13-Attachment C CIP 10323 Waters Ave FM 60% Schedule.pdf
PDF 73 KB Posted
- Solicitation number
- RPS-26-00423
- Issued by
- Hillsborough County, Florida
About this file
This file is a Construction Inspection Progress Schedule (CIP 10323) for the Waters Avenue Force Main Replacement project being managed by Hillsborough County's Capital Programs Department in Florida. The schedule document provides a detailed timeline for the force main replacement project, which is valued at approximately $2,200,000.00. The project involves the replacement of an existing force main along Waters Avenue, with the schedule outlining phased construction activities and anticipated milestones throughout the project duration. The document serves as the baseline schedule reference for Construction Management, Engineering and Inspections (CEI) services that are being procured to oversee and monitor the project's progress, quality, and compliance with specifications.
The schedule establishes the framework for tracking construction phases and deliverables that CEI service providers will be responsible for inspecting and documenting. This procurement includes a Small Business Enterprise (SBE) participation goal of 10% for subcontractor involvement, which bidders must address in their proposals. The schedule document is critical for prospective CEI service providers to understand project scope, duration, resource requirements, and inspection/certification points throughout the construction phases, enabling them to prepare accurate proposals and staffing plans for delivering comprehensive engineering and construction inspection services on this infrastructure replacement initiative.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
0 Waters Avenue Forcemain BODR Schedule
9/17/25 8/9/28
1 PHASE I DESIGN 9/17/25 10/30/26
2 BOCC Approval 9/17/25 9/17/25
3 Phase 1 Notice to Proceed 10/27/25 10/27/25 2ES+41 days
4 Prepare & Chair Kickoff Meeting 7 days 10/28/25 11/3/25 3
5 Draft BODR 83 days 11/4/25 1/25/26 4
6 HC BODR Comments 12 days 1/26/26 2/6/26 5
7 Prepare & Chair BODR Workshop 2 days 2/7/26 2/8/26 6
8 Final BODR 61 days 2/9/26 4/10/26 7
9 60% Design Submittal 81 days 3/31/26 6/19/26 8ES-11 days
10 HC 60% Design Comments 12 days 6/20/26 7/1/26 9
11 Prepare & Chair 60% Design Workshop
2 days 7/2/26 7/3/26 10
12 Permit Submittals 14 days 7/4/26 7/17/26 11
13 90% Design Submittal (GMP) 45 days 7/18/26 8/31/26 12
14 HC 90% Design Comments (GMP) 12 days 9/1/26 9/12/26 13
15 Prepare & Chair 90% Design Workshop
2 days 9/13/26 9/14/26 14
16 HC Agreement on Early Works Package
14 days 9/15/26 9/28/26 15
17 Early Works Construction NTP 9/28/26 9/28/26 16
18 100% Design Submittal 29 days 9/15/26 10/13/26 15
19 BOCC Approval & Phase 2 (Construction) Notice to Proceed
46 days 9/15/26 10/30/26 15
20 Phase 2 (Construction) Notice to Proceed
10/30/26 10/30/26 19
21 PHASE II CONSTRUCTION 4/28/26 8/9/28
22 Prepare Submittals 4 weeks 4/28/26 5/25/26 9SS+20 days
23 Submittals (Review/Approve) 2 weeks 6/22/26 7/3/26 9; 22
24 Long Lead Materails (Release/ Accept)
16 weeks 7/6/26 10/23/26 11; 23
25 Early Works Construction 4 weeks 9/29/26 10/26/26 17
26 Waters Ave FM Installation 11/2/26 4/19/28 20; 24; 25
27 Waters Ave FM Phase 1 24 weeks 11/2/26 4/30/27 20; 24; 25
28 Waters Ave FM Phase 2 24 weeks 5/3/27 10/20/27 27
29 Waters Ave FM Phase 3 24 weeks 10/21/27 4/19/28 28
30 Service Lateral Connections 68 weeks 12/2/26 4/19/28 27SS+4 weeks
31 Abandon/Restore 16 weeks 4/20/28 8/9/28 26; 29; 30
# Traits Title Given Work Planned Start Planned End Predecessors
Waters Avenue Forcemain BODR Schedule
PHASE I DESIGN
BOCC Approval
Phase 1 Notice to Proceed
Prepare & Chair Kickoff Meeting
Draft BODR
HC BODR Comments
Prepare & Chair BODR Workshop
Final BODR
60% Design Submittal
HC 60% Design Comments
Prepare & Chair 60% Design Workshop
Permit Submittals
90% Design Submittal (GMP)
HC 90% Design Comments (GMP)
Prepare & Chair 90% Design Workshop
HC Agreement on Early Works Package
Early Works Construction NTP
100% Design Submittal
BOCC Approval & Phase 2 (Construction) Notice to P…
Phase 2 (Construction) Notice to Proceed
PHASE II CONSTRUCTION
Prepare Submittals
Submittals (Review/Approve)
Long Lead Materails (Release/Accept)
Early Works Construction
Waters Ave FM Installation
Waters Ave FM Phase 1
Waters Ave FM Phase 2
Waters Ave FM Phase 3
Service Lateral Connections
Abandon/Restore