S01_12FPC324Q0016.pdf
PDF 332 KB Posted
- Solicitation number
- 12FPC324Q0016
About this file
This document is a Solicitation for a firm-fixed-price construction contract to furnish and install two new high efficiency heat pumps for the office space and conference room at the Aberdeen Plant Materials Center in Idaho. The work includes removing and disposing of two existing HVAC units, and providing all labor and materials for the new heat pump installation.
The solicitation is a 100% Small Business set-aside under NAICS code 238220 with a size standard of $19M. The estimated contract value is between $25,000 and $100,000. Quotes are due by 5:00 pm EST on April 30, 2024. The performance period is 15 calendar days from the Notice to Proceed. Interested contractors must be registered in SAM and complete the annual representations and certifications. Contractors are encouraged to arrange a site visit. The solicitation was issued by the USDA Farm Production and Conservation - Acquisition and Procurement Division on behalf of the NRCS.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1121704
USDA FPAC Business Center
Western Section
FPAC-HQ-12FPC3@usda.gov
FPAC-HQ-12FPC3
stephen.case@usda.gov
STEPHEN CASE 919-873-2121
103/29/2024
12FPC324Q0016
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Two New High Efficiency Heat Pumps Aberdeen Plant Materials Center West Aberdeen, Bingham County, Idaho.
The contractor shall furnish all labor, materials, equipment, and supervision required for the construction described in the attached statement of work. Work will consist of removing two existing HVAC units from site; cleaning area in preparation for new equipment; furnishing and installing two complete heat pump replacement units; connecting new units to existing ductwork, reworking ductwork as needed and repairing duct wrap insulation as necessary; provide and install all new control wiring and two new programmable thermostats with battery backup of settings; charge and start system, test for proper operation.
** Quotes must include the make, model, and specifications of the new unit to address requirements in the Scope of Work.
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
5 15 calendar days and complete it within ________________ ________________ calendar days after receiving
04/30/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 8/2014)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA FPAC Business Center Western Section
FPAC-HQ-12FPC3@usda.gov
FPAC-HQ-12FPC3
LAUREEN M. EIPP
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 8/2014) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 37
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12FPC324Q0016
Delivery: 15 Days After Notice to Proceed
Delivery Location Code: NRCS-ID-120211
USDA-NRCS-IDAHO STATE OFFICE
9173 W. BARNES DR.
SUITE C
BOISE ID 83709-1574 US
0001 High Efficiency Heat Pumps Aberdeen Plant
Materials Center West Aberdeen, Bingham County, Idaho.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Solicitation Number: 12FPC324Q0016
Updated thru FAC 2024-03 dated February 23, 2024. Page 4 of 37
PART I – THE SCHEDULE
B - SUPPLIES OR SERVICES AND PRICES/COSTS
Furnish and Install Two New High Efficiency Heat Pumps Aberdeen Plant Materials Center Office Space and Conference Room 1691A South 2700 West Aberdeen, Bingham County, Idaho, 83210.
This solicitation requires a price be submitted for all line items, failure to do so will disqualify the quote.
Line Item
Description Qty Unit Unit Price Extended Amount
001 Mobilization & Demobilization 1 LS $ $
002 Removal & Disposal of Old Units 1 LS $ $
003 Furnish & Installation New Units 1 LS $ $
SUBMITTED BY: _________________________________ EUI#______________________________
COMPANY: _________________________________________
** Quotes must include the make, model, and specifications of the new unit to address requirements in the Scope of Work.
ONE AWARD FOR THE AGGREGATE OF ALL ITEMS WILL BE MADE AS A RESULT OF THIS
SOLICITATION
Updated thru FAC 2024-03 dated February 23, 2024. Page 5 of 37
C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
1. Removing 2 existing HVAC units from site
2. Cleaning area in preparation for new equipment
3. Furnishing and installing two complete heat pump replacement units, minimum 5-ton capacity each with accessory electric backup heat. Systems must be sufficient to condition a space of 1,200 square feet with 12 ft ceiling (conference room) and 2,070 square feet with 9 ft ceiling (office space) to temperatures of 75F heating and 70F cooling.
