Project Manual Summary: Erie County Medical Center Tank #13 Removal and Replacement
This is a comprehensive project manual and bid specification document prepared by LaBella Associates, D.P.C. for Erie County Medical Center Corporation located at 462 Grider Street, Buffalo, New York, outlining the complete removal and replacement of a 5,000-gallon underground storage tank (UST). The project, designated IFB 2026-02, requires qualified contractors to provide all labor, equipment, materials, and services necessary for tank removal, site remediation, environmental compliance, backfilling, and installation of a new above-ground fuel storage system with dispensing capabilities. The bid due date is Monday, June 8, 2026, with a project duration of 120 calendar days from Notice to Proceed. The scope includes removal of the existing underground diesel fuel tank #13, proper handling of any petroleum-contaminated soils per New York State Department of Environmental Conservation (NYSDEC) requirements, installation of a new 5,000-gallon double-wall above-ground Fireguard tank on a reinforced concrete pad, installation of a complete fuel dispensing system with remote fill station and access controller, concrete and asphalt pavement restoration, and all associated site work.
The contractor must comply with extensive regulatory requirements including NYSDEC Petroleum Bulk Storage regulations, OSHA worker safety standards, and EPA guidelines for hazardous waste operations. A contingency allowance of $100,000 is included for unforeseen conditions. The specification mandates prevailing wage compliance per New York State Labor Law, OSHA 10 safety training certification for all workers, and comprehensive environmental oversight throughout the project including field screening for volatile organic compounds, soil sampling, and closure report documentation. All waste materials, contaminated soils, and the removed tank must be properly characterized, manifested, and disposed of at NYSDEC-approved facilities. The contractor must obtain required permits, coordinate with UDIG NY for utility locating, maintain detailed records of all disposal activities, and provide training to facility personnel on the new fuel management system and equipment operation. Payment for work is structured through periodic applications based on the Schedule of Values with retainage provisions, and the contractor bears all costs associated with additional testing, material replacement due to non-compliance, and any damage to existing adjacent structures or utilities.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
462 Grider Street
Buffalo, New York 14215
DATE: April 8, 2026
IFB 2026-02
BID Due Date: Monday, June 8, 2026
Prepared by:
LaBella Associates, D.P.C.
300 Pearl Street, Suite 130
Buffalo, NY 14202
(716) 551-6281 phone
(716) 551-6282 fax
Erie County Medical Center Corporation
462 Grider Street
Buffalo, NY 14215
P R
O J
E C
T
M A
N U
A L
Project No. 2244450.014
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
Bid Documents
TABLE OF CONTENTS 000110 - 1
SECTION 000100 – TABLE OF CONTENTS
DIVISION 00 – BIDDING REQUIREMENTS
Advertisement for Bids
Notice to Bidders Section 000100 Table of Contents
Section 007300 Sample Insurance Certificate
Section 008100 Prevailing Wage Rates
Section 008200 Statutory Requirements
DIVISION 01 – GENERAL REQUIREMENTS
Section 011000 Summary
Section 012100 Allowances
Section 012600 Contract Modification Procedures
Section 012900 Payment Procedures
Section 013100 Project Management and Coordination
Section 013200 Construction Progress Documentation
Section 013300 Submittal Procedures
Section 014000 Quality Requirements
Section 014200 References
Section 015100 Temporary Facilities and Controls
Section 016000 Product Requirements
Section 017700 Closeout Procedures
Section 017823 Operation and Maintenance Data
Section 017839 Project Record Documents
DIVISION 22 – PLUMBING
Section 221313.13 Underground Fuel-Oil Storage Tank Removal
Section 221323 Above Fuel Storage Tanks and Fuel Systems
DIVISION 26 – ELECTRICAL
Refer to Drawing E001
DIVISION 31 – EARTHWORK
Section 312000 Earth Moving
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 321216 Asphalt Concrete Paving
Section 321313 Concrete Pavement, Sidewalk, and Curbing
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
STATUTORY REQUIREMENTS 008200-1
SECTION 007300 – SAMPLE INSURANCE CERTIFICATE
See the following page for an example of the Certificate of Liability Insurance.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
SECTION 008100 – PREVAILING WAGE RATES
PART 1 - GENERAL
1.1 GENERAL
A. Contractor shall conform to NYS Prevailing Wage Rates. BIDDERS are cautioned to anticipate prevailing rate revisions during the project period. All such revisions shall be considered and included in the Bid. No additional compensation will be allowed.
