Attachment 7 Geotechnical Drilling Report Map Lab Tests.pdf
PDF 26 MB Posted
- Attached to
- Prince's Point WRE, Jefferson County, WI Federal contract opportunity
- Solicitation number
- 12FPC324B0006
About this file
This document appears to be Attachment 7 Geotechnical Drilling Report Map Lab Tests related to the federal contract opportunity for the Prince's Point WRE project in Jefferson County, Wisconsin.
The Prince's Point WRE project is being solicited by the USDA Farm Production and Conservation (FPAC) Operations Branch, Acquisition Division on behalf of the USDA Natural Resources Conservation Service (NRCS). The project involves the 1,750-acre wetland restoration of Prince's Point, which will include the construction of four wetland management basins, shallow scrapes and islands for habitat and wave protection, water control structures, and access road and bridge improvements. This attachment appears to provide geotechnical data and testing results relevant to the construction activities required under this contract.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DB-4: ((3) 3”x 36” Shelby tubes to Intertek PSI)
Embankment Height: ~8.1 ft, Ground Elev. 786.0
Soil Texture: 4 ft: CL w/ organics, dry, low plasticity, brown
8 ft: CL, slightly moist, low plasticity, tan
12 ft: Peat w/ some clay, moist, black
_________________________________________________ Sat. 7/9/22 9:10 am Dan & Alex
DB-5: ((3) 3”x 36” Shelby tubes to Intertek PSI), Ground Elev. 786.5
DB-5A: ((3) 3” x 36” Shelby tubes and small bag sample 8-10’ cutting blend to Lincoln SML)
Soil Texture: 1-4 ft OL, moist, black, very soft
5-8 ft OL, saturated, black, very soft
9-12 ft OL, saturated, black
DB-6: ((3) 3” x 36” Shelby tubes to Intertek PSI, small bag 1-12’ cutting blend to Lincoln SML)
Ground Elev. 786.0
Soil Texture: 1-4 ft OL, moist, black, very soft, 12.5” recovery
5-8 ft OL, saturated, black, very soft, 19.5” recovery
9-12 ft OL, saturated, black, very soft, 14.5” recovery
DB-7: ((3) 3” x 36” Shelby tubes to Intertek PSI), Ground Elev. 785.6
DB-7A: ((3) 3” x 36” Shelby tubes to Lincoln, small bag 1-12’ cutting blend to Lincoln SML)
Soil Texture: 1-4 ft ML and OL blend, light brown, very soft, 12” recovery
5-8 ft OL, saturated, black, very soft, 12” recovery
9-12 ft OL, saturated, black, very soft, 9.5” recovery
River Elev. 780.0 Inside Ditch Bank Elev. 778.0 (water level 777.0)
_____________________________________________________7/12/2022 Driller Tim & Ali
DB-8: ((3) 3” x 36” Shelby tubes to Intertek PSI, small bag 4-9’ cutting blend to Lincoln SML)
Ground Elev. 787.4
Soil Texture: 1-4 ft OL, moist, black, very soft, 10” recovery
5-8 ft OL, saturated at 7’, black, very soft, 14” recovery
9-12 ft OL, saturated, black, very soft, 6” recovery
DB-9: ((3) 3” x 36” Shelby tubes to Intertek PSI, small bag 4-9’ cutting blend to Lincoln SML)
Ground Elev. 787.5
Soil Texture: 1-4 ft OL, moist, black, very soft, 12” recovery
5-8 ft OL, saturated, black, very soft, 6” recovery
9-12 ft OL, saturated, black, very soft, 9” recovery
DB-10: ((3) 3” x 36” Shelby tubes to Intertek PSI), Ground Elev. 786.7
Soil Texture: 1-4 ft OL, moist, black, very soft, 21.5” recovery
5-8 ft OL, saturated, black, very soft, unknown” recovery
9-12 ft OL, saturated, black, very soft, 8.5” recovery
DB-7B: (small bag 16-26’ cutting blend and small bag 26.5-28’ cutting blend to Lincoln SML)
Ground Elev. 785.6
Soil Texture: 0 -13.5’ Blind drill through peat (no sample)
