Table of Contents
1. Scope
2. General Requirements
3. Basic Items
1. ABS Special Survey No. 1
2. Rescue Boat Davit Annual Inspection
3. SSDG Resilient Mount Replacement
4. Ship’s Cranes Refurbishment
5. Annual Fire Inspection
6. Annual Life Raft Inspection
7. Teco-Westinghouse Annual System Groom
8. Aft A-Frame Repairs
9. Main Deck Steel Bulkhead Repairs
10. Bilge / Ballast / Fire Pump Overhaul
11. Miscellaneous Pipe and Habitability Repairs
12. Hydraulic Hose Renewals
13. Centerboard Annual System Groom
14. Refrigeration System Repairs
15. Crane HPU Overhaul
16. Scientific Sea Water System Repairs
17. Scullery Dishwasher Replacement
4. Additional Work
5. Dockside Option Items
1. HVAC Unit Replacement
2. Chill Water Piping Insulation Repairs
3. Gangway Replacement
4. PRC Deck Repairs
5. Miscellaneous Repairs
6. Weather Deck Drain Modifications
7. Ventilation System Repairs
8. Rockwell Drive Cabinet Repairs
9. Circuit Breaker Overhaul
10. Watertight Door Inspection and Repairs
11. Mission UPS Modifications
12. Corrosion Mitigation Repairs
13. Temporary HVAC Repairs
CHANGES (REV 2)
Work Item Deletions: None
Work Item Relocations: None
Work Item Additions:
Item 512 – Corrosion Mitigation
Item 513 – Temporary HVAC Repairs
Work Item Modifications:
Item 3.7 - Added lift pump Teco Part Number to Paragraph 3.7.4.4.4
Item 3.10 - Modified Paragraph 3.10.4.3. Added photo of valve.
Item 3.15 - Modified Paragraph 3.15.4.4 adding photographs of crane HPU pump nameplate data
Item 5.2 - Modified Paragraph 5.2.4.1
Item 5.8 - Modified Paragraphs in Section 5.8.4 to delineate OEM and Prime
Contractor work
CHANGES (REV 1)
Work Item Deletions: None
Work Item Relocations: None
Work Item Additions: None
Work Item Modifications:
General Requirements – Modified Paragraph 2.2.3 for QP-1 requirements and Paragraph
2.2.19
Item 3.2 - Modified Paragraphs 3.2.4.5.9 and 3.2.4.7
Item 3.4 - Modified Paragraph 3.4.4.5 and clarified Paragraphs 3.4.4.8, 3.4.4.10, and 3.4.4.14
Item 3.6 - Added Paragraph 3.6.4.6
Item 3.8 - Modified Paragraph 3.8.4.12 and 3.8.4.6
- Added Paragraph 3.8.4.12.1 and 3.8.4.15
Item 3.9 - Modified Paragraph 3.9.4.12
Item 3.10 - Modified Paragraph 3.10.4.3
Item 3.11 - Added Paragraph 3.11.4.46.3
Item 3.14 - Added Paragraphs 3.14.4.2.3, 3.14.4.3, 3.14.4.7 and modified Paragraph
3.14.4.4.6
Item 3.16 - Modified Paragraph 3.16.4.2
Item 5.4 - Modified Paragraphs 5.4.4.2 and 5.4.4.5
Item 5.7 - Modified Paragraphs 5.7.4.3.3 and 5.7.4.3.4
- Added Paragraphs 5.7.4.8 and 5.7.4.9
Item 5.8 - Modified Paragraphs 5.8.4.2, 5.8.4.3, 5.8.4.5, 5.8.4.6, and 5.8.4.8
Item 5.9 - Modified Paragraphs 5.9.4.3 and 5.9.4.4 removing OEM requirements
Item 5.1 - Deleted the note for Paragraph 5.1.4.1 and modified Paragraph 5.1.5.3.
Item 5.2 - Added Computer Lab to list of excepted spaces in Paragraph 5.2.4.4
Item 5.11 - Modified Paragraph 5.11.4.2
1. SCOPE AND INTENT OF THE DOCKSIDE SHIP REPAIR CONTRACT
These detailed specifications contain requirements for NOAA Ship PISCES (R 226) FY20 Dockside Repairs.
The National Oceanic and Atmospheric Administration (NOAA) operates a fleet of research vessels that supports research and mapping for the National Fisheries Service, National Ocean Service, Office of Atmospheric Research and the National Weather Service, as well as provides support to other Federal agencies. These research missions are time sensitive and therefore the data must be collected at specific times during the sailing season to be meaningful.
At the end of each sailing season the vessels enter a repair period (drydock or dockside) to address repairs that have been previously identified, perform upgrades to mission systems or ship systems that either extend the life of the ship or provide new data collection capabilities or for safer operations of ships systems as well as address any emergent work that would adversely affect the ships ability to safely perform its mission on schedule, while meeting all regulatory body requirements (American Bureau of Shipping and United States Coast Guard) and all habitability requirements, including any that may be required as a result of contracts for personnel to augment ship staff.
2. GENERAL REQUIREMENTS
2.1. References
2.1.1. The following references form a part of these Detailed Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items, which are authorized by the Contracting Officer. All work procedures and all materials shall meet the ABS Rules.
2.1.2. All NOAA Specific References for the Ship / Ship Class are provided for reference only. The Contractor shall independently verify all pertinent information by field investigation (ship check). See Reference 2.1.4.1 for definitions of common shipboard repair work.