REQUIREMENTS OF ARTICLE 8 (SECTION 220-223) OF
THE NEW YORK STATE LABOR LAW
Prospective bidders can access the NYS prevailing wage rate schedule for this project by visiting the
DOL website at: The "Request for Wage and Supplement Information" (PW 39) you have submitted has been accepted, and a Prevailing Rate Case Number ( ) has been assigned to the project.
To access the PDF file of your schedule, click on https://apps.labor.ny.gov/wpp/publicViewProject.do?method=showIt&id=1528900 or copy and paste into your browser
END OF SECTION 008100
https://apps.labor.ny.gov/wpp/publicViewProject.do?method=showIt&id=1528900
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
SECTION 008200 - STATUTORY REQUIREMENTS
1.01 Pursuant to the Requirements of the New York State Labor Law, the following conditions and stipulations shall be included within the Contract, and shall form a part of the Contract Documents:
A. No laborer, workman or mechanic in the employ of the Contractor, Subcontractor or other person doing or contracting to do the whole or a part of the work contemplated by the Contract shall be permitted or required to work more than eight (8) hours in any one (1) calendar day or more than five (5) days in any one (1) week except in cases of extraordinary emergency including fire, flood or danger to life or property.
B. Each laborer, workman or mechanic, employed by the Contractor, Subcontractor or other person about or upon the work shall be paid the wages herein provided.
C. Each laborer, workman or mechanic, employed by the Contractor, Subcontractor or other person about or upon the work shall be provided the supplements as required by Article 220 of the New
York State Labor Law.
D. The following Wage Rate Schedule contains the minimum hourly rate of wage which can be paid and the minimum supplement that can be provided, as has been designated by the Industrial
Commissioner, to the laborers, working men or mechanics, employed in the performance of the
Contract, either by Contractor, Subcontractor of the person doing or contracting to do the whole or part of the work contemplated by the Contract. Such laborers, workingmen or mechanics shall be paid not less than such hourly minimum rate of wage and provided supplements not less than the prevailing supplements.
E. In the hiring of employees for the performance of work under this Contract or any Subcontract hereunder, no Contractor, Subcontractor, nor any person acting on behalf of such Contractor or
Subcontractor, shall by reason of race, creed, color or national origin discriminate against any citizen of the State of New York who is qualified and available to perform the work to which the employment relates.
F. No Contractor, Subcontractor, nor any person on his behalf shall in any manner, discriminate against or intimidate any employee hired for the performance of work under this Contract on account of race, creed, color or national origin.
G. There may be deducted from the amount payable to the Contractor by Owner under this Contract a penalty of Five Dollars ($5.00) for each person for each calendar day during which such person was discriminated against or intimidated in violation of the provisions of the Contract.
H. This Contract may be canceled or terminated by Owner, and all money due or to become due hereunder may be forfeited, for a second or subsequent violation of the terms or conditions of this section of the Contract.
I. The aforesaid provisions of this section covering every Contract for or on behalf of the State or municipality for the manufacturer, sale or distribution of materials, equipment or supplies shall be limited to operations performed within the territorial limits of the State of New York.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
J. Preference in employment shall be given to citizens of the State of New York who have been residents for at least six (6) consecutive months immediately prior to the commencement of their employment. Persons other than citizens of the State of New York may be employed when such citizens are not available. If the Requirements of Section 222 concerning preference in employment to citizens of the State of New York are not complied with, this Contract shall be void.
K. If a harmful dust hazard is created for which appliances or methods for the elimination of harmful dust have been approved by the Board of Standards and Appeals, such appliances or methods shall be installed and maintained and effectively operated by the Contractor. If the provisions of Section 222-a concerning harmful dust hazards are not complied with, the
Contract shall be void.
L. It is hereby agreed by and between the parties hereto that every Contractor and Subcontractor engaged in the public work described in this Contract shall post and maintain, at each of his establishments and at all places at which the public work described hereunder is being conducted, the Notice of the State Commission Against Discrimination indicating the substantive provision of the Law Against Discrimination, where complaints may be filed, and other pertinent information. Such Notice shall be posted in easily accessible and well-lighted places customarily frequented by employees and applicants for employment.
