13-2026-10-26 TECH W-Reed-Specifications-Final-9.pdf

PDF 9 MB Posted

Attached to
Edison Street, West Reed Avenue, and Dale Street Sewer Repairs
Solicitation number
2041
Issued by
Arlington County, Alexandria City, Virginia

About this file

This document is a 100% Design Specifications manual for the West Reed Avenue and Dale Street infrastructure project prepared by the City of Alexandria, Virginia, dated August 13, 2025, with an effective date of August 21, 2025. The specifications establish comprehensive technical and procedural requirements for the design and construction of improvements to West Reed Avenue and Dale Street, including storm drainage systems, pavement resurfacing, erosion and sediment control, landscape restoration, traffic control staging, and utility coordination. The project encompasses 42 drawing sheets covering existing conditions, demolition plans, proposed improvements, storm drain profiles, erosion control measures across initial and final phases, landscape plans, tree protection details, maintenance of traffic plans across six construction stages, and supporting technical details. The specifications are organized into 33 technical sections across multiple divisions addressing procurement requirements, general construction requirements, existing conditions, concrete work, special construction, earthwork, exterior improvements, and utility installations. Civil Engineer Garry Truyens (License No. 0402062282) is identified as the Engineer of Record responsible for all major sections.

The specifications establish detailed requirements for contractor responsibilities including mobilization, traffic control maintenance, preconstruction surveys with video documentation, utility coordination and protection, temporary tree and plant protection with penalties for encroachments ranging from $1,000 to $1,000 per caliper inch for significant damage, erosion and sediment control, final cleaning and site restoration, and submission of as-built drawings and certified surveys. Contractors must comply with City of Alexandria standards, Virginia Department of Transportation specifications and standards, ANSI A300 standards for tree work, and all applicable federal, state, and local safety and environmental regulations. The contract requires contractors to obtain all necessary permits at no cost, establish a preconstruction conference with the City Engineer and Arborist, attend bi-weekly progress meetings, and provide monthly work plan updates. No set-asides or specific pricing information is identified in these specifications, which function as the technical guidelines governing contract execution rather than the formal solicitation or award documents.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

West Reed Avenue and Dale Street

100% Design Specifications

City of Alexandria

August 13, 2025 August 21, 2025

West Reed & Dale St.

100% Specifications

TABLE OF CONTENTS – 000100 Page 1 of 5

SECTION 000100 – TABLE OF CONTENTS

PART 1 – GENERAL

Sect. No. Section Title Section Description Source

Division 00- Procurement and Contracting Requirements 000100 Table of Contents Tabulated list of Sections City of Alexandria 000107 Seals Page For seals of design professionals on Project Manual.

City of Alexandria

000115 List of Drawing Sheets List of Drawings City of Alexandria Division 01- General Requirements 010000 General Requirements City of Alexandria 011000 Summary Summary of the Work, phased construction, purchase contracts, Owner-furnished products, access to site, and work restrictions.

City of Alexandria

011100 Execution Requirements

General requirements for product installation, cutting and patching, protection, field engineering, and progress cleaning.

City of Alexandria

011200 As-Built Drawings and Survey

Administrative requirements for project records and survey.

City of Alexandria

011300 Closeout Procedures Contract closeout including substantial completion and final completion procedures, warranties and final cleaning.

City of Alexandria

011400 Temporary Tree and Plant Protection

Construction phase tree and plant protection, trimming, protection zone fencing and pruning.

City of Alexandria

012000 Unit Prices Provisions for unit prices. City of Alexandria 012900 Payment Procedures Provisions of the City’s procedures to process payments.

City of Alexandria

013000 Project Management and Coordination

Administrative requirements for project meetings; preconstruction, preinstallation, and project closeout conferences;

RFIs; and project websites.

TABLE OF CONTENTS – 000100 Page 2 of 5

013200 Construction Progress Documentation

Provisions to document construction progress.

City of Alexandria

014000 Construction Progress Documentation

Contractor's construction schedule including Gantt charts and CPM schedules;

Contractor's reports.

City of Alexandria

014100 Structural Tests & Special Inspections

Contract’s 3rd party testing and inspection requirements for structures

City of Alexandira

015000 Submittal Procedures Procedures for action and informational submittals including delegated-design submittals and submittals schedule.

City of Alexandria

016000 Traffic Control Requirements for maintenance of vehicular and pedestrian traffic during construction.

City of Alexandria

017000 Quality Requirements Quality-assurance and -control requirements, special tests and inspections, and Contractor's quality-control plan.

City of Alexandria

017700 Closeout Procedures Provisions for project closeout procedures.

City of Alexandria

018000 Mobilization Provisions for mobilization.

City of Alexandria

019000 Temporary Facilities and Controls

Temporary utilities and facilities for construction support, security, and protection.

City of Alexandria

019000.1 Temporary Facilities

and Controls – Sandbag Cofferdam

Material and construction requirements for temporary cofferdam.