4. Heat pump must be EnergyStar certified. Connect new unit to existing ductwork, reworking ductwork as needed and repairing duct wrap insulation as necessary.
5. New heat pump should have a minimum 17 SEER2 rating.
6. New heat pump system to use environmentally friendly A2L refrigerants, such as R-32 and R- 454B refrigerant.
7. Provide and install all new control wiring and 2 new programmable thermostats with battery backup of the settings.
8. Charge and start system, test for proper operation.
9. Quotes must include the make, model, and specifications of the new unit to address the above requirements.
AGAR 452.211-72 Statement of Work/Specifications. (Feb 1998) The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
(End of clause)
AGAR 452.211-73 Attachments to Statement of Work/Specifications. (Feb 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
(End of clause)
Updated thru FAC 2024-03 dated February 23, 2024. Page 6 of 37
D - PACKAGING AND MARKING
No clauses included in this section.
Updated thru FAC 2024-03 dated February 23, 2024. Page 7 of 37
E - INSPECTION AND ACCEPTANCE
52.246-12 Inspection of Construction. (Aug 1996)
(a) Definition."Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not-
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this- section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may-
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and
Updated thru FAC 2024-03 dated February 23, 2024. Page 8 of 37 material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
Updated thru FAC 2024-03 dated February 23, 2024. Page 9 of 37
F - DELIVERIES OR PERFORMANCE
52.242-14 Suspension of Work. (Apr 1984)
52.211-10 Commencement, Prosecution, and Completion of Work. (Apr 1984) The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than fifteen (15) days. The time stated for completion shall include final cleanup of the premises.
(End of clause)
Work Performance on Holidays The Contractor shall not perform work on the following holidays except in the case of emergency as permitted elsewhere in this contract:
New Year's Day Independence Day Labor Day Thanksgiving Day Christmas Day
The contract performance time has been established to allow for the non-working holidays stated above.
The Contractor may be permitted to work the following remaining designated Federal holidays provided that he/she submits a letter of request to the Contracting Officer at least five (5) days in advance of the holiday.
Birthday of Martin Luther King, Jr.'s Washington's Birthday Memorial Day Juneteenth Independence Day Columbus Day Veterans Day
Updated thru FAC 2024-03 dated February 23, 2024. Page 10 of 37
G - CONTRACT ADMINISTRATION DATA
Contracting Officer’s Authority The Contracting Officer (CO) is the only person authorized to approve changes in any of the requirements of this contract. This authority remains solely with the CO. In the event that the Contractor effects any change at the direction of any person other than the CO, the change will be considered to have been made without authority and NO adjustment will be made in the contract price to cover any INCREASE in costs incurred as a result thereof.
Contracting Officer’s Representative The Contracting Officer’s Representative (COR) is an individual designated in writing by the Contracting Officer (CO) to act as an authorized representative of the CO to perform specific contract administrative functions within the scope and limitations as defined by the CO in the COR’s appointment letter. This letter specifies the extent of the COR’s authority to act on behalf of the CO. The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery or any other term or condition of the contract. Any subsequent change to the COR or COR responsibilities will be confirmed, in writing, by the CO. A COR does not have the authority to and may never –
1. award, agree to, or execute any contract, contract modification, or notice of intent;
2. obligate, in any way, the payment of money by the Government;
3. make a final decision on any contract matter which is subject to the clause at FAR 52.233-1, Disputes; or
4. terminate, for any cause, the contractor’s right to proceed.
If the contractor does not receive a copy of the COR appointment letter, the contractor is required to request a copy of it from the CO prior to commencing work. Individuals not designated in writing as a COR by the CO are not considered a COR and do not have the authority delegated to the COR. If the contractor considers any action or inaction by a COR, any other government employee (such as an inspector), or representative or agent of the government as a change to the contract terms and conditions they must notify the contracting officer immediately and not proceed with any such change until approved by the contracting officer
Designated Payment Office Contact Point The contact point described below coordinates the issuance of payments under this contract. If payment is not received within 5 days after the due date specified in the contract, contact the payment office designated below for information on when payment will be made.