2.1.3. General References
2.1.3.1. ABS: American Bureau of Shipping "Rules for Building and Classing Steel Vessels Under 90 Meters in Length"
2.1.3.2. ABS: American Bureau of Shipping “Rules for Survey After Construction”
2.1.3.3. CFR: U. S. Coast Guard "Subchapter F - Marine Engineering", 46 CFR 50 through 46 CFR 64
2.1.3.4. CFR: U. S. Coast Guard "Subchapter J - Electrical Engineering", 46 CFR 110 through 46 CFR 113
2.1.3.5. Oceanographic Research Vessel (ORV)- 46 CFR chapters 188-196
2.1.3.6. Standard: IEEE Std 45-2002, "IEEE Recommended Practice for Electric
Installations on Shipboard"
2.1.4. NOAA Specific References
2.1.4.1. NOAA Standard Specification AMC-000-1H, “General Requirements for
Contract Repair Work on NOAA Ships”
2.1.4.2. NOAA Standard Specification MOC-300-3, “General Requirements for Electrical/ Electronic Items”
2.1.4.3. NOAA Standard Specification MOC-631-2D, “Coating Systems for Steel Surfaces”
2.1.4.4. NOAA Standard Specification AMC-631-4, “Coating Systems for Aluminum Surfaces”
2.1.4.5. Drawing FA02, “General Arrangements”
2.1.4.6. Drawing M283-304-FE41 “Penetration Details”
2.1.4.7. Drawing M283-304-FE43 “Bonding and Grounding Details”
2.1.4.8. Drawing M283-304-FE45 “Electrical Installation Details”
2.1.4.9. Drawing FF04, “Painting Schedule”
2.1.4.10. Drawing M283-304-FF03 “Color Coordination Manual”
2.1.4.11. Drawing SH-081-FM10-Equipment Removal Routes
2.1.5. Frame numbers and space names throughout this specification are derived from ship’s drawings. Equipment changes and space modifications over the ship’s life span may not all be reflected in the referenced drawings. Therefore, Contractors are encouraged to review all referenced drawings and to perform a field inspection of the ship prior to submitting a bid. Copies of drawings and technical manuals not included herein may be made available for review during any scheduled pre-bid inspection and during the performance period. During the pre-bid inspection, Contractors may review available drawings and technical manuals on board ship.
2.2. Requirements:
2.2.1. Contractor shall provide a Project Coordinator or equivalent delegated employee to be onsite at all times Contractor or sub-contractor personnel are working on the vessel. Project Coordinator shall oversee the execution of all ongoing work, including sub-contractor work, and shall serve as a point of contact on the vessel to coordinate between COR, Ship’s Force, Contractor, and sub-contractor personnel.
2.2.2. Unless otherwise stated in these work items, prepare and coat all new steel, disturbed steel, or otherwise required painted surfaces in accordance with References 2.1.4.3 and 2.1.4.4. If no paint system is identified in the item, then apply the appropriate coating system similar to the area being coated as identified in Paragraph 5.2 of Reference 2.1.4.3, except that the top coat shall match the surrounding area.
2.2.3. All ssurface preparation and painting of tanks, voids, and surfaces greater than 50 square feet shall be accomplished by an SSPC QP1 certified painting contractor. All other painting, including touch-ups, painting new pipes, foundations, etc. may be accomplished using a qualified contractor experienced with shipboard painting. All painting required by Item 3.4 “Ship’s Crane Refurbishment” shall be completed by a QP1 certified painting contractor.
2.2.4. Unless specifically stated otherwise in an individual work item, the Contractor shall provide all labor and material, including subcontractors and crane and other services, to accomplish all work called for in the Detailed Specification. All items removed or opened for repair, overhaul, rework, testing, etc., shall be re-installed after the work scope is accomplished.
2.2.5. These Detailed Specifications are a combination of “performance specifications” and “design specifications.” Whenever possible, the Government has provided performance specifications, giving the Contractor the opportunity to accomplish the work requirements as best as he or she sees fit, while providing a fully functional repair and/or equipment/system installation in accordance with all work requirements. When specific details are required, the Government will provide design/detail specifications; this will be more the exception, than the rule.
2.2.6. All new equipment and furnishings purchased by the Contractor for installation on the ship shall be provided with factory supplied technical manuals, or data sheets, complete with parts listings. This documentation shall be turned over to the COR after installation is completed.
2.2.7. On repairs or overhauls of existing equipment, Contractor shall follow Original
Equipment Manufacturer’s (OEM’s) recommendations for parts and service in such a manner that the manufacturer’s warranty on parts and labor is not voided, where the warranty still applies or equivalent warranty is offered. Unless specified elsewhere in the details specification, all replacement parts shall be new parts from the OEM.
2.2.8. Provide manufacturer’s technical representatives where required in the individual work items, to witness and to provide technical guidance during operational testing of equipment and systems. All tests and trials of equipment or systems shall be witnessed by the COR, ABS, and/or USCG as applicable, to ensure compliance with regulatory body requirements to maintain the ship’s ABS class certification, and to complete all requirements of these specifications.
2.2.9. All visual examinations, hydrostatic testing, and non-destructive testing (NDT) shall be in accordance with ABS Rules for Building and Classing Steel Vessels, Survey After Construction 2005, Part 7. All contractors performing NDT and hull gauging shall be certified under the ABS external specialists program.
2.2.10. Provide and maintain a status report of all American Bureau of Shipping (ABS) inspections and technical reviews required by ABS, during the course of this contract, to ensure the ship’s ABS certification requirements are in compliance.
2.2.11. All inspection, test, Quality, and Condition Reports shall be provided to the COR in Adobe Portable Document Format (.pdf).
2.2.12. Maintain a Quality Assurance (QA) TEST AND INSPECTION PLAN applicable to all work items, including all additional work items which are authorized by the Contracting Officer. Update QA TEST AND INSPECTION PLAN weekly and provide a copy to the COR 24-hours prior to the scheduled weekly progress meeting. Include the following minimum information for each work item and additional work item:
2.2.12.1. Specification item and paragraph number
2.2.12.2. Component/Equipment name
2.2.12.3. Test Schedule (Date and time)
2.2.12.4. Test or Inspection description
2.2.12.5. Acceptance Criteria
2.2.13. Quality Assurance Inspection Report
2.2.13.1. Within the first week after the start of the Period of Performance, Contractor shall schedule and hold a meeting on the ship or other acceptable location between ABS, COR, Contractor QA superintendent, Contractor Project Manager / Ship Coordinator, Ship’s CO and Chief Engineer to discuss and schedule all ABS required inspections and surveys. Contractor shall develop a list of all items required for ABS Inspections and provide the list and survey schedule dates to the COR no later than seven (QTY 7) days after the meeting. The survey schedule shall list all initial inspections required by the ABS Surveyor. Throughout the duration of the Contract, the Contractor shall schedule the services of an ABS Surveyor as required by ABS for performing inspections of all new installations, hull modifications, tank inspections, gauging inspections, and load tests. NOAA will pay for all ABS surveys associated with work required by these specifications. The Contractor shall provide a credit for any additional ABS charges associated with rescheduling of surveys and rework surveys which are directly under the control of the Contractor.
2.2.14. Provide a copy of ABS approved welding procedures and maintain a list of currently qualified welders.
2.2.15. For all items that are not direct replacements (unit for unit exchange), Contractor shall weigh all materials and items removed, installed, or relocated on the ship.