AECOM

Division 02- Existing Conditions 020250 Existing Utilities and

Structures Certain information regarding the reputed presence, size, character, and location of existing Underground Facilities, test pits.

City of Alexandria

024114 Pavement Removal Removal of existing pavement including existing sidewalk, curb and gutter, asphalt pavement, concrete pavement and concrete entrance & apron.

024116 Structure Demolition Demolition of site City of Alexandria

TABLE OF CONTENTS – 000100 Page 3 of 5

024116 Structure Demolition Demolition of site improvements, removal of below-grade construction, and storm drain structures and pipes.

City of Alexandria

024119 Selective Demolition Demolition of selected portions of existing buildings, structures, and associated site improvements.

City of Alexandria

Division 03- Concrete 031100 Concrete Forming Formwork for cast-in-place concrete with shoring, bracing, and anchorage, accessories, and stripping.

AIA MasterSpec

032000 Concrete Reinforcing Materials and installation of deformed reinforcing steel bars and accessories for cast-in-place concrete.

AIA MasterSpec

033000 Cast-In-Place Concrete General building and structural applications;

concrete mixtures, formwork, reinforcing, finishing, and curing.

City of Alexandria

Division 13 – Special Construction 135140 Traffic Control Requirements for maintenance of vehicular and pedestrian traffic during construction.

City of Alexandria

Division 31- Earthwork 311000 Site Clearing Clearing, grubbing, vegetation protection, stripping and stockpiling topsoil and rock, and disconnecting utilities.

City of Alexandria

312000 General Earthwork Grading, excavation, drainage course, subgrade preparation and backfill for various work around the site.

City of Alexandria

312000.1 Imported Suitable

Backfill

Backfill material imported to the site at the direction of the City

City of Alexandira

TABLE OF CONTENTS – 000100 Page 4 of 5

312000.2 Imported No. 57 Stone Backfill material imported

to the site at the direction of the City

City of Alexandira

312002 Trenching Supplemental instructions to those provided in general earthwork for trench excavation and dewatering and backfilling of trenches and compaction.

City of Alexandria

312003 Pavement and Walkway Earthwork

Supplemental instructions to those provided in general earthwork for excavation and placement

City of Alexandria

Sect. No. Section Title Section Description Source of fill, stone and sub-base below walks and pavements, compaction of fill, stone or sub-base courses under walks and pavement.

312319 Dewatering Temporary construction dewatering requirements for ground-water control.

City of Alexandria

315000 Excavation Support and Protection

Temporary Excavation Support and Protection systems.

City of Alexandria

Division 32- Exterior Improvements 321216 Asphalt Paving Replacement of asphalt pavement.

City of Alexandria

321723 Pavement Markings Pavement markings and striping along roadway.

City of Alexandria

323113 Chain-link Fence New Chain-link fence ordered by the City

City of Alexandria

323300 Site Furnishings (Structures)

Salvaged or New wooden pergolas and shed

City of Alexnadira

329113 Soil Preparation Planting soils specified according to quantities of amendments (compost, lime, sulfur, fertilizer, etc.); layered soil assemblies

TABLE OF CONTENTS – 000100 Page 5 of 5

329114 Riprap Classifications, material standards, and installation of ripraps.

VDOT

329115 Stone for Masonry, Riprap, Porous Backfill, and Gabions

Aggregate used in construction of masonry, erosion control, or drainage structures.

VDOT

329116 Geosynthetics and Low-Permeability Liners

Artificial fiber textile products used for construction, and low-permeability liners for stormwater management.

VDOT

329200 Turf and Grasses Seeded, sodded, plugged, and sprigged turf and meadows; pesticides;

erosion-control materials;

turf renovation.

City of Alexandria

329300 Plants Plants and plantings onsite. City of Alexandria

329416 Landscape Timbers Requirements for Landscape Timbers

City of Alexandira

329600 Transplanting Transplanting any plants that may be moved onsite.

AIA MasterSpec

Division 33- Utilities

Sect. No. Section Title Section Description Source

330500 Common Work Results for Utilities

Materials and installation processes for general utilities.

City of Alexandria

331100.10 Piping General

Provisions

Water piping general provisions

Virginia American Water

331100.11 Piping Specialties Water piping specialties Virginia American Water

331100.12 Fire Hydrants Fire hydrant install Virginia American Water

334200 Stormwater Conveyance

Storm drainage piping and fittings, connections, manholes, inlets, endwalls, cleanouts, and catch basins.

City of Alexandria

334200.1 Inline Check Valves Storm sewer pipe backflow

prevention.