M. Requirements for OSHA 10 Compliance – Chapter 282 of the Laws of 2007 as Labor Law 220-h that have taken effect on July 18, 2008. The statute provides as follows:
The advertised specifications for every contract for public work of $ 250,000.00 or more must contain a provision requiring every worker employed in the performance of a public work contract shall be certified as having completed an OSHA 10 safety training course. The clear intent of this provision is to require that all employees of public work contractors receive such training “prior to performing any work on the project”.
All contractors and sub-contractors shall attach a copy of proof of completion of the OSHA 10 course to the first certified payroll submitted to the contracting agency and on each succeeding payroll where any new or additional employee is first listed in accordance with the Bureau enforcement of the above referenced statute.
Proof of completion may include but is not limited to:
1. Copies of bona fide course completion card.
2. Training roster, attendance record of other documentation from the certified trainer pending issuance of the card.
3. Other valid proof.
** Note – A certification by the employer attesting that all employees have completed such course is not sufficient proof that the course has been completed.
Any questions regarding this statute may be directed to the New York State Department of
Labor, Bureau of Public Work at 518-485-5696.
END OF SECTION 000820
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
SECTION 011000 - SUMMARY
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2
SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Work under separate contracts.
4. Access to site.
5. Coordination with occupants.
6. Work restrictions.
7. Project Duration.
8. Specification and Drawing conventions.
9. Miscellaneous provisions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.3
PROJECT INFORMATION
A. Project Identification: Tank #13 Removal and Replacement
1. Project Location: 462 Grider Street, Buffalo New York 14215
B. Owner: Town of Boston
1. Owner's Representative (Project Manager, Capital Projects – Plant Operations): Neldria
Staton, Ph. (716) 896-5374, e-mail: nstaton@ecmc.edu
C. Architect/Engineer: Labella Associates D.P.C. 300 Pearl Street, Suite 130, Buffalo, NY 14202.
1. Project Manager: Michael Rogalski, PE, Project Manager, Ph. (716) 710-3036, e-mail mrogalski@labellapc.com.
D. Type of Contract:
1. Project will be executed under a single prime contract.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents is for the removal of an existing underground fuel tank and providing Above Ground Fuel Storage for the Erie County Medical mailto:nstaton@ecmc.edu mailto:mrogalski@labellapc.com
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
Center Corporation vehicles use. The project in general consists of the following:
1. Remove existing underground fuel tank #13. Provide all necessary DEC requirements for this work.
a. Provide temporary shoring and/or temporary relocation of adjacent above ground tank unit the backfill of removed tank 13 is stabilized
2. Provide compacted backfill in location of removed fuel tank #13 to existing grade, future slab shall be provided by others at a future date.
3. Provide a new above ground fuel storage tank with dispensing capabilities and safety feature required by code.
4. Provide a new reinforced concrete pad and other site amenities to accommodate the new above ground storage tank.
5. Provide new electric work to accommodate the above ground fuel storage tank and any necessary interior work to access the existing electrical distribution system.
1.5 ACCESS TO SITE
A. General: Each Contractor shall have limited use of Project site for construction operations as indicated on Drawings by the Contract limits and as indicated by requirements of this Section.
B. Use of Site: Limit use of Project site to Work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
C. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period. Repair damage caused by construction operations.
D. Condition of Existing Grounds: Repair damage caused by construction operations.
1.6 COORDINATION WITH OCCUPANTS
A. Partial Owner Occupancy: The Public will have access to the entire building during the construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.
B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial
Completion of the Work, provided such occupancy does not interfere with completion of the
Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.
1. Architect will prepare a Certificate of Substantial Completion for each specific portion of the Work to be occupied prior to Owner acceptance of the completed Work.
2. Obtain a Certificate of Occupancy from authorities having jurisdiction before limited
Owner occupancy.
3. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026 occupied portions of Work.
4. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.7 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
B. On-Site Work Hours: Limit work in the existing building to normal business working hours of
7:00 a.m. to 4:30 p.m., Monday through Friday, unless otherwise indicated.