USDA, National Finance Center Administrative Payments Branch (APB) Telephone: (800) 421-0323 or (504) 426-6510
If questions arise on the amount paid, contact the contracting officer at the number or address shown in the contract.
Electronic Invoicing and Payment Requirements – Invoice Payment Platform (IPP) Invoices must be submitted electronically through the U.S. Department of the Treasury’s Invoice Payment Platform System (IPP) or the Contractor must be willing to accept payment by Government purchase card.
The Contractor must use the IPP website (https://www.ipp.gov) to register, access, and use IPP for submitting invoices. Contractor assistance with enrollment can be obtained by calling (866) 973-3131.
Invoices submitted by means other than IPP will not be accepted unless the Contracting Officer authorizes alternate procedures in writing.
https://www.ipp.gov/
Updated thru FAC 2024-03 dated February 23, 2024. Page 11 of 37
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
- Itemization of the amounts requested;
- Subcontractor listing showing 1) each subcontractor and the total value of the subcontract, 2) the portion of the instant progress payment that will be made to each subcontractor, and 3) the total amount previously paid to each subcontractor;
- Payment request certification from the clause; and
- Release of claims (final payment only). “I, (Name of Contractor), do hereby release the United
States of America from any and all claims and liabilities of any character whatsoever arising under and by virtue of contract number (Identify Contract) dated (Date) as amended, except as stated.
(Date of Release) (Signature of Contractor)”]
Updated thru FAC 2024-03 dated February 23, 2024. Page 12 of 37
H - SPECIAL CONTRACT REQUIREMENTS
52.236-13 Accident Prevention. (Nov 1991)
(a) The Contractor shall provide and maintain work environments and procedures which will-
(1) Safeguard the public and Government personnel, property, materials, supplies, and equipment exposed to Contractor operations and activities;
(2) Avoid interruptions of Government operations and delays in project completion dates; and
(3) Control costs in the performance of this contract.
(b) For these purposes on contracts for construction or dismantling, demolition, or removal of improvements, the Contractor shall-
(1) Provide appropriate safety barricades, signs, and signal lights;
(2) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910; and
(3) Ensure that any additional measures the Contracting Officer determines to be reasonably necessary for the purposes are taken.
(c) If this contract is for construction or dismantling, demolition or removal of improvements with any Department of Defense agency or component, the Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1, in effect on the date of the solicitation.
(d) Whenever the Contracting Officer becomes aware of any noncompliance with these requirements or any condition which poses a serious or imminent danger to the health or safety of the public or Government personnel, the Contracting Officer shall notify the Contractor orally, with written confirmation, and request immediate initiation of corrective action. This notice, when delivered to the Contractor or the Contractor’s representative at the work site, shall be deemed sufficient notice of the noncompliance and that corrective action is required. After receiving the notice, the Contractor shall immediately take corrective action. If the Contractor fails or refuses to promptly take corrective action, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. The Contractor shall not be entitled to any equitable adjustment of the contract price or extension of the performance schedule on any stop work order issued under this clause.
(e) The Contractor shall insert this clause, including this paragraph (e), with appropriate changes in the designation of the parties, in subcontracts.
(End of clause)
AGAR 436.211 Distribution of Advance Notices and Solicitations (Oct 2023) Solicitation notices posted for construction contracts anticipated to be awarded to a small business must include a statement that, “Pursuant to FAR 36.211(b), information regarding USDA’s definitization of equitable adjustments for change orders under construction contracts may be found at Contracting with USDA | USDA. USDA’s procedures that apply to the definitization of equitable adjustments for change orders under construction contracts may be found in the USDA Contracting Desk Book, located at Policies & Regulations | USDA, under Parts 436 and 443.”