Tideflex or Approved Equal Check Valve

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

END OF SECTION – 000100

City of Alexandria 100% Specifications

SEALS PAGE – 000107 Page 1 of 1

SECTION 000107 – SEALS PAGE

1.1 DESIGN PROFESSIONALS OF RECORD

A. Civil Engineer: Engineer on Record.

1. Name: Garry Truyens

2. License No.: 0402062282

3. Responsible for Sections: 000100, 000107, 000115, 010000, 011000, 011100, 011200, 011300, 011400, 012000, 012900, 013000, 013200, 014000, 015000, 016000, 017000, 017700, 018000, 019000, 019000.1, 020250, 024114, 024116, 024119, 031100, 032000, 033000, 135140, 311000, 312000, 312002, 312003, 312319, 315000, 321216, 321723, 329113, 329114, 329115, 329116, 329200, 329300, 329600, 330500, 331100.10, 331100.11, 331100.12, 334200, 334200.1,.

PART 2 – PRODUCTS (Not Used)

PART 2 – EXECUTION (Not Used)

END OF SECTION – 000107

LIST OF DRAWING SHEETS – 000115 Page 1 of 2

SECTION 000115 – LIST OF DRAWING SHEETS

1.1 LIST OF DRAWINGS

A. Drawings consist of the Contract Drawings and other drawings listed on the Table of

Contents page of the separately bound drawing set titled 100% Plan, dated January

2025, as modified by subsequent Addenda and Contract modifications.

Sheet No. Sheet Title

1 Cover

2 General Notes

3 Existing Conditions Plan (1 of 2)

4 Existing Conditions Plan (2 of 2)

5 Structure Tables

6 Storm Drain Inlet Drainage Area Map

7 Demolition Plan (1 of 2)

8 Demolition Plan (2 of 2)

9 Proposed Conditions Plan (1 of 2)

10 Proposed Conditions Plan (2 of 2)

11 Concrete Resurfacing

12 Storm Drain Profiles

13 Storm Drain Profiles

14 Storm Drain Profiles

15 Storm Drain Profiles

16 Storm Drain Profiles

17 Erosion And Sediment Control - Initial Phase (1 of 2)

18 Erosion And Sediment Control - Initial Phase (2 of 2)

19 Erosion And Sediment Control - Final Phase (1 of 2)

20 Erosion And Sediment Control - Final Phase (2 of 2)

21 Erosion And Sediment Control Notes (1 of 2)

22 Erosion And Sediment Control Notes (2 of 2)

23 Erosion And Sediment Control Details (1 of 2)

24 Erosion And Sediment Control Details (2 of 2)

25 Landscape Plan (1 of 2)

26 Landscape Plan (2 of 2)

27 Landscape And Tree Protection Details

28 Maintenance of Traffic Plan - Stage 1

29 Maintenance of Traffic Plan - Stage 2

30 Maintenance of Traffic Plan - Stage 3

31 Maintenance of Traffic Plan - Stage 4

32 Maintenance of Traffic Plan - Stage 5

33 Maintenance of Traffic Plan - Stage 6

34 Details

LIST OF DRAWING SHEETS – 000115 Page 2 of 2

35 Details

36 Details

37 Details

38 Boring Logs

39 Tree Survey (1 of 2)

40 Tree Survey (2 of 2)

41 Minor Water Quality Impact Assessment

42 Water Quality Impact Assessment Form

PART 2 – PRODUCTS (Not Used)

PART 3 – EXECUTION (Not Used)

END OF SECTION – 000115

GENERAL REQUIREMENTS – 010000 Page 1 of 11

SECTION 010000 – GENERAL REQUIREMENTS

1.1 SUMMARY

A. Public Utility Installations and Structures:

1. Public utility installations and structures shall be understood to include all poles, tracks, pipes, wires, conduits, vaults, manholes, and all other appurtenances and facilities pertaining thereto whether owned or controlled by the Owner (City of Alexandria), other governmental bodies or privately owned, used to provide gas, electricity, telephone, sewerage, drainage, water or other public or private property which may be affected by the work shall be deemed included hereunder.

2. The Contractor shall be responsible for all coordination with the utility companies.

3. The Contract Documents contain data relative to existing public or private utility installations and structures above and below the ground surface.

These data are not guaranteed as to their completeness or accuracy, and it is the responsibility of the Contractor to make his own investigations to inform himself fully of the character, condition, and extent of all such installations and structures as may be encountered and as may affect the construction operations.

4. The Contractor shall protect all public or private utility installations and structures from damage during the work. Access across any buried installation or structure shall be made only in such locations and by means approved by the Utility Owner. The Contractor shall so arrange his operations as to avoid any damage to these facilities. All required protective devices and construction shall be provided by the Contractor at his expense. All existing utilities damaged by the Contractor shall be repaired by the Contractor, at his expense, as directed by the Utility Owner. No separate payment shall be made for such protection or repairs to public utility installations or structures.