1. Weekend Hours if applicable: Coordinate with Erie County Medical Center Corporation.
Notify Erie County Medical Center Corporation point of contact no less than 7 days for weekend hours.
2. Early Morning Hours: Coordinate with Erie County Medical Center Corporation. Notify
Erie County Medical Center Corporation point of contact no less than 7 days for weekend hours.
3. Hours for Utility Shutdowns: Coordinate with Erie County Medical Center Corporation.
Notify Erie County Medical Center Corporation point of contact no less than 7 days for weekend hours.
4. Hours for Core Drilling: During normal business hours.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than seven days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify Owner not less than seven days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
E. Restricted Substances: Use of tobacco products and other controlled substances on Project site is not permitted.
F. Employee Identification: Provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
G. Employee Screening: Comply with Owner's requirements for drug and background screening of
Contractor personnel working on Project site.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
ALLOWANCES 012100 - 1
1. Maintain list of approved screened personnel with Owner's representative.
1.8 PROJECT DURATION
A. The project duration for all contracts shall be 120 calendar days from the issuance of the Notice to Proceed.
B. Any extension of the project duration will be modified through a change order. Refer to section
012600 Contract Modification Procedures.
1.9 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on
Drawings.
3. Keynoting: Materials and products are identified by reference keynotes referencing
Specification Section numbers found in this Project Manual.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
ALLOWANCES 012100 - 2
SECTION 012100 - ALLOWANCES
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
B. Types of allowances include the following:
1. Contingency allowances.
C. Related Requirements:
1. Section 014000 "Quality Requirements" for procedures governing the use of allowances for field testing by an independent testing agency.
1.3 DEFINITIONS
A. Allowance is a quantity of work or dollar amount established in lieu of additional requirements, used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order.
1.4 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise Architect of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work.
B. At Architect's request, obtain proposals for each allowance for use in making final selections.
Include recommendations that are relevant to performing the Work.
C. Purchase products and systems selected by Architect from the designated supplier.
1.5 ACTION SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
ALLOWANCES 012100 - 3
1.6 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
B. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
C. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.7
CONTINGENCY ALLOWANCES
A. Use the contingency allowance only as directed by Architect for Owner's purposes and only by
Change Orders that indicate amounts to be charged to the allowance.
B. Contractor's related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, insurance, equipment rental, and similar costs.
C. Change Orders authorizing use of funds from the contingency allowance will include
Contractor's related costs and reasonable overhead and profit.
D. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order.
1.8
ADJUSTMENT OF ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, and similar margins.
1. Include installation costs in purchase amount only where indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.
3. Submit substantiation of a change in scope of Work, if any, claimed in Change Orders related to unit-cost allowances.
4. Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
CONTRACT MODIFICATION PROCEDURES 012600 - 1
1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.
2. No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. Allowance No. GC-1: Contingency Allowance: Include the sum of One Hundred Thousand
Dollars, $100,000, for unforeseen conditions and general construction work over and above what is documented on the Construction Documents as directed by the Owner or Architect.
END OF SECTION 012100
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
CONTRACT MODIFICATION PROCEDURES 012600 - 2
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
A. Section includes administrative and procedural requirements for handling and processing
Contract modifications.
B. Related Requirements:
1. Refer to General Condition on substitution Procedures for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request or 10 days, when not otherwise specified, after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract
Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
CONTRACT MODIFICATION PROCEDURES 012600 - 3
e. Quotation Form: Use forms acceptable to Architect.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the
Contract, Contractor may initiate a claim by submitting a request for a change to Architect.
1. Include a statement outlining reasons for the change and the effect of the change on the
Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the
Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use form acceptable to Architect.
1.5 ADMINISTRATIVE CHANGE ORDERS
A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.
1.6 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Change Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.
1.7 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Architect may issue a Construction Change Directive on
AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the
Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the
Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PAYMENT PROCEDURES 012900 - 1
END OF SECTION 012600
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PAYMENT PROCEDURES 012900 - 2
SECTION 012900 - PAYMENT PROCEDURES
1.2
SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process
Applications for Payment.
B. Related Requirements:
1. Section 012100 "Allowances" for procedural requirements governing the handling and processing of allowances.
2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
1.3
DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for
Payment.