16-26’ ML, saturated, very soft, weight of hammer
26.5-28’ CL, saturated, firm, SPT 4, 4, 5
___________________________7/14/2022 Drillers Tim & Ali
P-2: ((1) 3” x 36” Shelby tube to Intertek PSI), Ground Elev. 784.4
Soil Texture: 1-3 ft CL, moist, light brown, SPT 6,6,7,6
5-7 ft CL, moist, light brown, (6.5-7’ ML Marl), SPT 5,3,5,5
9-11ft CL, saturated, light brown, stiff, SPT 5,5,9,10, pp 3.5-4.0 t/sf
13-15 ft CL, saturated, light brown, stiff, SPT 6,7,9,12
15-18 ft Shelby tube, CL stiff, grey, 30” recovery
Ditch Water Elev = 776.5 Ditch Bottom Elev = 771.9
P-1: ((1) 3” x 36” Shelby tube to Intertek PSI), Ground Elev. 782.5
Soil Texture: 1-3 ft CL, slightly moist, light brown, stiff, SPT 7,4,5,6
5-7 ft OL, moist, light brown, SPT weight of hammer, 6” recovery in split spoon
9-11 ft CL, saturated, grey, very stiff, SPT 5,7,8,13 pp 3.75 t/sf, full recovery
11-14 ft Shelby tube broke off
New hole:
0-15 ft blind drill
15-18 ft Shelby tube
18-20 ft CL, dark brown, saturated, firm, SPT 6,6,7,8 pp 2.0 t/sf
Ditch Water Elev = 776.6
Ditch Bottom Elev = 772.6
SP 2.3: ((2) 3”x36” Shelby tubes to Intertek PSI)
East Sheet Pile Site, Elev 779.2
Soil Texture: 1-3 ft OL, no recovery in split spoon, weight of hammer
5-7 ft OL, no recovery in split spoon, weight of hammer
9-11 ft ML, Marl, grey, 6” recovery in spoon, very soft, weight of hammer
13-15 ft ML, Marl, grey, sat, 12” recover, very soft, weight of hammer
17-19 ft CL, grey, saturated, 18” recover, very soft, weight of hammer
21-23 ft CL, grey, saturated, 24” recover, very soft, weight of hammer
25-27 ft CL, grey, saturated, soft, 18” recovery, SPT 3,3,5,4 pp 1.75-2.25 t/sf
27-29 ft CL, light grey, saturated, firm, 24” recovery, SPT 4,4,6,9 pp 2.75 t/sf
29-32 ft Shelby Tube
32-34 ft CL, light grey, sat, firm, 24” recover, 2.5” ribbon, SPT 5,6,10,12 pp 3.5-4.25 t/sf
34-36 ft CL, light grey, sat, firm, 24” recovery, 2.5” ribbon, SPT 5,6,7,9 pp 2.25-2.5 t/sf
36-38 ft CL, light brown, sat, firm, 24” recovery, 2.5” ribbon, SPT 3,3,5,7 pp 1.25 t/sf
38-41 ft Shelby Tube pp 2.75 t/sf
_________________________________________________7/19/2022 Drillers Tim and Alex
SP 2.2: ((2) 3”x36” Shelby tubes to Intertek PSI)
East Sheet Pile Site, Elev 778.5
Soil Texture: 1-3 ft OL, no recovery in split spoon, weight of hammer
5-7 ft ML, Marl, grey, very soft, weight of hammer
9-11 ft ML, Marl, grey, very soft, weight of hammer
13-15 ft ML, Marl, grey, very soft, weight of hammer
17-19 ft ML, Marl, grey, sat, 6” recover, very soft, weight of hammer
CL, grey, sat, 18” recover, soft
21-23 ft CL, grey, sat, 24” recover, soft, weight of hammer
25-27 ft CL, grey, sat, 24” recover, soft, weight of hammer
29-31 ft CL, grey, saturated, firm, 18” recovery, SPT 3,3,5,6 pp 1.75 t/sf
31-34 ft Shelby Tube, grey, firm CL at bottom
34-36 ft CL, grey, saturated, firm, 24” recovery, 2.5” ribbon, SPT 3,4,4,6 pp 2.0 t/sf
36-38 ft CL, grey, saturated, firm, 24” recovery, 2.5” ribbon, SPT 4,3,4,4 pp 1.5-2.0 t/sf, torvane 0.6 x 2 = 1.2 t/sf
38-41 ft Shelby Tube, pp 2.25 t/sf at bottom
_________________________________________________7/21/2022 Drillers Tim and Alex
SP 2.1: ((2) 3”x36” Shelby tubes to Intertek PSI)
East Sheet Pile Site, Elev: 778.7, The actual drill hole location was ~16 ft N of staked location due to small trees/brush causing a potential safety hazard. (Nick from United took a picture of the location)
Soil Texture: 1-3 ft OL, no recovery in split spoon, weight of hammer
5-7 ft OL, Peat, black, 2” recovery, weight of hammer