5. Where utility installations or structures owned or controlled by the Owner (City of Alexandria) or other governmental body are encountered during the course of the work, and are not indicated on the Plans or in the Specifications, and when, in the opinion of the COTR, removal, relocation, replacement or rebuilding is necessary to complete the work under this Contract, such work shall be accomplished by the utility having jurisdiction, or such work may be approved, in writing by the City’s technical representative Engineer, for the Contractor to accomplish. If such work is accomplished by the utility

GENERAL REQUIREMENTS – 010000 Page 2 of 11 having jurisdiction it will be carried out expeditiously and the Contractor shall give full cooperation to permit the utility to complete the removal, relocation, replacement or rebuilding as required. If such work is accomplished by the Contractor, it will be in accordance with the General and Supplemental General Conditions.

6. All Owner (City of Alexandria) and other governmental utility departments and other Owners of public or private utilities which may be affected by the work will be informed in writing by the Contractor within two weeks after the execution of the Contract or Contracts covering the work. Such notice will set out, in general, and direct attention to the responsibilities of the Owner (City of Alexandria) and other governmental utility departments and other Owners of public or private utilities for such installations and structures as may be affected by the work and will be accompanied by one set of Plans and Specifications covering the work under such Contract(s).

7. In addition to the general notice given, the Contractor shall give written notice to Owner (City of Alexandria) and other governmental utility departments and other Owner of public or private utilities of the location of his proposed construction operations, at least one (1) week in advance of breaking ground in any area or on any unit of the work.

8. The maintenance, repair, removal, relocation or rebuilding of public or private utility installations and structures, when accomplished by the Contractor as herein provided, shall be done by methods approved by the Utility Owner at no additional cost.

1.2 PRECONSTRUCTION SURVEY

A. Before any work is performed at the site by the Contractor a joint preconstruction survey will be performed. The preconstruction survey is to be provided by the Contractor. The Contractor is to provide the viewing software supporting the video images. The Contractor, COTR and Owner will review the existing conditions jointly and a video record (DVD) of this review will be made by the Contractor for record purposes. The Contractor is to retain his/her own copies of the video record. Following completion of the Work, the video record may be used to compare conditions prior to construction to those conditions following construction to ascertain that the site has been properly restored.

1.3 CONSTRUCTION RECORDS AND PHOTOGRAPHS

GENERAL REQUIREMENTS – 010000 Page 3 of 11

A. Contractor shall keep accurate records on the construction progress (type of Work performed, extent of repairs, location, etc.) on a day-to-day basis. A qualified representative of Contractor shall enter the progress into a construction logbook. Entries and notations shall be made in a neat and legible manner. These logs shall be delivered to COTR upon completion of the construction.

B. Provide pre-construction photographs prior to commencement of work on the site.

Provide exposures of the area where the Work is to take place as designated by the COTR. Take two (2) photographs at each project location. One photograph should be looking in the upstream direction and the other shall be taken looking in the downstream direction. Each photograph shall be labeled identifying the relevant features and is to indicate the date and time stamp and the direction of the view.

Provide digital construction photographs during the progress of the Work. Take two

(2) weekly exposures at each project location starting 1 month after the date of the pre-construction photographs and continuing as long as the Work is in progress. Ensure each photo is annotated in such a manner that a reviewer can clearly understand precisely where the photo was taken and what aspect or view of the Work is presented. Take a minimum of four (4) exposures at each project location upon Final Acceptance and Completion of the Work. The location of the photographs is to be directed by the COTR. For the Work of the Contract, digital images date and time stamp shall be provided as follows:

1. Pre-construction – Minimum of ten (10) exposures.

2. Construction (Monthly) – Minimum of ten (10) exposures per month.

3. Post construction – Minimum of twenty (20) exposures.

1.4 SHOP DRAWINGS AND SUBMITTALS

A. GENERAL

The Contractor shall furnish one (1) digital copy and descriptive literature for all manufactured or fabricated items with each submittal to the COTR for review and approval. Additional information such as special drawings, assembly, arrangement and configuration, schedules, and calculations, shall be provided when specifically required in the Technical Specifications.

The term “shop drawings” shall mean drawings, prints, sketches, descriptive literature, test reports, samples, calculations, schedules, material lists, material safety data sheets, GENERAL REQUIREMENTS – 010000 Page 4 of 11 and items of similar meaning. No material shall be fabricated or shipped unless the applicable drawings or submittals have been reviewed and approved by the COTR.

Contractor shall review and check drawings and submittals. Contractor shall indicate his/her review by initials and date, and shall also reference each applicable item, section, or division of the Specifications. If the drawings or submittals deviate from the Contract Drawings, Contractor shall advise COTR, in writing, of the deviation and the reasons therefore.

In the event the Contractor obtains COTR’s acceptance for the use of material or equipment other than that which is shown on the Contract Drawings or specified, Contractor shall, at his/her own expense, and using methods acceptable to COTR, make any changes to structures, facilities, and/or piping, that may be necessary to accommodate this equipment.