1.4
SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the schedule of values to Architect at earliest possible date, but no later than seven days after notice to proceed as been issued.
3. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide subschedules showing values coordinated with each element.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project identification on the schedule of values:
a. Project name and location.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PAYMENT PROCEDURES 012900 - 3
b. Owner's name.
c. Owner's Project number.
d. Name of Architect.
e. Architect's Project number.
f. Contractor's name and address.
g. Date of submittal.
2. Arrange schedule of values consistent with format of AIA Document G703.
3. Arrange the schedule of values in tabular form, with separate columns to indicate the following for each item listed:
a. Related Specification Section or division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent. Round dollar amounts to whole dollars, with total equal to Contract Sum.
1) Labor.
2) Materials.
3) Equipment.
4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.
5. Allowances: Provide a separate line item in the schedule of values for each allowance.
Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.
6. Overhead Costs, Proportional Distribution: Include total cost and proportionate share of general overhead and profit for each line item.
7. Overhead Costs, Separate Line Items: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.
8. Temporary Facilities: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.
9. Closeout Costs. Include separate line items under Contractor and principal subcontracts for
Project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.
10. Schedule of Values Revisions: Revise the schedule of values when Change Orders or
Construction Change Directives result in a change in the Contract Sum. Include at least one separate line item for each Change Order and Construction Change Directive.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Architect paid for by Owner.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PAYMENT PROCEDURES 012900 - 4
B. Payment Application Times: The date for each progress payment is indicated in the
Owner/Contractor Agreement. The period of construction work covered by each Application for
Payment is the period indicated in the Agreement.
1. Submit draft copy of Application for Payment seven days prior to due date for review by
Architect.
C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 form for
Applications for Payment.
1. Other Application for Payment forms proposed by the Contractor may be acceptable to
Architect and Owner. Submit forms for approval with initial submittal of schedule of values.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule.
Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of
Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.
E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.
1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices.
Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.
3. Provide summary documentation for stored materials indicating the following:
a. Value of materials previously stored and remaining stored as of date of previous
Applications for Payment.
b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.
c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.
F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt. One copy shall include waivers of lien and similar attachments if required.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PAYMENT PROCEDURES 012900 - 5
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit conditional final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit waivers.
4. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.
5. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.
H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of values.
3. Contractor's construction schedule (preliminary if not final).
4. Products list (preliminary if not final).
5. Sustainable design action plans, including preliminary project materials cost data.
6. Schedule of unit prices.
7. Submittal schedule (preliminary if not final).
8. List of Contractor's staff assignments.
9. List of Contractor's principal consultants.
10. Copies of building permits.
11. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
12. Initial progress report.
13. Report of preconstruction conference.
14. Certificates of insurance and insurance policies.
15. Performance and payment bonds.
16. Data needed to acquire Owner's insurance.
I. Application for Payment at Substantial Completion: After Architect issues the Certificate of
Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
a. Complete administrative actions, submittals, and Work preceding this application, as described in Section 017700 "Closeout Procedures."
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
J. Final Payment Application: After completing Project closeout requirements, submit final
Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Certification of completion of final punch list items.
3. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
4. Updated final statement, accounting for final changes to the Contract Sum.
5. AIA Document G706.
6. AIA Document G706A.
7. AIA Document G707.
8. Evidence that claims have been settled.
9. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
10. Final liquidated damages settlement statement.
11. Proof that taxes, fees, and similar obligations are paid.
12. Waivers and releases.
END OF SECTION 012900
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. RFIs.
3. Digital project management procedures.
4. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
C. Related Requirements:
1. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
A. RFI: Request for Information. Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site.
Identify individuals and their duties and responsibilities; list addresses and cellular
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office, and in prominent location inbuilt facility. Keep list current at all times.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their
Work is required.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and scheduled activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
1.6 REQUEST FOR INFORMATION (RFI)
A. General: Immediately on discovery of the need for additional information, clarification, or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.
1. Architect will return without response those RFIs submitted to Architect by other entities controlled by Contractor.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PROJECT MANAGEMENT AND COORDINATION 013100 - 4
2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. Project name.