ML, Marl, grey, 6” recovery, very soft
9-11 ft ML, Marl, grey, 12” recovery, very soft, weight of hammer
13-15 ft ML, Marl, grey, sat, 12” recovery, very soft, weight of hammer
17-19 ft ML, Marl, grey, sat, 6” recovery, very soft, weight of hammer
CL, grey, sat, 8” recovery, soft
21-23 ft CL, grey, sat, 24” recovery, soft, weight of hammer
25-17 ft CL, grey, sat, 24” recovery, soft, weight of hammer
29-31 ft CL, grey, sat, 24” recovery, firm, 2” ribbon, SPT 2,4,5,6 pp 2.0 t/sf, tv 0.6 x 2 = 1.2 t/sf
31-34 ft Shelby Tube, CL, grey, firm at bottom, pp 2.0 t/sf
34-36 ft CL, grey, sat, 24” recovery, firm, 2” ribbon, SPT 3,4,5,5 pp 1.5-1.75 t/sf, tv 0.5 x 2 = 1 t/sf
36-38 ft CL, grey, sat, 24” recovery, firm, 2” ribbon, SPT 4,5,5,7 pp 2.0 t/sf, tv 0.6 x 2 = 1.2 t/sf
38-41 ft Shelby Tube, CL, grey, firm at bottom, pp 2.0 t/sf
_________________________________________________7/22/2022 Drillers Dan and Alex
SP 1.1: ((2) 3”x36” Shelby tubes to Intertek PSI)
West Sheet Pile, Elev: 780.6
Soil Texture: 1-3 ft OL, Topsoil, black, 8” recovery, SPT 1,1,1,1
5-7 ft OL, Topsoil, black, 3” recovery
CL, grey, 18” recovery, firm, SPT 2,3,4,6, pp 2.25
9-11 ft CL, grey, moist, firm, ~2 in ribbon, SPT 4,4,4,6, pp 2.0-2.5
13-16 ft Shelby Tube Sample, CL, grey at bottom
16-18 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,3,5, pp 1.5
18-20 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,4,5,6, pp 2.0
20-22 ft CL, grey, sat, firm, ~3.0 in ribbon, SPT 4,4,5,7, pp 2.0
22-24 ft CL, grey, sat, firm, ~3.0 in ribbon, SPT 3,4,4,7, pp 1.5-1.75
24-26 ft CL, grey, sat, firm, ~3.0 in ribbon, SPT 3,4,6,6, pp 1.5
26-28 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,3,4,7, pp 1.25-1.5
28-30 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,4,3,6, pp 1.25
30-32 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,5,5,6, pp 1.25
32-34 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,4,5,6, pp 1.5
34-36 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,5,5, pp 1.25
36-39 ft Shelby Tube Sample, CL, grey at bottom
SP 1.3: ((2) 3”x36” Shelby tubes to Intertek PSI)
West Sheet Pile, Elev: 780.5
Soil Texture: 1-3 ft OL, Topsoil, black, no recovery, SPT 2,1,2,2
5-7 ft OL, Topsoil, black, very soft 6” recovery
ML, Marl, grey, 6” recovery, moist, soft
CL, grey, 6” recovery, moist, soft, SPT 2,1,2,3, pp 1.0
7-9 ft ML, Marl, grey, sat, very soft, 18” recovery
CL, grey, firm, sat, 6” recovery, SPT 0,0,1,2, pp 1.75
9-11 ft CL, grey, sat, firm, ~2 in ribbon, SPT 2,2,2,4, pp 2.0
11-13 ft CL, grey, sat, very firm, ~2.0 in ribbon, SPT 3,4,5,5, pp 3.0-3.5
13-16 ft Shelby Tube Sample, CL, grey at bottom
16-18 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,5,6,7, pp 2.0-2.25
18-20 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,4,6, pp 2.0
20-22 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,3,4,6, pp 2.0-2.5
24-26 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,4,5,7, pp 1.5-2.0
28-30 ft CL, grey, sat, soft to firm, ~2.0 in ribbon, SPT 2,3,3,5, pp 1.0
32-34 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,3,5,7, pp 1.75
35-37 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,3,4,5, pp 1.5
37-40 ft Shelby Tube Sample, CL, grey at bottom
_________________________________________________7/25/2022 Drillers Dan and Ali
SP 2.4: ((2) 3”x36” Shelby tubes to Intertek PSI)
New East Sheet Pile, Elev: 780.31 ft
Soil Texture: 1-3 ft OL, Topsoil, black, 6” recovery
ML, Marl, grey, sat, soft, 6” recovery, SPT 0,1,1,1
5-7 ft CL, grey sat, firm, SPT 3,5,6,9, pp 4.25
