This document appears to be the Pre-Bid Conference Minutes for a federal contract opportunity. The key details are:
The contract opportunity is for the Prince's Point Wetland Restoration and Enhancement (WRE) project located in Jefferson County, Wisconsin. The wetland restoration will cover approximately 1,750 acres and include constructing dikes, shallow scrapes/islands, water control structures, and access road/bridge improvements.
The solicitation is being issued by the USDA Farm Production and Conservation (FPAC) Operations Branch, Acquisition Division on behalf of the USDA Natural Resources Conservation Service (NRCS). The Pre-Bid Conference Minutes outline several changes to the construction specifications, including requirements for clearing/grubbing, structure removal, earthfill, and pipe installation. The minutes also address questions from prospective bidders regarding material sources, settlement plate monitoring, field office location, pump salvage, and other contract requirements. No extension to the bid closing date was granted.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Other attendees not shown on the sign-in sheet
Rachel Barker – WDNR (Landowner)
Mark Steinfest – Ducks Unlimited
Brittany Ehlen – Ducks Unlimited
Steve Becker – NRCS
Dave Gundlach – NRCS
Construction and Material Specifications Changes
Construction Specification 2 – Clearing and Grubbing
7. Items of Work and Construction Detail
Bid Item 3, Clearing and Grubbing
(3) Add – Burned trees and brush shall be buried with a minimum of 18 inches of soil cover.
Burial can be partially above and below ground.
(4) Change – Payment will be to the nearest 0.1 acre.
Construction Specification 3 – Structure Removal
7. Items of Work and Construction Detail
Bid Item 2, Structure Removal and Bid Item 17, Well Decommissioning
(1) c) Add – Contractor shall provide the WDNR (Rachel Barker) with 30 days advance notice to disconnect power at pump and pivot stations and remove transformers prior to structural removal operations.
Construction Specification 8 – Mobilization and Demobilization
4. Items of Work and Construction Detail
Bid Item 1, Mobilization and Demobilization Add
(10) Gates will combination locks shall be provided at both entrances to the site (Kincaid Lane and Hwy 106). Gate locations shall be specified by the Engineer. Gates shall be wide enough to pass all construction and agricultural equipment; minimum width of 16 feet.
(11) Measurement and payment shall be made at the lump sum contract price.
Add Subsidiary Item, Parking Area Gravel
(1) Contractor may provide parking area gravel at their discretion to maintain a clean work surface for equipment and pump storage, and keep loose mud and/or debris off roads. Gravel can be salvaged from roads within the work limits or imported.
Gravel can remain in the parking area after completion of the work.
(2) No separate payment will be made for parking area gravel. Compensation therefore will be considered as incidental in the payment for Bid Item 1.
Construction Specification 11 – Removal of Water
8. Items of Work and Construction Detail
Subsidiary Item, Removal of Water
(2) Delete – WDNR is responsible to maintain the tile/ditch drainage system…
(2) Add - The contractor is responsible for repairing, re-routing, or restoring subsurface drainage tile that is damaged or obstructed by construction activities, so that drainage water conveyance is sustained to the pump system for dewatering.
Construction Specification 23 – Earthfill Delete Section 8. Testing. Quality control tests are not required beyond that described under Section 10.
10. Items of Work and Construction Detail
Add - Contractor is responsible for verifying earthfill quantities determined by GPS survey and CAD surface models developed by NRCS. If the contractor calculates more or less quantity, compensation shall be incorporated into the unit bid price for Bid Items 7 and 8.
Contractor shall accept the quantity and location of settlement plates as representative of the foundation consolidation under new dike construction. Final locations for settlement plates shall be determined by the Engineer prior to new dike construction.
Bid Item 7, Earthfill – Dike Construction and Ditch Filling
(5) Add – Earthfill shall be installed in loose “horizontal” lift thickness not to exceed 9 inches. Earthfill shall not be installed and compacted on sloped fills, i.e., bathtub method.
Bid Item 8, Earthfill – Island Construction
(4) Add – Earthfill shall be installed in loose “horizontal” lift thickness not to exceed 9 inches. Earthfill shall not be installed and compacted on sloped fills, i.e., bathtub method.
Material Specification 521 – Aggregates for Drainfill and Filters
C. Add – Submit crushed gravel gradation to the Engineer for approval at least 7 days prior to installation. Gravel shall meet the following gradation.
Sieve Percent Passing ¾ inch 100% No. 4 50 - 80% No. 40 15 - 35% No. 200 5 – 15%
Construction Specification 42 – Concrete Pipe Conduits and Drains
11. Items of Work and Construction Detail
Bid Item 22, 24” Reinforced Concrete Pipe & Bid Item 23, 30” Reinforced Concrete Pipe
(3) Add - Excavate pipe trench down to firm clay material. Backfill to the pipe flowline with clay material compacted in 4 inch loose lifts with a manually directed power tamper.