Provide a summary report to the COR, similar to the sample table below, indicating the total weight in pounds of the materials and items with a breakdown of their locations by space, deck, frame, distance from centerline, and height off of the deck.
Description Add/Remove Weight Deck Frame P/S Dist off
CL
Ht Abv Dk
2.2.16. In the event fuel is off-loaded, the fuel shall be metered off and on through a filtered, de-watering system. Store removed fuel in clean storage facilities. Treat and circulate fuel stored longer than six (6) weeks to prevent water accumulation and biological growth.
2.2.17. Contractor is responsible for providing necessary electrical power to complete this contract. Ship’s and NOAA pierside electricity supplies shall not be used unless authorized by the COR. Contractor shall ensure temporary power rigged does not block primary accesses/egress routes or interfere with the weathertight boundaries of the ship without the authorization of the COR.
2.2.18. Upon COR authorization, electrical power distribution systems available aboard the ship for Contractor power tools include 480vac via three submersible pump receptacles and 120vac receptacles throughout the ship.
2.2.19. Contractor is responsible for providing temporary sanitary and rest/break services for Contractors. Sink in AMR may be used for cleansing & washing hands and shall be left in as-found conditions.
2.2.20. Contractor is responsible for providing crane services to execute this contract.
Contractor shall not operate Ship’s Cranes.
2.2.21. Ships force will maintain a minimal presence during accomplishment of work to these specifications. Their availability to operate ship’s equipment will be limited with the exception of requirements for fuel transfer and ballasting to accommodate tank work and entry. Unless otherwise specified, provide a minimum of two working days’ prior notice for any equipment operations.
2.2.22. Coordinate with Ships force to operate all new and disturbed machinery for a period sufficient to indicate satisfactory performance, but not less than one hour, after all adjustments and deficiency corrective actions have been made, without further adjustment.
2.2.23. Red-line / As-Built Drawings:
2.2.23.1. The Contractor shall Redline “as-built” drawings for modifications accomplished by these detail specifications.
2.2.23.2. The Contractor shall provide final CAD and PDF Drawings of final “as-built” configuration as required by individual work items. Final “as-built” PDF drawings shall be delivered to the COR in 11x17 black and white format.
2.2.24. Daily Clean-up
2.2.24.1. To the maximum extent practical and in accordance with Reference
2.1.4.1, remove dirt, debris, scrap, supplies, and other materials incident to work from the ship at the end of each work day. Leave the work site "broom clean".
2.2.24.2. If blasting residue or other foreign particles collect on the exterior decks of the ship, remove the residue or particles by COB on Friday of the work week.
Do not sweep or wash the residue or particles through the ship's deck drains unless specifically pre-authorized by the COR.
2.2.24.3. Contractor is responsible for removing and disposing all trash and waste generated by the execution of this contract at the Contractor’s expense in accordance with local, State, and Federal regulations. Contractor shall provide appropriate disposal receptacles to contain and dispose of all generated waste.
2.2.24.4. Contractor shall clean all spaces affected by this specification upon completion of production work and before Dock Trials. Cleaning shall consist of removing all trash, debris, production residue, temporary protective coverings, and mopping all decks to return ship to “as-found” conditions.
Contractor shall also touch-up paint in all affected spaces as needed to return ship to “as-found” conditions.
2.2.25. Engine Room Bilge Cleaning
2.2.25.1. In accordance with the requirements of Reference 2.1.4.1, the Contractor shall pump and properly dispose of all oily water from the engine room bilges and clean bilges as required for hot work. If the Contractor dirties the bilges due to work contained in this statement of work, then the Contractor shall pump empty and clean the bilges. At the completion of all repair contract work, clean the engine room bilges by flushing with a fresh water and detergent solution (to remove all oil and other debris) and pump the bilges dry.
If bilge cleaning is not performed the cost of the bilge cleaning shall be deducted from the contract total.
2.2.26. Daily Safety and Housekeeping Inspection
2.2.26.1. COR will conduct a daily safety and housekeeping inspection of all spaces affected by Contractor work. Contractor shall address or take corrective action on all discrepancies within 4 hours after notification.
2.2.27. Protective Coverings
2.2.27.1. Prior to start of work, install protective coverings as needed to affected spaces to protect the ship, ship systems, and equipment from damage and entry of dust, dirt, grit, sand, and other foreign particles in accordance with the requirements of Reference 2.1.4.1.
2.2.27.2. Prior to starting work on interior spaces, protect the decks and deck coverings from damaging spaces where work is to be performed and through which workers will traverse, as follows:
2.2.27.2.1. Cover the decks and deck coverings with temporarily fitted heavy vinyl, plywood or particle board. Securely tape all edges and joints of the protective covering to prevent movement and to prevent a tripping hazard. Other materials may be used if pre-approved by the COR.
2.2.27.2.2. For decks over which equipment, valves, piping or other materials will be handled, the plywood or particle board must be of sufficient thickness to protect the deck from damage the if the equipment or materials are dropped.
2.2.27.2.3. Maintain the protective coverings in place during the entire contract period. Promptly replace sections which are damaged.
2.2.27.3. Prior to abrasive blasting, or other work operations which create atmospheric contamination on or near the ship, prevent the entry of airborne contaminates.
2.2.27.4. Plug, wrap, blank, cover, or mask openings into the ship as needed.
2.2.27.5. Install industrial foam filter material on the intake and exhaust end of all ventilation systems which will be in use during the blasting operations.
Monitor the air flow through the filters and replace the filters when air flow becomes restricted.
2.2.27.6. Whenever abrasive blasting is performed inside the ship, confine the blast materials to the compartment being blasted.
2.2.27.7. After completing the work, remove and dispose of the protective coverings.
2.2.27.8. Re-establish the condition which existed at the start of the work. It is the responsibility of the Contractor to repair and clean all damage and contamination resulting from failure to provide adequate protection.
2.2.28. Kick-off/Pre-dockside Meeting
2.2.28.1. Unless previously completed after Contract award, on the first day of the
Period of Performance and before commencing work on the ship the Contractor shall host a kick-off meeting in the Ship’s Mess at 0800. As a minimum, the meeting shall be attended by the COR, Contracting Officer, and a Contractor's management official having authority to make binding commitments. Other interested parties may attend the meetings as appropriate.