The shop drawings and submittals listed in these specifications are required to be prepared by the Contractor. Contractor’s refusal to cooperate and provide such requirements may serve as the basis for the Owner to terminate the Contract.

B. WORK PLAN REQUIREMENTS

1. The Contractor shall prepare and submit to the Owner a written Draft Work Plan within ten (10) days after receipt of the Notice to Proceed.

2. The Contractor shall present the COTR, the primary schedule sequence of construction activities within ten (10) days after receipt of the Notice to Proceed.

3. The Contractor shall confirm the equipment to be used for the entire project. The Contractor shall provide noise reduction measures on all operating machinery, equipment and systems.

4. The Contractor shall incorporate the Project Schedule and related activities, permit application review and approved traffic control plan implementation, site dewatering, flow diversion and controls, public access and use, erosion and sedimentation measures, and public notification with the Work Plan.

Contractor shall also include details associated with the means and methods, as well as timing of excavations.

5. Contractor shall attend bi-weekly progress meetings,

6. Contractor shall submit a two week look ahead schedule for discussion at each bi-weekly progress meeting.

7. Contractor shall revise and submit Work Plan updates every month.

1.5 PERMITS

GENERAL REQUIREMENTS – 010000 Page 5 of 11

A. Contractor shall obtain, at his expense, all permits, approvals, and licenses required by all local, state, and federal agencies having jurisdiction. Permits issued by the City will be issued at no cost to the Contractor.

1.6 CLEANING

A. Contractor shall at all times keep the construction site and the surrounding area presentable to the public, clear and clean of rubbish and debris caused by or resulting from the Contractor’s operation. At completion of the Work each day, Contractor shall remove all the rubbish, debris, tools, equipment, temporary Work and surplus materials, from and about the premises, and shall leave the site clean and ready for use.

On a daily basis, all waste and excess materials shall be disposed of off the project site and at no additional expense to Owner. In no case shall waste materials (any removed concrete, piping, equipment, etc.) be buried on the site. Burning is not permitted.

After completion of all Work and before final acceptance of the Work, Contractor shall thoroughly clean all equipment and materials and shall remove all foreign matter such as grease, dirt, labels, stickers, etc., from the exterior of the piping, equipment, and all associated fabrication.

1.7 UTILITY SERVICE

A. Contractor shall arrange for and pay all costs for utility services that may be required for the Work.

1.8 PLANS AND SPECIFICATIONS

A. Contractor To Check Plans and Data:

1. Contractor shall verify all dimensions, quantities and details shown on the Plans, Supplementary Drawings, Schedules, Specifications or other data received from the COTR, and shall notify him of all errors, omissions, conflicts, and discrepancies found therein. Failure to discover or correct errors, conflicts or discrepancies shall not relieve the Contractor of full responsibility for unsatisfactory work, faulty construction or improper operation resulting there from nor from rectifying such conditions at his own expense. He will not be allowed to take advantage of any errors or omissions, as full instructions will be furnished by the COTR, should such errors or omissions be discovered. All schedules are given for the convenience of the COTR and

GENERAL REQUIREMENTS – 010000 Page 6 of 11 the Contractor and are not guaranteed to be complete. The Contractor shall assume all responsibility for the making of estimates of the size, kind, and quality of materials and equipment included in work to be done under the Contract.

1.9 TEMPORARY STRUCTURES

A. Responsibility for Temporary Structures

1. In accepting the Contract, the Contractor assumes full responsibility for the sufficiency and safety of all temporary structures or work and for any damage which may result from their failure or their improper construction, maintenance or operation and will indemnify and save harmless the Owner (City of Alexandria) and COTR, Owner’s Consultants from all claims, suits or actions and damages or costs of every description arising by reason of failure to comply with the above provisions.

B. Temporary Fences

1. If, during the course of the work, it is necessary to remove or disturb any fence or part thereof, the Contractor shall, at his own expense, if so approved by the COTR, provide a suitable temporary fence which shall be maintained until the permanent fence is replaced. The COTR shall be solely responsible for the determination of the necessity for providing a temporary fence and the type of temporary fence to be used.

1.10 SAFETY

A. Accident Prevention

1. Precautions shall be exercised at all times for the protection of persons and property. The safety provisions of applicable laws, building and construction codes shall be observed. The Contractor shall comply with the U.S.

Department of Labor Safety and Health Regulations for construction promulgated under the Occupational Safety and Health Act of 1970 (PL 9 1-596), and under Section 107 of the contract Work Hours and Safety Standards Act (PL-54), except where state and local safety standards exceed the federal requirements and except where state safety standards have been approved by the Secretary of Labor in accordance with provisions of the Occupational Safety and Health Act.

B. First Aid

1. The Contractor shall keep upon the site, at each location where work is in progress, a completely equipped first aid kit and shall provide ready access thereto at all times when people are employed on the work.