9-11 ft CL, grey, sat, firm, ~2 in ribbon, SPT 4,5,6,9, pp 3.25
13-16 ft Shelby Tube Sample, CL, grey at bottom
16-18 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,3,4,5, pp 1.5
18-20 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,3,4,6, pp 1.25
20-22 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,4,5,7, pp 1.5
24-26 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,4,5,7, pp 1.75
28-30 ft CL, grey, sat, firm, ~2.0 in ribbon, SPT 8,9,7,7, pp 1.0
32-34 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,4.5.7, pp 1.25-1.5
35-37 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,5,6, pp 1.25
SP 2.5: ((2) 3”x36” Shelby tubes to Intertek PSI)
New East Sheet Pile, ~100 ft north of SP 2.4, Elev: 780.43
Soil Texture: 1-3 ft OL, Topsoil, black, 6” recovery, SPT 1,3,4,5, 5-7 ft CL, grey sat, firm, SPT 1,3,4,5, pp 2.0-2.5
9-11 ft CL, grey, sat, firm, ~2 in ribbon, SPT 4,5,6,7, pp 2.25-2.5
13-15 ft CL, grey sat, firm, ~2.5 in ribbon, SPT 4,4,5,5, pp 1.5
15-18 ft Shelby Tube Sample, CL, grey at bottom
18-20 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,4,7, pp 1.5
20-22 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,2,4,6, pp 1.5-2.0
24-26 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,3,4,6, pp 1.5-2.0
28-30 ft CL, grey, sat, firm, ~2.0 in ribbon, SPT 3,2,4,5, pp 1.25
32-34 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,3,4,5, pp 1.5-1.75
35-37 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,3,5,6, pp 1.5-1.75
_________________________________________________7/27/2022 Drillers Tim and Alex
B.1: ((2) 3”x36” Shelby tubes to Intertek PSI)
East side of bridge, Elev: 787.7
Soil Texture: 1-3 ft GW, sand and gravel, brown, 6” recovery, SPT 2,5,4,8
5-7 ft OL, Peat, black, soft, 6” recovery, SPT 9,4,3,4
9-11 ft OL, Peat, brown, soft, SPT 2,1,1,1
13-15 ft CL, grey, sat, firm, ~2.0 in ribbon, SPT 5,6,8,10, pp 3.0
17-19 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,4,5, pp 1.5
19-22 ft Shelby Tube Sample, CL, grey at bottom
22-24 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,4,4,6, pp 1.5
26-28 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,4,5,6, pp 1.75
30-32 ft CL, grey, sat, firm, ~2.0 in ribbon, SPT 3,3,4,5, pp 2.25
32-34 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,3,5,6, pp 2.0
35-37 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,4,5, pp 1.0
B.2: ((2) 3”x36” Shelby tubes to Intertek PSI)
West side of bridge, Elev: 787.6
Soil Texture: 1-3 ft GW, sand and gravel, brown, 6” recovery, SPT 10,9,12,9
5-7 ft OL, Peat, black, soft, 8” recovery, SPT 5,3,4,4
9-11 ft OL, Peat, brown, soft, 3” recovery
ML, Marl, grey, sat, soft, 3” recovery, SPT 1,2,2,1
13-15 ft ML, Marl, grey, sat, soft, 4” recovery
CL, grey, sat, firm, ~20” recovery, ~2.0 in ribbon, SPT 3,3,6,5, pp 2.5
17-19 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,2,3,4, pp 1.5
21-23 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 2,3,2,4, pp 1.0
23-26 ft Shelby Tube Sample, CL, grey at bottom
26-28 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 3,3,4,4, pp 2.0
30-32 ft CL, grey, sat, firm, ~2.0 in ribbon, SPT 3,4,5,7, pp 2.25
32-34 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 4,5,6,7, pp 2.25
35-37 ft CL, grey, sat, firm, ~2.5 in ribbon, SPT 5,4,6,7, pp 1.75
22040
SHELBY TUBE PHOTO LOG
United Engineering Consultants, Inc.
DB-1
DB-2
DB-3
DB-4
DB-5
DB-6
DB-7
DB-8
DB-9
DB-10
SP-1.1 / SP-1.3
SP-2.1
P-2 (TOP TUBE) / SP-2.2
SP-2.3
SP-2.4
SP-2.5
B-1
B-2