This document provides a Quality Assurance Surveillance Plan (QASP) template for a property preservation and inspection services contract. The template outlines performance objectives for property inspections, preservation, and reporting. It describes methods for surveillance, standards, procedures, and acceptance of services. Contractors must perform to minimum thresholds and correct any deficiencies. The government will inspect tasks and document any defects using a Task Discrepancy Report. Contractors must respond with corrective actions to prevent recurrence. Acceptance is based on meeting performance standards in the PWS and QASP procedures.

The related federal contract opportunity is a solicitation for property preservation and inspection services issued by the US Department of Agriculture Rural Development. Questions are due by May 6th, 2019 and proposals are due by May 28th, 2019. The government will award an Indefinite Delivery Indefinite Quantity contract with an 18-month ordering period for REO and foreclosure services. The solicitation instructions are in Attachment C.

Att C2 QASP Template

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment C2

TEMPLATE

PERFORMANCE BASED

QUALITY ASSURANCE SURVEILLANCE PLAN

PROPERTY PRESERVATION AND INSPECTION SERVICES

BASE IDIQ CONTRACT

INTRODUCTION

This Quality Assurance Surveillance Plan (QASP) has been developed to evaluate contractor actions while implementing the Performance Work Statement (PWS). It is designed to provide an effective surveillance method of monitoring contractor performance for each listed objective on the Performance Requirements Matrix in the contract. The QASP provides a systematic method to evaluate the services the contractor is required to furnish.

The contractor, and not the Government, is responsible for management and quality control actions to meet the terms of the contract. The role of the Government is quality assurance to ensure contract standards are achieved.

In this contract the quality control program is the driver for service quality. The contractor is required to develop a comprehensive program of inspections and monitoring actions. The first major step to ensuring a “self-correcting” contract is to ensure that the quality control program approved at the beginning of the contract provides the measures needed to lead the contractor to success.

Once the quality control program is approved, careful application of the process and standards presented in the remainder of this document will ensure a robust quality assurance program

The Performance Requirement Summary (PRS), paragraph 7, along with contractor’s proposed requirements are stated below:

Performance Standards Summary

Performance Objectives
PWS Para
Performance Threshold

(Minimum Acceptable) Method of Surveillance

Objective I: PROPERTY INSPECTIONS

2.1.1 Perform Property Inspections

OBJECTIVE 2: PROPERTY PRESERVATION

OBJECTIVE 3: REPORTS

OBJECTIVE 6:

TRANSITION IN/OUT

SURVEILLANCE

The Government will evaluate the performance objectives through surveillance as reflected above and in the PWS by reviews and acceptance of work products and services.

STANDARD

The Contractor shall perform all work required in a satisfactory manner in accordance with the appropriate PWS paragraph. The QA shall not consider the services complete until all deficiencies have been corrected. The Contracting Officer’s Representative (COR) or shall notify the Contracting Officer (CO) for appropriate action if any of the above performance objectives are not in accordance with acceptable AQL.

PROCEDURES

The COR will inspect all tasks required by the contract to ensure Contractor compliance with the contract requirements. Inspection results will be recorded in a Surveillance Log noting the date, time and result of inspection or verification.

The COR will document all defects using a “Task Discrepancy Report (TDR)”. The COR will verbally notify the Contract Specialist (CS) of the defect and will submit a copy of the TDR as an Action Memo via email to the CO and CS. The COR will ensure the TDR is completed in its entirety and coordinated through the Contracting Officer. The Contractor will also be furnished a copy of the TDR. The Contractor shall furnish their response to the TDR. The Contractor’s response will address the accuracy and validity of the defect, planned corrective action and actions to prevent recurrence. The TDR information will be included when assessing the Contractor’s overall performance (i.e., past performance assessments, exercise of options, etc.).

If any of the services do not conform to the contract requirements, the Government may require the Contractor to perform the services again in conformity with contract requirements. The Contractor must correct the defect(s) within agreed upon timeframes. The COR shall not certify satisfactory performance for the contract until all defects have been corrected.

When the defects in services cannot be corrected by re-performance, the Government may:

1) Require the Contractor to take necessary action to ensure that future performance conforms to contract requirements; and,

2) Reduce the contract price to reflect the reduced value of the services performed.

The COR shall, in addition to providing documentation to the CO, maintain a complete quality assurance file. The file will contain copies of all reports, evaluations, recommendations, and any actions relating to the Government’s performance of the quality assurance function, including originals of all surveillance activity checklists. All such records will be retained for the life of the contract. The COR shall forward these records to the CO at completion or termination of the contract.

The COR shall upload a copy of the Surveillance Log as an Action Memo and email to the CO every three months.

ACCEPTANCE OF SERVICES

Acceptance of services shall be based upon compliance with performance standards described in the PWS and surveillance procedures described in this QASP. Prior to approving/certifying any Contractor invoices, the COR will verify that all invoiced services have been performed in compliance with contract requirements. The COR shall not certify satisfactory performance for the contract until all defects have been corrected.

[ATTACHMENTS: SURVEILLENCE LOG & TASK DESCREPANCY REPORT]

SURVEILLANCE LOG

PROJECT TITLE: PROPERTY PRESERVATION AND INSPECTION SERVICES

For Quarter Period of (circle) Q1 (July-Sep) Q2 (Oct-Dec) Q3 (Jan-Mar) Q4 (Apr-Jun) Year _____

Performance Standard Objectives

PWS

Ref.

Method of Surveillance

Date Accomplished

Compliance Results

COR NAME: SIGNATURE DATE

Task Discrepancy Report

1. Contract/Order Number: ________
2. Report Number

3. To: (Contractor and Manager’s Name)

4. From: (Name of Client Representative)

5. Dates

Prepared:
Returned by Contractor
Action Completed

6. Discrepancy or Problem: (Describe in detail; include reference to PWS; attach continuation sheet if necessary.)

Contractor Response

7. To: (Contracting Officer)

8. From: (Contractor)

9. Contractor Response as to Cause, Corrective Action and Actions to Prevent Recurrence; Attach continuation sheet if necessary. (Cite applicable Q.C. program procedures or new Q.C. procedures)

10. Government Evaluations (Acceptance, partial acceptance, rejection: attach continuation sheet if necessary)

11. Government Actions (Reduced payment, cure notice, show cause, other)

Closeout

Name-Title
Signature
Date

Contractor Notified

Client Rep

CO/PM