GENERAL REQUIREMENTS – 010000 Page 7 of 11

1.11 LINES AND GRADES

A. Grade

1. All work under this Contract shall be constructed in accordance with the lines and grades shown on the Plans, or as otherwise approved by the COTR. The full responsibility for keeping alignment and grade shall rest upon the Contractor.

2. The Contractor shall provide copies of all construction stake-out computations (cut sheets) to the COTR prior to the installation of improvements.

B. Safeguarding Marks

1. The Contractor shall safeguard all points, stakes, grade marks, monuments and benchmarks made or established on the work, bear the cost of reestablishing them if disturbed, and bear the entire expense of rectifying work improperly installed due to not maintaining or protecting or to removing without authorization such established points, stakes and marks.

2. The Contractor shall safeguard all existing and known property corners, monuments and marks adjacent to but not related to the work and, if required, shall bear the cost of reestablishing them if disturbed or destroyed.

1.12 ADJACENT STRUCTURES AND LANDSCAPING

A. Responsibility

1. The Contractor shall be entirely responsible and liable for all damage or injury as a result of his operations to all adjacent public and private property, structures of any kind and appurtenances thereto met with during the progress of the work. The cost of protection, replacement in their original locations and conditions or payment of damages for injuries to such adjacent public and private property and structures affected by the work, whether or not shown on the Plans, and the removal, relocation and reconstruction of such items called for on the Plans or specified shall be included in the various Contract Items and no separate payments will be made therefore.

2. Contractor is expressly advised that the protection of buildings, structures, tunnels, tanks, pipelines, etc. and related work adjacent and in the vicinity of his operations, wherever they may be, is solely his responsibility.

Conditional inspection of buildings or structures in the immediate vicinity of the project which may reasonably be expected to be affected by the Work shall be performed by and be the responsibility of the Contractor.

3. Contractor shall, before starting operations, make an examination of the interior and exterior of the adjacent structures, buildings, facilities, etc., and

GENERAL REQUIREMENTS – 010000 Page 8 of 11 record by notes, measurements, photographs, etc., conditions which might be aggravated by open excavation and construction. Repairs or replacement of all conditions disturbed by the construction shall be made to the satisfaction of the Director of Transportation & Environmental Services and COTR. This does not preclude conforming to the requirements of the insurance underwriters. Copies of surveys, photographs, reports, etc., shall be submitted to the COTR.

4. Prior to the beginning of any excavations the Contractor shall advise the COTR of all buildings or structures on which he intends to perform work or which performance of the project work will affect.

B. Protection of Trees

1. All trees and shrubs shall be adequately protected by the Contractor to the satisfaction of the COTR and the City of Alexandria Arborist.

C. Lawn Areas

1. Project site areas shall be left in as good condition as before the starting of the work. Where sod is removed, it shall be carefully removed, and later replaced with same or like kind.

D. Restoration of Fences

1. Any fence, or part thereof, that is damaged or removed during the course of the work shall be replaced or repaired by the Contractor and shall be left in as good a condition as before the starting of the work. The manner in which the fence is repaired or replaced and the materials used in such work shall be subject to the approval of the COTR. The cost of all labor, materials, equipment, and work for the replacement or repair of any fence shall be deemed included in the appropriate Contract Item or items, or if no specific Item is provided therefore, as part of the overhead cost of the work and no additional payment will be made therefore. Private fences removed from within the Right-of-Way shall be replaced as described above at the Right-of- Way line.

1.13 PROTECTION OF WORK AND PUBLIC

A. Barriers and Lights

1. During the prosecution of the work, the Contractor shall put up and maintain at all times such barriers and lights as will effectually prevent accidents. The Contractor shall provide suitable barricades, lights, "danger" or "caution" signs at all places where the work causes obstructions or constitutes in any way a hazard to the public in accordance with state and local requirements.

GENERAL REQUIREMENTS – 010000 Page 9 of 11

B. Smoke Prevention

1. The Contractor shall use hard coal, coke, oil or gas as fuel for equipment generating steam. A strict compliance with ordinances regulating the production and emission of smoke will be required. No open fires will be permitted.

C. Noise

1. The Contractor shall eliminate noise to as great an extent as practicable at all times. Air compressing plants shall be equipped with silencers and the exhaust of all gasoline motors or other power equipment shall be provided with mufflers. The Contractor shall strictly observe the City of Alexandria Noise Control Code, Title II, Chapter 5.

2. Except in the event of an emergency, work shall be done within the regular working hours specified in the City of Alexandria Noise Control Code, Title II, Chapter 5. If the proper and efficient prosecution of the work requires operations outside of these hours, the written permission of the Director of Transportation & Environmental Services must be obtained.

D. Access to Public Services

1. Neither the materials excavated nor the materials or plant used in the construction of the work shall be so placed as to prevent free access to all fire hydrants, valves or manholes, or access required by emergency vehicles and/or personnel.