AGAR 452.228-71 Insurance Coverage. (Nov 1996)
Updated thru FAC 2024-03 dated February 23, 2024. Page 13 of 37
Pursuant to FAR clause 52.228-5, Insurance-Work on a Government Installation, the Contractor will be required to present evidence to show, as a minimum, the amounts of insurance coverage indicated below:
(a) Workers Compensation and Employer's Liability. The Contractor is required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 shall be required, except in States with exclusive or monopolistic funds that do not permit worker's compensation to be written by private carriers.
(b) General Liability. The Contractor shall have bodily injury liability insurance coverage written on a comprehensive form of policy of at least $500,000 per occurrence.
(c) Automobile Liability. The Contractor shall have automobile liability insurance written on a comprehensive form of policy. The policy shall provide for bodily injury and property damage liability covering the operation of all automobiles used in connection with performing the contract. Policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage or loss.
(d) Aircraft Public and Passenger Liability. When aircraft are used in connection with performing the contract, the Contractor shall have aircraft public and passenger liability insurance. Coverage shall be at least $200,000 per person and $500,000 per occurrence for bodily injury, other than passenger injury. Coverage for passenger injury shall be at least $200,000 multiplied by the number of seats or passengers, whichever is greater.
(End of Clause)
AGAR 452.236-73 Archaeological or Historic Sites. (Feb 1988) If a previously unidentified archaeological or historic site(s) is encountered, the Contractor shall discontinue work in the general area of the site(s) and notify the Contracting Officer immediately.
(End of clause)
AGAR 452.236-74 Control of Erosion, Sedimentation, and Pollution. (Nov 1996)
(a) Operations shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).
(b) Pollutants such as fuels, lubricants, bitumens, raw sewage, and other harmful materials shall not be discharged on the ground; into or nearby rivers, streams, or impoundments; or into natural or man-made channels. Wash water or waste from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.
(c) Mechanized equipment shall not be operated in flowing streams without written approval by the Contracting Officer.
Updated thru FAC 2024-03 dated February 23, 2024. Page 14 of 37
PART II—CONTRACT CLAUSES
I - CONTRACT CLAUSES
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (Jun 2020) 52.204-13 System for Award Management Maintenance. (Oct 2018) 52.204-18 Commercial and Government Entity Code Maintenance. (Jul 2016) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition of Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023)
52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. Nov 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. (Nov 2015)
52.219-6 Notice of Total Small Business Set-Aside. (Nov 2020) 52.219-28 Post-Award Small Business Program Rerepresentation. (Feb 2024)
52.222-3 Convict Labor. (Jun 2003) 52.222-6 Construction Wage Rate Requirements. (August 2018) 52.222-7 Withholding of Funds. (May 2014) 52.222-8 Payrolls and Basic Records. (July 2021) 52.222-9 Apprentices and Trainees. (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements. (Feb 1988) 52.222-11 Subcontracts (Labor Standards). (May 2014) 52.222-12 Contract Termination—Debarment. (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (May 2014) 52.222-14 Disputes Concerning Labor Standards. (Feb 1988) 52.222-15 Certification of Eligibility. (May 2014) 52.222-19 Child Labor-Cooperation with Authorities and Remedies (Nov 2023) 52.222-21 Prohibition of Segregated Facilities. (Apr 2015) 52.222-26 Equal Opportunity. (Sept 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction. (Apr 2015) 52.222-50 Combating Trafficking in Persons. (Nov 2021) 52.222-55 Minimum Wages Under Executive Order 14026 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 14026 (Jan 2022)
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts.