2.2.28.2. The Contractor’s baseline Schedule, including start dates for each work item, and QA Test and Inspection Plan shall be submitted for approval by the COR at, or before, the Kick-off/Pre-dockside Meeting. Any potential impacts to schedule, habitability, and material delivery delays, or complex work shall be identified.
2.2.29. Weekly Progress Meetings
2.2.29.1. Hold Weekly Progress meetings at a time and place mutually agreeable to the COR and Contractor. The meetings shall be attended by the COR and a Contractor management official who has authority to make binding commitments. Other interested parties may attended, subject to COR and Contractor approval.
2.2.29.2. Submit a written Progress Report to the COR by 3:00pm the day before the Progress Meeting with the following information:
2.2.29.3. Percent complete of each contract item and additional work items authorized by the Contracting Officer.
2.2.29.4. Any problems which could impact timely completion, including material delays. Include a problem description, schedule impact estimate, and mitigation plan.
2.2.30. Sequence of Work:
2.2.30.1. Working Hours: Contractor shall schedule working hours between 0700 and 1700 Monday through Saturday. Contractor shall obtain COR approval for ship work outside of these hours.
2.2.30.2. Unless approved by COR, the ship will not be available for work on the following days:
2.2.30.2.1. Thanksgiving: 28 November 2019
2.2.30.2.2. Christmas: 22 December – 25 December 2019
2.2.30.2.3. New Years: 1 January 2020
2.2.30.3. Schedule: In addition to the deliverables required under CAR 1352.271-73 of the RFP, the Contractor shall provide a schedule to the COR detailing the start and estimated completion dates for each work item no later than 10 days after Contract award. Schedules shall be submitted in PDF format. Contractor schedules shall identify the following milestone completion dates:
a. Contract Start Date
b. Ship Uninhabitable
c. Commissioning HVAC Plant Start Date
d. Crew Move-aboard (Ship habitable)
e. Dock Trials
2.2.30.4. For all scheduled, planned work, Contractor shall provide a minimum of
10 days notice to COR prior to making the ship “uninhabitable”.
2.2.31. Hazardous Materials
2.2.31.1. NOAA Ship PISCES was constructed between 2006 and 2009. There was no asbestos used during construction. Asbestos requirements contained in referenced Standard Specifications do not apply to this ship.
2.2.31.2. The Contractor is responsible for the control, handling, and disposal of any hazardous materials generated during accomplishment of this contract.
2.3. Metrication
2.3.1. A combination of Standard English units of measure (feet – pounds) and Metric
System International (SI) units of measure (millimeter - kilogram) were used in the builders' drawings, specifications and reference materials for construction, operation, maintenance and repair of this ship. In this specification for NOAA Ship PISCES, there is a combination of Standard English units and metric units.
2.4. Notes
2.4.1. Descriptive data of NOAA Ship PISCES (M283):
Length Overall: 208.6 feet Beam (Molded): 49.2 feet Displacement: 1,766 metric tons Light Ship 2,479 metric tons Full Load Draft: 20.35 feet Full Load Centerboard Retracted
29.7 feet Full Load Centerboard Extended Cruising Speed: 12 knots [Max speed 14 knots] Propulsion: Diesel Electric, Single Propeller, Fixed Pitch, with two, in-line 1508 hp DC Motors Generators: Caterpillar 3508B, 3512B (two each) 600 volts AC Bow Thruster: Elliott 40T3S, 360 Degree Electric Service: 480 volts AC Year Built: Commissioned November 2009 Builder: VT Halter Marine Inc,. Moss Point, MS
ABS ID: 9161926
IMO Number: 9349071 Construction: Welded Steel Hull, Aluminum Superstructure Crew size: 22 Bunks: 39 Homeport of Record: Pascagoula, MS Dockside Location: NOAA Gulf Marine Support Facility, 151 Watts Avenue, Pascagoula, MS 39567
2.4.2. All contractors, vendors, and visitors are encouraged to make pre-arrival arrangements for the pre-bid inspection in advance by calling the Port Engineer at 202.734.9947.
END OF ITEM
3.0 BASIC ITEMS (ORF)
3.1 ITEM 301: ABS SPECIAL SURVEY NO. 1
3.1.1. Scope
3.1.1.1. Provide labor and materials to support completion of all ABS Annual
Surveys and address outstanding ABS requirements or deficiencies.
3.1.2. References
3.1.2.1. NOAA Standard Specification MOC-100-1A, “ABS Load Line Survey”
3.1.2.2. Drawing 085- FA02, General Arrangements
3.1.3. Government-Furnished Material (GFM)
3.1.3.1. None
3.1.4. Requirements
3.1.4.1. The Contractor shall provide all labor and materials to enable the local
American Bureau of Shipping (ABS) surveyor to complete NOAA Ship PISCES Load Line Survey No.1 in accordance with reference 3.1.2.1 and other annual Classification surveys to maintain Regulatory compliance. Other required annual surveys for ABS Classification include Annual Automation Survey 1, Annual Hull Survey 1, Annual Machinery Survey 1, and the Cargo Gear Survey. All inspections will be accomplished with COR, or other government representative present. New ABS findings not already covered by this Specification shall be considered a topic of additional work.
3.1.4.2. Government will compensate ABS for survey costs under a separate purchase order. Contractor shall prepare vessel for various survey parts in accordance with the survey test schedule Contractor produced in Paragraph
2.2.13 and bear cost of re-survey due to improper/ inadequate vessel preparation. Neither Government nor Contractor shall be compensated by the other for delay of a scheduled survey if delay is caused by ABS for which neither Contractor nor Government is at fault.
3.1.4.3. In accordance with reference 3.1.2.1, open, clean, and certify the following tanks are cleared for entry. Cleaning shall include power washing followed by removal of all residual water and power washing residue.
Reference 3.1.2.2 provides detailed information regarding the tanks.
Contractor shall preserve and paint removed man-hole covers in accordance with the Paint Schedule. Tanks will be pumped to low suction by Ship’s Force prior to opening.
3.1.4.3.1. FO Tank 4-7-1F
3.1.4.3.2. FO Tank 4-7-2F
3.1.4.3.3. FO Tank 4-13-1A
3.1.4.3.4. FO Tank 4-13-2A
3.1.4.3.5. FO Tank 4-19-0
3.1.4.4. In accordance with Reference 3.1.2.1, open, clean, and certify the following tanks are safe for hot-work. Cleaning shall include power washing followed by removal of all residual water and power washing residue.