E. Dust Prevention

1. The Contractor shall prevent dust nuisance from his operations by keeping the construction areas sprinkled with water. Allaying dust in roadway construction areas shall be in accordance with VDOT Specification Section 511.

1.14 CLEANING

A. During Construction

1. During construction of the work, the Contractor shall, at all times, keep the site of the work and adjacent premises as free from material, debris and rubbish as is practicable and shall remove the same from any portion of the site if, in the opinion of the COTR, such material, debris, or rubbish constitutes a nuisance or is objectionable.

2. The Contractor shall remove from the site all of his surplus materials and

GENERAL REQUIREMENTS – 010000 Page 10 of 11 temporary structures when no further need therefore develops.

3. The Contractor shall be responsible and liable for all spillage and incur all associated costs including, but not limited to, costs related to repair and maintenance resulting from damages thereof.

B. Final Cleaning

1. At the conclusion of the work, all erection plant, tools, temporary structures and materials belonging to the Contractor shall be promptly taken away, and he shall remove and promptly dispose of all water, dirt, rubbish or any other foreign substances. The Contractor shall thoroughly clean all piping and materials installed by him prior to final inspection.

1.15 MISCELLANEOUS

A. Use of Chemicals

1. All chemicals used during project construction or furnished for project operation, whether herbicide, pesticide, disinfectant, polymer, reactant, or of other classification, must show approval of either Environmental Protection Agency (EPA) or United States Department of Agriculture (USDA) for its intended use. Use of all such chemicals and disposal of residues shall be in strict conformance with instructions.

B. Protection Against Siltation and Bank Erosion

1. The Contractor shall arrange his operations to minimize siltation on construction sites.

2. The Contractor, at his own expense, shall remove any siltation deposits and correct any erosion problems as determined by the COTR which results from his construction operations.

3. The Contractor shall vacuum clean all new and existing storm drainage facilities and discharge points affected by construction prior to final acceptance by the Director of Transportation & Environmental Services.

C. Protection of Wetland Areas

1. The Contractor shall properly dispose of all surplus material, including soil, in accordance with Local, State and Federal regulations. Under no circumstances shall surplus material be disposed of in wetland areas as defined by the Virginia Department of Environmental Quality.

D. Existing Facilities

1. The work shall be so conducted to maintain existing facilities in operation insofar as is possible. Requirements and schedules of operations for

GENERAL REQUIREMENTS – 010000 Page 11 of 11 maintaining existing facilities in service during construction shall be as described in these Specifications.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 GENERAL

A. Construction Documents: Execution of the Work shall be governed by the documents listed here in order of precedence:

1. The Contract

2. Technical Specifications

3. Contract Drawings

4. City of Alexandria, VA, Department of Transportation & Environmental Services, Design and Construction Standards, July 1989 (City Standards)

5. Virginia Department of Transportation, Road and Bridge Specifications, 2020 (VDOT Specifications)

6. Virginia Department of Transportation, Road and Bridge Standards, Volumes I & II, 2008 with latest Revisions (VDOT Standards)

B. In case of discrepancy in the figures, in the Drawings or in the Specifications, the matter shall be promptly submitted to the COTR who shall promptly make a determination in writing.

3.2 Hours of Operation:

All work shall be carried out between the hours of 7:00AM and 6:00 PM, Monday thru Friday, and 9:00AM and 6:00PM, on Saturdays.

END OF SECTION - 010000

SUMMARY – 011000 Page 1 of 2

SECTION 011000 – SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Use of Premises.

2. Specification Formats and Conventions.

1.2 USE OF PREMISES

A. General: Contractor shall have full use of premises, as shown in the contract plans, in conformance with the limitations stipulated by Virginia Department of Environmental Quality for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Owner's (City of Alexandria) right to perform work or to retain other contractors on portions of Project.

B. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine construction operation within the Project Limits-of- Disturbance as noted on the Drawings.

2. Keep approaches to the premises clear and available to Owner (City of Alexandria), Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

1.3 SPECIFICATION FORMATS AND CONVENTIONS

A. Specification Format: The Specifications are organized into Divisions and Sections.

1. Division 1: Sections in Division 1 govern the execution of the Work of all Sections in the Specifications.

B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

SUMMARY – 011000 Page 2 of 2

1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.

2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.

a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION – 011000

EXECUTION REQUIREMENTS – 011100 Page 1 of 7

SECTION 011100 – EXECUTION REQUIREMENTS

1.1 SUMMARY

A. This Section includes general procedural requirements governing execution of the Work including, but not limited to, the following:

1. Construction layout.

2. Field engineering and surveying.

3. General installation of products.

4. Progress cleaning.

5. Starting and adjusting.

6. Protection of installed construction.

7. Correction of the Work.

B. See Division 1 Section "Closeout Procedures" for final cleaning.

1.2 SUBMITTALS

A. Certificates: Submit certificate signed by professional engineer certifying that location and elevation of improvements comply with requirements.

B. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept hazardous materials, for hazardous waste disposal.