Engineer shall approve the foundation prior to pipe installation.
Add (4) Excavation and earthfill is subsidiary to pipe installation and compensation therefore will be considered incidental to and included in the payment for Bid Items 22 and 23.
Construction Specification 51 – Corrugated Metal Pipe
11. Items of Work and Construction Detail
Bid Item 9, Water Control Structure
(2) Add - Excavate down to firm clay material. Backfill to the base of the structure with clay material compacted in 4 inch lifts with a manually directed power tamper. Engineer shall approve the foundation prior to installation of the water control structure.
(3) Add - Excavation and earthfill is subsidiary to pipe installation and compensation therefore will be considered incidental to and included in the payment for Bid Item 9.
Construction Specification 61 – Rock Riprap
8. Items of Work and Construction Detail
Bid Item 10, Rock Riprap
Add (4) Excavate down to firm clay material. Backfill to the bottom elevation of rock with clay material compacted in accordance with CS 23 Earthfill. Engineer shall approve the foundation prior to geotextile and rock riprap placement.
Add (5) Excavation and earthfill is subsidiary to rock riprap installation and compensation therefore will be considered incidental to and included in the payment for Bid Item 10.
Material Specification 523 – Rock for Riprap Add E. Items of Work and Construction Detail
Bid Item 10, Rock Riprap
Add (1) Rock shall be inspected and approved by the engineer at the quarry source at least 14 days prior to delivery. The contractor shall provide rock soundness tests to the Engineer for approval at least 14 days prior to delivery.
Add (2) Gradation for D50 = 6” rock riprap shall be as follows:
D100 9” - 12” D85 8” – 11” D50 6” – 9” D15 2” – 3”
Questions and Answers
Question: Is all borrow material (including clay fill material) intended to come from on-site locations?
Response: Yes
Question: Are excavation numbers based on compacted in place? Any adjustments, or how will additional excavated material be accounted for?
Response: Excavation for earthfill borrow is subsidiary to the payment for earthfill.
Measurement and payment for additional excavation under Bid Items 5 and 6 is specified in CS 21, Section 10.
All earthfill quantities are based on compacted, in-place volume to design elevation with no adjustment factors. See amended language under CS 23, Section 10 for measurement and payment of additional earthfill for foundation consolidation and variations in CAD surfaces.
If the contractor feels that 24 settlement plates are not adequate to quantify foundation consolidation, a modification request for additional plates can be submitted to the Contracting Officer prior to the commencement of earthfill operations.
Question: Is the contractor required to warranty the height of the dikes after completion?
Answer: After dike construction is completed to design elevations, approved by the Engineer, and seeded and mulched, the contractor does not have to warranty height.
Question: Could you please elaborate on moisture content?
Answer: Moisture content is an empirical field test. It is required to readily make a ball without release of free water.
Question: Please clarify the discrepancy between quality control tests mentioned in the CS 23 base spec and the Class C compaction requirements in Section 10: Items of Work and Construction Detail?
Response: An amendment will remove Section 7 Testing in CS 23.
Question: Is there a specific size requirement for the field office? Can it be located on Kincaid property, outside the work limits?
Response: There is no minimum size. It must be large enough to contain the provisions specified CS 96.
Field office can be located on Kincaid Lane and on Kincaid property as an alternative to the staging area. Power can be obtained from Kincaid’s existing buildings/infrastructure.
Contractor would be responsible for a private agreement with Cody Kincaid (estimated utility rent $250/month), and all costs associated with power routing and hookup.
Question: Will the bid closing date or deadline for questions be extended?
Response: No
Question: Please elaborate on pump removal and salvaging?
Response: Pumps will be salvaged and placed in staging area. The contractor will dispose of all other associated piping and appurtenances off-site as specified in the plan drawings and specs.
Question: On the artesian well what has to be removed/disposed?
Response: WE Energies will disconnect power and remove the transformers. Contractor shall notify WDNR (Rachel Barker) 30 days prior to well decommissioning and well works removal. WDNR will contact WE Energies. Contractor shall excavate, remove, and dispose off-site, all piping and appurtenances associated with the artesian well as specified in CS 3.
Question: What gate requirements will there be and who is responsible for those?
Response: Contractor shall furnish and install gates and combination locks at both entrances (Kincaid Lane and Hwy106) under an amendment to CS 1. Gates shall be wide enough for all construction and agricultural equipment access.
Question: Is the contractor required to use the entire staging area?
Response: No. Contractor only needs to use staging space required for their mobilization and demobilization of construction equipment and pump storage.
Question: Will cover crops be taken care of prior to construction?
Response: Yes, cover crops will be mowed down by DNR or operator prior and close to construction. A map of cover crop vs. soybean areas will be provided in amendment.
Question: Who is responsible for permits?
Response: Contractor responsible for utility locates. All other permits will be made available to the awarded contractor. The contractor is responsible for understanding and following those the permit general provisions and conditions.