2. Project number.
3. Date.
4. Name of Contractor.
5. Name of Architect.
6. RFI number, numbered sequentially.
7. RFI subject.
8. Specification Section number and title and related paragraphs, as appropriate.
9. Drawing number and detail references, as appropriate.
10. Field dimensions and conditions, as appropriate.
11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
12. Contractor's signature.
13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Architect.
1. Attachments shall be electronic files in PDF format.
D. Architect's Action: Architect will review each RFI, determine action required, and respond. Allow seven working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.
1. The following Contractor-generated RFIs will be returned without action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Architect's action may include a request for additional information, in which case
Architect's time for response will date from time of receipt by Architect of additional information.
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PROJECT MANAGEMENT AND COORDINATION 013100 - 5
3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract
Sum may be eligible for Contractor to submit Change Proposal according to Section
012600 "Contract Modification Procedures."
a. If Contractor believes the RFI response warrants change in the Contract Time or the
Contract Sum, notify Architect in writing within 10 days of receipt of the RFI response.
1.7 DIGITAL PROJECT MANAGEMENT PROCEDURES
A. Use of Architect's Digital Data Files: Digital data files of Architect's CAD drawings will be available by Architect for Contractor's use during construction.
1. Digital data files may be used by Contractor in preparing, Shop Drawings, and Project record Drawings.
2. Architect makes no representations as to the accuracy or completeness of digital data files as they relate to Contract Drawings.
3. Digital Drawing Software Program: Contract Drawings are available in AutoCAD 2023.
4. Contractor shall execute a data licensing agreement in the form of Agreement form acceptable to Owner and Architect.
5. A fee payable by the Contractor to obtain Architects CAD Drawings.
B. PDF Document Preparation: Where PDFs are required to be submitted to Architect, prepare as follows:
1. Assemble complete submittal package into a single indexed file incorporating submittal requirements of a single Specification Section and transmittal form with links enabling navigation to each item.
2. Name file with submittal number or other unique identifier, including revision identifier.
3. Certifications: Where digitally submitted certificates and certifications are required, provide a digital signature with digital certificate on where indicated.
1.8 PROJECT MEETINGS
A. General: Attend and participate in all meetings and conferences at Project site unless otherwise indicated.
1. Attendees: Contractors project manager is mandatory. Foreman, sub-contractors or suppliers are required to attend when their presence is requested.
2. Agenda: Prepared by Architect or Owner.
3. Minutes: prepared by Architect or Owner.
B. Preconstruction Conference: Architect and Owner will schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than 15 days after execution of the Agreement.
1. Attendees: Authorized representatives of Owner Architect, and their consultants;
Contractor and its superintendent; major subcontractors; suppliers; and other concerned
Erie County Medical Center Corporation
Tank #13 Removal and Replacement
April 2026
PROJECT MANAGEMENT AND COORDINATION 013100 - 6
parties shall attend the conference. Participants at the conference shall be familiar with
Project and authorized to conclude matters relating to the Work.
2. Agenda: Discuss items of significance that could affect progress, including the following:
a. Responsibilities and personnel assignments.
b. Tentative construction schedule.
c. Phasing.
d. Critical work sequencing and long lead items.
e. Designation of key personnel and their duties.
f. Lines of communications.
g. Use of web-based Project software.
h. Procedures for processing field decisions and Change Orders.
i. Procedures for RFIs.
j. Procedures for testing and inspecting.
k. Procedures for processing Applications for Payment.
l. Distribution of the Contract Documents.
m. Submittal procedures.
n. Preparation of Record Documents.
o. Use of the premises and existing building.
p. Work restrictions.
q. Working hours.
r. Owner's occupancy requirements.
s. Responsibility for temporary facilities and controls.
t. Procedures for moisture and mold control.
u. Procedures for disruptions and shutdowns.
v. Construction waste management and recycling.
w. Parking availability.
x. Office, work, and storage areas.
y. Equipment deliveries and priorities.
z. First aid.
aa. Security.
bb. Progress cleaning.
3. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.
C. Progress Meetings: Attend progress meetings at biweekly intervals or as mutually agreed upon by all parties. Architect or Owner will conduct meetings
1. Attendees: In addition to representatives of Owner and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: prepared by Architect or Owner and can include the following:
a. Contractor's Construction Schedule: Contractor to provide hardcopies of the updated construction…