C. Certified Surveys: Submit two copies signed by Virginia certified land surveyor or professional engineer.

D. Final Property Survey: Submit one hard copy and one copy in a digital format showing the Work performed and record survey data.

1.3 QUALITY ASSURANCE

A. Land Surveyor Qualifications: A professional land surveyor who is legally qualified to practice in Virginia and who is experienced in providing land-surveying services of the kind indicated.

EXECUTION REQUIREMENTS – 011100 Page 2 of 7

PART 2 - PRODUCTS (Not Used)

PART 3 – EXECUTION

3.1 EXAMINATION

A. Existing Conditions: The existence and location of site improvements, utilities, and other construction indicated as existing are not guaranteed. Before beginning work, the contractor shall investigate and verify the existence and location of all existing underground and overhead utilities and other infrastructure and systems affecting the Work.

1. Before construction, verify the location and points of connection of utility services.

2. Before construction, verify the location of all trees.

3. Before construction, verify location and extents of all right-of-way lines.

B. Existing Utilities: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning site work, investigate and verify the existence and location of underground utilities and other construction affecting the Work.

1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, and water-service piping; and underground electrical services.

2. Furnish location data for work related to Project that must be performed by public utilities serving Project site.

C. Acceptance of Conditions: Examine substrates, areas, and conditions, with Installer or Applicator present where indicated, for compliance with requirements for installation tolerances and other conditions affecting performance. Record observations.

1. Verify compatibility with and suitability of substrates, including compatibility with existing finishes or primers.

2. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Existing Utility Information: Furnish information to local utility that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction.

EXECUTION REQUIREMENTS – 011100 Page 3 of 7

B. Field Measurements: Take field measurements as required to fit the Work properly.

Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

C. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

D. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to COTR. Include a detailed description of problem encountered, together with recommendations for changing the Contract Documents.

3.3 CONSTRUCTION LAYOUT

A. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify COTR promptly.

B. General: Engage a professional Virginia registered Surveyor to lay out the Work using accepted surveying practices.

1. Establish benchmarks and control points to set lines and levels as needed to locate each element of Project.

2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.

3. Inform installers of lines and levels to which they must comply.

4. Check the location, level and plumb, of every major element as the Work progresses.

5. Notify COTR when deviations from required lines and levels exceed allowable tolerances.

6. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction.

C. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations.

D. Structure Lines and Levels: Locate and lay out control lines and levels for structures and foundations. Transfer survey markings and elevations for use with control lines and levels.

Level foundations and piers from two or more locations.

E. Record Log: Maintain a log of layout control work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, EXECUTION REQUIREMENTS – 011100 Page 4 of 7 name and duty of each survey party member, and types of instruments and tapes used.

Make the log available for reference by COTR.

3.4 FIELD ENGINEERING

A. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

B. Benchmarks: Establish and maintain a minimum of two permanent benchmarks on Project site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark.

1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.

C. Certified Survey: On completion of foundations, major site improvements, and other work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and site work.

3.5 INSTALLATION

A. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.

B. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

C. Install products at the time and under conditions that will ensure the best possible results.

Maintain conditions required for product performance until Substantial Completion.

D. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

E. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels.

F. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that

EXECUTION REQUIREMENTS – 011100 Page 5 of 7 adequate provisions are made for locating and installing products to comply with indicated requirements.

G. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.

1. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

H. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

I. Hazardous Materials: Use products, cleaners, and installation materials that are not considered hazardous.

3.6 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully.

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg. F (27 deg. C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris.

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

1. Remove liquid spills promptly.

2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

EXECUTION REQUIREMENTS – 011100 Page 6 of 7

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Burying or burning waste materials on-site will not be permitted.

Washing waste materials down sewers or into waterways will not be permitted.

H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.7 PROTECTION OF INSTALLED CONSTRUCTION

A. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Substantial Completion.

B. Comply with manufacturer's written instructions for temperature and relative humidity.

3.8 CORRECTION OF THE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes.

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

EXECUTION REQUIREMENTS – 011100 Page 7 of 7

B. All existing conditions must be restored to the original or better conditions to the satisfaction of the COTR. Any damage to the existing properties must be restored and paid for by Contractor.

C. Restore permanent facilities used during construction to their specified condition.

D. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

E. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

END OF SECTION – 011100

West Reed & Dale St.

AS-BUILT DRAWINGS AND SURVEY – 011200 Page 1 of 2

SECTION 011200 – AS-BUILT DRAWINGS AND SURVEY

1.1 SUMARY

A. This Section includes administrative and procedural requirements for Project Record Documents, including the following:

1. Record Product Data

2. Record Drawings

B. See Division 2 Sections for specific requirements for Project Record Documents of the Work in those Sections.

1.2

SUBMITTALS

A. Record Product Data: Submit one copy of each Product Data submittal.

B. Record Drawings:…