Reference 3.1.2.2 provides detailed information regarding the tanks.
Contractor shall preserve and paint removed man-hole covers in accordance with the Paint Schedule. Ship’s Force will empty #4C Ballast Tank to the low suction level. Contractor shall arrange a sump truck to dispose of all waste fluid within the Bilge Residue Tank and Oil Retention Tank. For estimating purposes, Contractor shall estimate removal and disposal of 1,000 gallons of waste.
3.1.4.4.1. Bilge Residue Tank (Oily Waste Tank 4-47-2)
3.1.4.4.2. Oil Retention Tank (Waste Oil Tank 4-47-1)
3.1.4.4.3. #4C Ballast Tank (4-39-01)
3.1.4.5. Inspect all opened tanks with ABS, including all striker plates and sounding tubes. Replace the striker plate in Bilge Residue Tank (4-47-2) with ½” Steel 2x2x1/2” thick angle iron. Paint all new and disturbed surfaces.
3.1.4.6. Complete proper surface preparation and paint the Bilge Residue Tank (4- 47-2), including all piping passing through the tank, with two coats of International 385 primer (or equal) and one top coat (minimum 6 mils thick each).
3.1.4.7. Upon completion of all inspections and work within opened tanks, close all opened tanks with new gaskets.
3.1.4.8. Contractor shall inspect the following reach rods for operation and submit a CFR documenting all discrepancies and recommended repairs.
3.1.4.8.1. Port and STBD Sea Chest Isolation Valves (QTY 2)
3.1.4.8.2. Firemain Isolation Valve (QTY 1)
3.1.4.8.3. Main SW Overboard Valves (QTY 2)
3.1.4.8.4. ASW SW Overboard (QTY 1)
3.1.4.8.5. Sea Strainer Isolation Valves (QTY 6)
3.1.4.9. Provide all reports to COR.
3.1.4.10. Contractor shall provide all labor and materials to adjudicate all deficiencies identified by ABS. Additional ABS required repairs not identified in this specification will be the subject of additional work.
3.1.5. Quality Assurance
3.1.5.1. As required in reference 3.1.2.1
3.1.6. Notes
3.1.6.1. None
Trim and Stability Booklet, Sheet 12
VTHM Job No: M282
TANK CAPACITY SUMMARY
Trim 0 M Aft
Vessel: 63X15X8.65M FRV
VTHM Hull No: 1953 Name: HENRY B. BIGELOW
Tank Location SP Vol
M^3/MT
Capacity Liters
Capacity M Tonnes
VCG
Meters
LCG
Meters
TCG
Meters
FSM
M-MT
BALLAST 4-1-0 FP FR D-7 CTR 0.98 43,616 44.71 5.792 2.895 0.000 20.88
BALLAST 4-34-0 DB#3 FR 34-39 CTR 0.98 35,489 36.38 2.040 22.315 -0.038 31.39
BALLAST 4-29-1 DB#3 FR 29-39 STBD 0.98 33,944 34.79 2.341 21.041 3.974 23.73
BALLAST 4-29-2 DB#3 FR 29-39 PORT 0.98 35,827 36.72 2.288 21.005 -3.959 23.95
BALLAST 4-39-01 DB#4 FR 39-49 CTR 0.98 66,957 68.63 1.955 26.997 0.000 62.48 *
Subtotal 213,567 218.910 2.877 19.40 -0.01
FO 4-7-1 DT#1F FR 7-13 STBD 1.18 31,288 26.54 3.752 6.602 0.971 3.88
FO 4-7-2 DT#1F FR 7-13 PORT 1.18 31,288 26.54 3.752 6.602 -0.971 3.92
FO 4-13-1 DT#1A FR 13-19 STBD 1.18 21,456 18.20 3.540 10.115 2.278 4.14
FO 4-13-2 DT#1A FR 13-19 PORT 1.18 21,456 18.20 3.540 10.115 -2.278 4.16
FO 4-19-1 DT#2 FR 19-29 STBD 1.18 59,077 50.10 3.927 15.214 3.669 11.38
FO 4-19-2 DT#2 FR 19-29 PORT 1.18 59,077 50.10 3.927 15.214 -3.669 11.40
FO 4-19-0 DT#2 FR 19-23 CTR 1.18 25,631 21.74 2.159 13.007 0.000 20.78
FO 4-39-1 DB#4 FR 39-49 STBD 1.18 43,025 36.49 2.241 26.609 4.436 33.18 *
FO 4-39-2 DB#4 FR 39-49 PORT 1.18 43,025 36.49 2.241 26.609 -4.436 32.50 *
FO 3-72-1 DT#5 FR 72-78 STBD 1.18 28,039 23.78 4.965 45.274 4.903 19.66
FO 3-72-2 DT#5 FR 72-78 PORT 1.18 28,039 23.78 4.965 45.274 -4.903 19.66
FO DAY TANK 3-39-1 FR 39-49 STBD 1.18 16,636 14.11 4.715 26.992 6.779 0.67 *
FO DAY TANK 3-39-2 FR 39-49 PORT 1.18 16,636 14.11 4.715 26.992 -6.779 0.67 *
Subtotal 424,673 360.180 3.613 20.50 0.00
FRESH WATER 3-19-1 FR 19-27 STBD 1.00 17,505 17.46 5.008 14.200 0.937 2.58 *
FRESH WATER 3-19-2 FR 19-27 PORT 1.00 17,505 17.46 5.008 14.200 -0.937 2.58 *
Subtotal 35,010 34.920 5.008 14.20 0.00
WASTE WATER 4-29-0 FR 29-34 CTR 1.00 34,965 34.88 (for FW) 35.84 (for SW) 2.060 19.309 0.000 31.39 * ROLL STABILIZATION 2-22-0 FR 22-29 CTR 0.98 72,451 74.26 14.950 15.700 0.000 467.91 * Subtotal 107,416 109.140 10.831 16.85 0.00
OILY WASTE 4-47-2 FR 47-49 PORT 0.98 5,350 5.48 2.035 29.201 -3.417 0.66 *
WASTE OIL 4-47-1 FR 47-49 STBD 1.09 5,350 4.92 2.035 29.201 3.417 0.59 *
LO 3-47-01 FR 47-49 PORT 1.09 3,549 3.26 4.111 29.150 -0.592 0.71 *
EMERG GEN DAY FR 54-56 STBD 1.18 888 0.75 12.622 33.400 0.263 0.01 *
INCINERATOR FR 69-70 PORT 1.18 296 0.25 11.207 42.100 -6.875 0.08 *
Subtotal 15,433 14.660 3.200 29.65 -1.83
HYRO LAB (12" OF WATER) FR 38-45 STBD 0.98 5,073 5.20 8.804 25.300 5.500 22.62 *
3.2 ITEM 302: RESCUE BOAT DAVIT ANNUAL INSPECTION
3.2.1. Scope
3.2.1.1. Overhaul the Fast Rescue Boat Davit and Winch assembly and conduct an annual inspection of the Rescue Boat Davit.