(Sep 2013) 52.223-6 Drug-Free Workplace. (May 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Jun 2020)
52.225-13 Restrictions on Certain Foreign Purchases. (Feb 2021)
52.228-2 Additional Bond Security. (Oct 1997) 52.228-11 Pledges of Assets. (Feb 2021)
Updated thru FAC 2024-03 dated February 23, 2024. Page 15 of 37
52.228-12 Prospective Subcontractor Requests for Bonds. (Dec 2022) 52.228-14 Irrevocable Letter of Credit. (Nov 2014)
52.232-5 Payments under Fixed-Price Construction Contracts. (May 2014) 52.232-23 Assignment of Claims. (May 2014) 52.232-27 Prompt Payment for Construction Contracts. (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer—System for Award Management. (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations. (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (Mar 2023)
52.233-1 Disputes. (May 2014) 52.233-3 Protest after Award. (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim. (Oct 2004)
52.236-2 Differing Site Conditions. (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work. (Apr 1984) 52.236-5 Material and Workmanship. (Apr 1984) 52.236-6 Superintendence by the Contractor. (Apr 1984) 52.236-7 Permits and Responsibilities. (Nov 1991) 52.236-8 Other Contracts. (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
(Apr 1984) 52.236-10 Operations and Storage Areas. (Apr 1984) 52.236-11 Use and Possession Prior to Completion. (Apr 1984) 52.236-12 Cleaning Up. (Apr 1984) 52.236-16 Quantity Surveys. (Apr 1984) 52.236-17 Layout of Work. (Apr 1984) 52.236-21 Specifications and Drawings for Construction. (Feb 1997)
52.243-5 Changes and Changed Conditions. (Apr 1984)
52.244-6 Subcontracts for Commercial Products and Commercial Services (Feb 2024)
52.246-21 Warranty of Construction (Mar 1994)
52.249-2 Termination for Convenience of the Government (Fixed-Price). Alternate I (Apr 2012) 52.249-10 Default (Fixed-Price Construction). (Apr 1984)
52.253-1 Computer Generated Forms. (Jan 1991)
52.204-21 – Basic Safeguarding of Covered Contractor Information Systems (Nov 2021)
(a) Definitions. As used in this clause—
Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Updated thru FAC 2024-03 dated February 23, 2024. Page 16 of 37
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
Updated thru FAC 2024-03 dated February 23, 2024. Page 17 of 37
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
(End of clause)
52.222-36 Equal Opportunity for Workers with Disabilities. (Jun 2020)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause)
52.225-9 Buy American—Construction Materials. (Oct 2022)
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is– https://www.acquisition.gov/far/part-22#FAR_22_1408
Updated thru FAC 2024-03 dated February 23, 2024. Page 18 of 37
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.
supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if– https://www.acquisition.gov/far/subpart-2.1#FAR_2_101 https://www.acquisition.gov/far/subpart-25.1#FAR_25_105
Updated thru FAC 2024-03 dated February 23, 2024. Page 19 of 37
(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together.
Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/subpart-12.5#FAR_12_505
Updated thru FAC 2024-03 dated February 23, 2024. Page 20 of 37
Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
“None”
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-
(i) The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at
FAR 25.105.
(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
Updated thru FAC 2024-03 dated February 23, 2024. Page 21 of 37
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
Updated thru FAC 2024-03 dated February 23, 2024. Page 22 of 37
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction Material Description Unit of Measure Quantity Price (dollars)*
Item1:
Foreign construction material _______ _______ _______
Domestic construction material _______ _______ _______
Item2: _______ _______ _______
Foreign construction material _______ _______ _______
Domestic construction material
[* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.]
Updated thru FAC 2024-03 dated February 23, 2024. Page 23 of 37
52.228-5 Insurance-Work on a Government Installation (Jan 1997)
(a) The Contractor shall, at its own expense, provide and maintain during the entire performance of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.
(b) Before commencing work under this contract, the Contractor shall notify the Contracting Officer in writing that the required insurance has been obtained. The policies evidencing required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective-
(1) For such period as the laws of the State in which this contract is to be performed prescribe; or
(2) Until 30 days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in subcontracts under this contract that require work on a Government installation and shall require subcontractors to provide and maintain the insurance required in the Schedule or elsewhere in the contract. The Contractor shall maintain a copy of all subcontractors' proofs of required insurance and shall make copies available to the Contracting Officer upon request.
52.228-13 Alternative Payment Protections. (Jul 2000)
(a) The Contractor shall submit one of the following payment protections:
Payment Bond, SF25A Irrevocable letter of credit (ILC) Tripartite Escrow Agreement
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within five (5) days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds, which…