This document contains the Scope of Work for furnishing and installing two new high efficiency heat pumps at the Aberdeen Plant Materials Center office space and conference room in Aberdeen, Idaho.
The Scope of Work requires the removal and disposal of two existing HVAC units, followed by the furnishing and installation of two new high efficiency heat pump units with a minimum 17 SEER2 rating, using environmentally friendly refrigerants. The new units must be connected to the existing ductwork, with any necessary rework and insulation repair. The work also includes providing and installing new programmable thermostats with battery backup. The anticipated period of performance is 15 calendar days from the Notice to Proceed.
The related federal contract opportunity is a Request for Quotes (RFQ) under Solicitation Number 12FPC324Q0016, issued by the USDA Farm Production and Conservation - Acquisition and Procurement Division on behalf of the USDA Natural Resources Conservation Service. This is a 100% Small Business set-aside contract, with a NAICS code of 238220 (Plumbing, Heating, and Air-conditioning Contractors) and a Small Business Size Standard of $19M. The estimated magnitude of the project is between $25,000 and $100,000.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Furnish and Installation of two New High Efficiency Heat Pumps
Aberdeen Plant Materials Center Office Space and Conference Room 1691A South 2700 West Aberdeen, Bingham County, Idaho, 83210.
Background:
The United States Department of Agriculture Natural Resources Conservation Service Aberdeen Plant Materials Center requires disposal and replacement of its office space, and conference room HVAC units.
Scope of Work:
Removing two existing HVAC units from site; cleaning area in preparation for new equipment;
furnishing and installing two complete heat pump replacement units; connecting new units to existing ductwork, reworking ductwork as needed and repairing duct wrap insulation as necessary;
provide and install all new control wiring and two new programmable thermostats with battery backup of settings; charge and start system, test for proper operation.
System Specifications:
New heat pumps should have a minimum 17 SEER2 rating, use environmentally friendly A2L refrigerants (such as R-32 and R- 454B refrigerant), and have programmable thermostats with battery backup.
** Quotes must include the make, model, and specifications of the new unit to address requirements in the Scope of Work.
Performance:
Fifteen days after the notice to proceed (NTP) is issued.