3.2.2. References
3.2.2.1. Technical Manual FRV40-226-093-010 “Rescue Boat Handling System”
3.2.2.2. Technical Manual FRV40-226-027-010 “Encapsulated Liferafts and Davits Model: Davit SRR 360/3,65/21 Winch: 08-02 HVStop”
3.2.2.3. NOAA Standard Specification AMC-300-1, "Overhaul of Electrical
Rotating Machinery”
3.2.3. Government-Furnished Material (GFM)
3.2.3.1. None
3.2.4. Requirements
3.2.4.1. Coordinate removal of the Fast Rescue Boat with Ship’s Force.
3.2.4.2. Tag-out the Fast Rescue Boat system.
3.2.4.3. Prior to removal or disassembly of any components, Contractor shall procure the services of the OEM to inspect the Fast Rescue Boat Davit launch system and winch assembly and review all repairs detailed in this specification.
Submit a CFR for any additional recommended repairs, modifications that are not already identified in this specification, or changes to the repairs detailed in this specification.
3.2.4.4. Remove the two hydraulic cylinders from the Davit. Note: These are spring loaded guide rods and must be disassembled and reinstalled in accordance with Reference 3.2.2.1. Transport the cylinders to an OEM approved overhaul and repair facility and overhaul the hydraulic cylinders.
Overhaul shall include replacement of all hardware, seals, gaskets, and counterbalance valves. Conduct proper surface preparation and paint the cylinders using an OEM-approved coating system. Re-chrome or replace the hydraulic cylinder rods. Reinstall the spring loaded guide rods in accordance with Reference 3.2.2.1 including refilling the oil level. Install new inspection plugs and clean threads on cylinder and reinstall on the ship.
3.2.4.5. Drain and dispose of the hydraulic oil and remove the Davit W 50 RS
Winch as an assembly from the ship. Complete a detailed inspection of the entire winch assembly, including a borescope inspection between the winch drum and chain housing. Provide a CFR for any recommended repairs above those detailed below:
3.2.4.5.1. Inspect the throttle block. Disassemble, inspect, clean, and reassemble using new seals, plugs, and hardware. Replace the needle valve. Remove all corrosion. Preserve, paint, and reinstall the throttle block.
3.2.4.5.2. Inspect all hydraulic piping, end fittings for corrosion, and piping support for corrosion. Preserve and paint. Reinstall using new seals and hardware as necessary.
3.2.4.5.3. Completely disassemble the friction brake. Replace the friction discs and clutch assembly using new OEM parts.
3.2.4.5.4. Replace the oil. Contractor shall wipe down the inside of the oil reservoir and inspect the tank prior to refilling with Contractor furnished oil.
3.2.4.5.5. Replace the accumulator and recharge to the proper pressure.
3.2.4.5.6. Replace the manual pump handle.
3.2.4.5.7. Inspect the chain assembly.
3.2.4.5.8. Disconnect the electrical motor from the winch assembly and transport to an approved overhaul and repair facility. Inspect the motor and overhaul in accordance with Reference 3.2.2.3. Overhaul shall include replacement of all seals, bearings, cleaning and testing of the motor windings. Provide a report when the overhaul is complete. Paint the motor and replace all junction box penetrations. Re-terminate all electrical connections and ensure the junction box is watertight. Reinstall the electrical motor.
3.2.4.5.9. Preserve the winch foundation and all normally inaccessible surfaces in accordance with the Paint Schedule. Foundation shall be blasted (or UHP washed) in accordance with Reference 3.2.2.1 to an SSPC 10 condition. Note that the removable bulkhead separating the fueling station and the FRB Davit area may need to be temporarily lifted to aid in accessing the winch foundation and foundation bolts.
3.2.4.6. Conduct proper surface preparation removing all corrosion and paint all surfaces including the winch assembly, winch foundation and davit in accordance with Reference 3.2.2.1.
3.2.4.7. Reinstall all components on the ship using new hardware. OEM approved foundation mounting bolts shall be installed and torqued in the presence of
COR.
3.2.4.8. Replace the Davit Falls wire rope and brake release cable.
3.2.4.9. Renew the rescue boat cradle pads.
3.2.4.10. Arrange for an annual inspection of the rescue boat davit on NOAA Ship PISCES. The Inspection shall be carried out by a technician from Palfinger.
3.2.4.10.1. Provide a three (3) day notice (minimum) to PISCES Commanding
Officer or Ship’s Bosun so that arrangements can be made for the Ship’s Bosun to attend the davit inspection.
3.2.4.10.2. Inspection shall include visual and operational actions encompassing the davit and davit operating system. Visual inspections shall include structural integrity of davit and davit foundation, winch, brake, lifting hook and end link, and cable. Operational tests shall demonstrate the performance of all davit- controlled operating features including launching, braking, retrieval, and stowage of the rescue boat.
3.2.4.11. Contractor shall weight test the winch upon completion of repairs to the satisfaction of the OEM representative and COR.
3.2.4.12. Submit a condition report detailing the scope of the inspections and testing accomplished as well as an itemized list of any required parts or other work that should be performed to keep davit fully SOLAS compliant.
3.2.4.13. Purchase and installation of new parts, or other davit work not already specified herein shall be the topic of additional work.
3.2.5. Quality Assurance
3.2.5.1. Condition report to be on standard forms provided by Palfinger.
3.2.6. Notes
3.2.6.1. Palfinger Rescue Boat Davit and Winch:
Model: SA3.5/ RSQ475A/ W50RS Palfinger Marine USA Inc (LA) 912 Highway 90 East New Iberia, LA 70560 POC: Mike Resweber Phone: 337-551-6230 Email: mike.resweber@palfingermarine.com mailto:mike.resweber@palfingermarine.com
3.3 ITEM 303: SSDG RESILIENT MOUNT REPLACEMENT
3.3.1. Scope
3.3.1.1. Replace the existing resilient mounts on four SSDG upper and lower foundations.
3.3.2. References
3.3.2.1. Drawing M282-073-FP22 “Generator Intermediate Mass Raft Details”
3.3.2.2. Spreadsheet M283-FR05 “Resiliently Mounted Equipment”
3.3.3. Government-Furnished Material (GFM)
3.3.3.1. Resilient Mounts Christie & Grey Mounts Model 10.103.70 (QTY 72) and
10.103.75 (QTY 40). Total Cost: $25,000.
3.3.4. Requirements
3.3.4.1. Measure and record the shim heights on all the generator mounting bolts.
Provide the COR with a condition report stating all of the measurements.
3.3.4.2. Contractor shall remove the existing engine foundation vibration mounts and install new GFM provided resilient mounts on all 4 engines; using Reference 3.3.2.1 and Reference 3.3.2.2 as a guide to ensure that the correct mounts are installed in the correct locations and as follows:
3.3.4.2.1. The generator/engine set base frame must be supported independently and leveled in position but approximately 35 mm (1.4”) higher than as found condition. Install the upper mountings directly to the generator/engine frame with no shims and with no load on the mountings.
3.3.4.2.2. The rafts must be supported independently and leveled but approximately 18 mm (0.71”) higher so as to leave a clearance of about 6 mm (0.25”) between the upper mountings and the raft top surface. Install the lower mounting to the rafts without shims. There should be a clearance of about 6 mm (0.25”) below the lower mountings at this stage.
3.3.4.2.3. Measure and record the clearances below each mounting. Take a reading at each corner of the base and average these. If the difference across a base is more than 2 mm consideration should be given to using taper shims.
3.3.4.2.4. For the upper mountings, subtract the smallest clearance of any of the upper mountings from each of the other upper measurements. The remainder is the shim thickness to be used below that mounting.
3.3.4.2.5. For the lower mountings, subtract the smallest clearance of any of the lower mountings from each of the other lower measurements. The remainder is the shim thickness to be used below that mounting.
3.3.4.2.6. Round the shim thickness calculated to the nearest millimeter (0.040”) and record. This is the shim thickness for that mounting. If taper shims are used record the thickness at each corner.
3.3.4.2.7. Prepare shims with the two bolt clearance holes for fitting below the mountings. Each shim shall be a single piece covering the whole of the mounting base. Install the shims and insert the fixing bolts loosely to ensure that the mounting are not strained horizontally.
3.3.4.2.8. At this stage there should be clearance below the mountings.
Transfer the weight onto the mountings by first lowering the rafts. The lower mountings should not compress significantly (perhaps 2 mm (0.080”) under the weight. When the rafts are free lower the generator/engine set onto the upper mountings.
3.3.4.2.9. Allow to settle for 48 hours before measuring the “installed” mounting heights. These must be recorded with details of the positions and shims used at each position.
3.3.4.3. Tighten all mounting bolts to their correct torque valves.
3.3.4.4. Accomplish a complete engine and generator alignment inspection by an OEM certified technician (CAT) after the mounts have had the final torque.
Ensure proper alignment and a provide report as a CFR. Provide readings for radial, axial, and angular misalignment, and inspect for soft foot conditions.
3.3.5. Quality Assurance
3.3.5.1. None
3.3.6. Notes
3.3.6.1. None
3.4 ITEM 304: SHIP’S CRANES REFURBISHMENT
3.4.1. Scope:
3.4.1.1. Inspect and overhaul the three ship’s cranes, as specified.
3.4.2. 3.12.1 References
3.4.2.1. Tech Manual FRV40-226-134-010 “Knuckle Boom Crane”
3.4.2.2. Tech Manual FRV40-226-111-010 “Telescoping Boom Crane”
3.4.2.3. Tech Manual FRV40-226-105-010 “Stores Handling System”
3.4.2.4. ABS Guide for Certification of Lifting Appliances
3.4.2.5. NOAA Standard Specification AMC-300-1, "Overhaul of Electrical
3.4.3. Government Furnished Material
3.4.3.1. Knuckleboom Crane Planetary Gear Reducers and Hydraulic Motors (QTY 3) – Value $20,000
3.4.3.2. Telescoping Crane Planetary Gear Reducers and Hydraulic Motors (QTY
4) – Value $27,500
3.4.3.3. Hydraulic Swivels – QTY 2 – Value - $5,000
3.4.3.4. Knuckleboom Crane Control Valve and Bracket – Value - $10,000
3.4.3.5. Telescoping Crane Control Valve and Bracket – Value - $8,500
3.4.3.6. Telescoping Crane Holding Valve – value - $600
3.4.3.7. Knuckleboom Crane Counterbalance Valve Manifold and Bracket – value
- $3,200
3.4.4. Requirements
3.4.4.1. Tag-out all electrical and hydraulics to the Telescoping, Knuckleboom, and Stores Handling Cranes.
3.4.4.2. Procure the services of the OEM to complete an inspection and system groom on each crane. An Appleton OEM Technician may be obtained from below contact information. Contractor may elect to do the work separately using OEM approved parts and repair procedures, but at a minimum, the OEM shall be onsite to complete the initial (Paragraph 3.4.4.3) and final inspections, (Paragraph 3.4.4.24), system groom, and operational testing of each crane.
OEM shall be onsite for a minimum of 40 hours. Travel hours do not constitute time required to be on-site.
Appleton Marine 3030 E. Pershing St.
Appleton, WI 54911 POC: Steve Zahringer Email: steve.zahringer@appletonmarine.com Phone: 920-738-5432 (EXT 126) / 920-738-1390
3.4.4.3. Inspect the cranes with the OEM. Inspection includes operation and inspection of all electrical, hydraulic, mechanical, and structural components of the Knuckleboom, Telescoping, and Ship’s Stores Cranes. All repairs shall be completed in accordance with the OEM Technician recommendations.
Submit a CFR for additional recommended repairs that are not already covered by this specification.
3.4.4.4. Disconnect all hydraulic piping and electrical connections to the Telescoping and Knuckleboom Cranes as required to complete the work of this specification. Cap all hydraulic hoses and pipes to prevent contamination.
3.4.4.5. On the Knuckleboom Crane, disconnect and remove the luff and jib boom cylinders. Remove the Hydraulic Winch, cable, and other necessary components to aid in removal. Disconnect the heel and jib pin and remove the luff and jib booms from the ship. Luff and Jib cylinders were refurbished in 2019. Inspect the cylinders, paint, and if no additional work is required, store in a covered location until reinstallation. Overhaul the hydraulic winch and replace all seals, bearings, and consumables. Winch seal is currently leaking on the inboard seal. Ensure all repairs are leak-free.
3.4.4.6. On the Telescoping Crane, disconnect and remove the luff cylinder, winch, cable, and other components necessary to aid in removal of the boom.
Disconnect the heel pin and remove the telescoping boom from the ship.
Inspect the Luff cylinder, replace the seal, and paint the Cylinder. Submit a CFR if additional repairs are required. Store in a covered location until reinstallation.
mailto:steve.zahringer@appletonmarine.com
3.4.4.7. Contractor shall provide shoreside cranes and all rigging to accomplish crane component removal and reinstallation.
3.4.4.8. Transport the removed crane components to an approved repair and overhaul the removed crane components. Completely disassemble all removed components. Overhaul includes inspecting all portions of the disassembled components by the OEM, replacement of all bushings and thrust washers, reconditioning all pins, removal of all corrosion and painting the entire crane assembly. Cover all mechanical and electrical components that could be damaged by grit blast. Spot and sweep (or UHP) the removed luff and jib booms and the telescoping boom and paint in accordance with OEM recommendations using a QP1 certified contractor. Reassemble all booms using new or reconditioned hardware and lubricate/grease in accordance with OEM recommendations.
3.4.4.9. After removal of the crane boom assemblies, inspect the entire crane assembly, foundation, mounting pedestal, and all associated hardware with the OEM. Provide an inspection report for each crane detailing inspection results and all recommended repairs that are not already directed by this specification.
3.4.4.10. Contractor shall remove all rust and corrosion from both the Knuckleboom and Telescoping cranes, including the foundations and mounting pedestals on the ship. On all shipboard components and structures, conduct proper surface preparation to SSPC-11 and repaint the entire crane assembly, foundation, and pedestal from the crane platform upwards in accordance with the Paint Schedule using a QP1 certified contractor.
3.4.4.11. Inspect the Turntable Bearing on both cranes (Knuckleboom Crane - Item 2, Appleton Part Number YMD-9075; Telescoping Crane -Item 2, Appleton Part Number YMD-8543).
3.4.4.12. On the Knuckleboom Crane, replace the following components using GFM provided materials. See Drawing AMD-1585 of Reference 3.4.2.1 for reference:
3.4.4.12.1. Three Hydraulic Motors and Planetary Speed Reducers. Hydraulic
Motors are Appleton part number YMD-9102 and Planetary Speed Reducers are P/N YMD-7435.
3.4.4.12.2. Replace the Hydraulic Swivel (Item 16, Appleton Part Number
YMD-3136).
3.4.4.12.3. Control Valve (Item 17, Appleton Part Number YMD-9471) and foundation (bracket, Item 71, Appleton P/N JMD-1588)
3.4.4.12.4. Replace the Counterbalance Valve Manifold (Item 11, P/N YMD-
9298)
3.4.4.12.5. Replace the Counterbalance Manifold Bracket (Item 131, P/N
MMD-3767)
3.4.4.13. On the Telescoping Crane, replace following components using the GFM provided materials. See Drawing AMD-1503 of Reference 3.4.2.2 for reference:
3.4.4.13.1. Four Hydraulic Motors and Planetary Speed Reducers. Hydraulic
Motors are Appleton part number YMD-8873 and Planetary Speed Reducers are P/N YMD-7208.
3.4.4.13.2. Replace the Hydraulic Swivel (Item 16, Appleton Part Number
YMD-3136).
3.4.4.13.3. Control Valve (Item 17, Appleton Part Number YMD-8893) and foundation (bracket, Item 156 Appleton P/N JMD-1452) for the Control Valve.
3.4.4.14. Replace the end fittings and threaded connections for all piping and tubing between each new hydraulic motor assembly on the Knuckleboom and Telescoping Cranes as well as all piping and tubing to the hydraulic hoses on the crane pedestal. Paint all new and disturbed surfaces.
3.4.4.15. Reinstall the overhauled Knuckleboom Crane luff and jib boom, hydraulic cylinders, winch, cable, and all removed components onto the respective Pedestal mount in accordance with References 3.4.2.1 and 3.4.2.2. Inspect and torque all pedestal mounting bolts as necessary.
3.4.4.16. Replace the wire rope on both cranes with new.
3.4.4.17. Lubricate the Telescoping assembly on the Telescoping crane for operation.
3.4.4.18. Inspect all hoses on the cranes for wear, abrasion, and chaffing.
3.4.4.19. Reconnect all hydraulic hoses, piping, and electrical connections.
3.4.4.20. Inspect all joints and replace all seals, gaskets, O-rings, consumables, and hardware as required. Properly lubricate all joints.
3.4.4.21. Contractor shall inspect the chest-packs for both the Telescoping and Knuckleboom cranes. Submit a CFR detailing repairs required to bring the chest-packs to a fully operating condition.
3.4.4.22. Contractor shall inspect the FWD Stores Crane and complete the following repairs:
3.4.4.22.1. Remove and overhaul the Gearbox assembly. Replace all bearings, seals, gaskets, and O-rings. Blast and paint the gearbox assembly.
Reinstall the gearbox using new hardware.
3.4.4.22.2. Remove and overhaul the motor in accordance with Reference
3.4.2.5. Overhaul includes replacement of all bearings. Preserve, paint, align, and balance, and reinstall the motor using new hardware.
3.4.4.22.3. Submit a CFR detailing additional recommended repairs. Paint all new and disturbed surfaces.
3.4.4.23. Submit a CFR detailing repairs to all cranes and any further recommended repairs to bring the cranes to a fully operational condition.
3.4.4.24. Contractor shall perform an annual inspection and weight testing of the ship’s cranes to complete the initial ABS Lifting Gear Appliances certification in accordance with References 3.4.2.4 to include a rock / tilt test and slewing bolt inspections.
3.4.4.24.1. Conduct a weight test on the Telescoping and Knuckleboom cranes to 125% of the rated load in the presence of ABS and complete all inspections and testing (including 15% of slewing ring bolt NDT testing and replacement) in accordance with Reference 3.4.2.4.
NOTE: The Telescoping Crane failed to remain on the Cargo Gear Certificate in 2019 and was…