15N01_Pavement_Repair_Questions_and_Answers_1-30-19.pdf PDF
Amendment_002_129AC719R0001.pdf PDF
A1_129AC719R0001_final.pdf PDF
4. PAL Fire Plan.pdf PDF
15N01_Solcitation_129AC719R0001.pdf PDF
5. CA4, mod 15, 11022018.pdf PDF
2. Road Log 2.pdf PDF
3. Drawings 2.pdf PDF
6.SF24 Bid Bond.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

15N01 ROAD REPAIR

SPECIAL CONTRACT REQUIRMENTS

The following Special Contract Requirements amend and supplement the Standard Specifications for Construction of Roads and Bridges, on Federal Highway Projects (FP03) US Customary Version, US Department of Transportation, and Federal Highway Administration.

Preface

101 - Terms, Format, and Definitions

102 - Bid, Award, and Execution of Contract

103 - Scope of Work

104 - Control of Work

105 - Control of Material

106 - Acceptance of Work

107 - Legal Relations and Responsibility to the Public

108 - Prosecution and Progress

109 - Measurement and Payment

153 – Contractor Quality Control

155 - Schedules for Construction Contracts

201 - Clearing and Grubbing

204 - Excavation and Embankment

207 – Earthwork Geotextiles

301 – Untreated Aggregates

404 – Hot Asphalt Concrete

625 - Turf Establishment

703 - Aggregate

714 – Geotextile and Geocomposite Drain Material

718 - Traffic Signing and Marking Material

2 | P a g e

Preface Preface_wo_03_15_2004_m

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

3 | P a g e

101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005

101.01_nat_us_01_22_2009

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp Milepost ppm Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

http://www.nist.gov/

4 | P a g e

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

5 | P a g e

Figure 101-1—Illustration of road structure terms.

6 | P a g e

102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

7 | P a g e

103 - Scope of Work 103.00_nat_us_02_16_2005

Deletions

Delete all but subsection 103.01 Intent of Contract.

8 | P a g e

104 - Control of Work 104.00_nat_us_06_16_2006

Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

9 | P a g e

105 - Control of Material 105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02(a) Government-provided sources.

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

10 | P a g e

106 - Acceptance of Work 106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

11 | P a g e

107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

• Exact time and location of spill including a description of the area involved.

• Containment procedures.

• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

12 | P a g e

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

107.10_05_us_05_04_2007

107.02 Protection and Restoration of Property and Landscape

Meet the requirements chapters 10, 11, and 12.2 in their entirety of “Water Quality Management for National Forest System Lands in California Best Management Practices” dated September

13 | P a g e

108 - Prosecution and Progress 108.00_nat_us_02_16_2005

108 Delete.

Delete Section 108 in its entirety.

14 | P a g e

109 - Measurement and Payment 109.00_nat_us_02_17_2005

109 Deletions

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

15 | P a g e

Section 153. - CONTRACTOR QUALITY CONTROL

Construction Requirements

153.02 Contractor Quality Control Plan.

(a) Process control testing. Add the following:

See Table 153-1 for schedule of minimum sampling and testing for process control. Where no minimums are specified, submit proposed tests to be performed and the proposed sampling and testing frequencies.

For aggregates and/or aggregate/asphalt mixtures accepted under Subsection 106.03, sample and test for conformity with the Certification a minimum of one time per pay item.

(b) Inspection/control procedures.

(3) Production phase. Add the following:

(d) Inspect the work, materials or assemblies accepted under Subsection 106.03 to ensure that all the work and materials comply with contract requirements. Furnish the results of the work inspection, along with the product certification or commercial certification as applicable, to the CO prior to incorporating the materials into the work.

(c) Description of records. Add the following:

Identify the format for reporting test results, materials certifications and the procedures to be used to maintain inspection records.

(d) Personnel qualifications.

(1) Add the following:

Designate a Quality Control Supervisor (QCS) whose primary responsibility is managing the inspection system. The QCS may be the Contractor's Superintendent. Designate a QCS who is experienced to perform and supervise all work inspection, sampling and testing. The QCS will monitor all phases of the work and identify deficiencies and take appropriate corrective action.

Add the following:

(3) Personnel assigned to sampling or testing will have 1 year or more of recent job experience in the type of sampling and testing required by the contract, and the following:

(a) NICET Level II certification in highway materials, or State (SHA) or industry certification-related sampling and testing equivalent to their intended responsibilities.

(b) WAQTC or other nationally accepted certification program for intended sampling and testing responsibilities.

16 | P a g e or

(c) Current or previous employment by an AASHTO accredited laboratory performing sampling and testing equivalent to their intended responsibilities.

(d) Demonstrated proficiency or successful testing of one or more proficiency samples may be substituted for basic qualifications pending verification of test results.

153.03 Testing. Delete the title and text of this Subsection and substitute the following:

153.03 Sampling and Testing. Perform the work required by Table 153-1 and by the accepted Quality Control Plan.

(a) Acceptance sampling. Acceptance sampling schedules and times or locations will be provided by the CO. Use a procedure for random sampling. In addition, sample any material that appears defective or inconsistent with similar material being produced, unless such material is voluntarily removed and replaced or otherwise corrected.

(b) Testing. Furnish a laboratory equipped with all test equipment necessary to satisfy the requirements of the contract. Ensure test equipment has been checked, calibrated, standardized and/or otherwise verified in accordance with AASHTO and ASTM standards by an individual qualified to do this work. Ensure mobile laboratories receive an equipment inspection after the laboratory has been moved to its permanent location on the project site and anytime it is moved thereafter. Inspect equipment within 45 days of actual use in project testing and at least once a year thereafter. Do not use equipment that has not been inspected or is found to be deficient.

Mark deficient equipment and take it out-of-service until it is repaired or replaced and shown by subsequent inspection to perform as required. Maintain records documenting these inspections in the laboratory. Provide certification(s) stating the equipment conforms to testing requirements and provide evidence of current inspection.

The CO may require the Contractor to perform testing to demonstrate acceptable equipment and an acceptable level of technician competence. The CO may also check equipment and inspection records to verify condition. Repair or replace equipment not meeting applicable requirements.

Keep laboratory facilities clean and maintain equipment in proper working condition. Provide the CO unrestricted access to the laboratory for inspection and review.

Keep laboratory facilities clean and maintain equipment in proper working condition. Provide the CO unrestricted access to the laboratory for inspection and review.

(c) Certifications. For materials accepted by certification in accordance with 106.03, review all certifications to insure compliance with the requirements of the contract prior to incorporating materials into the work and provide a signed copy of the reviewed certification(s) to the CO.

153.04 Records. Add the following to the fIrst paragraph:

17 | P a g e

When tests are on material being incorporated into the work, report test results within the reporting times indicated in the sampling and testing requirements at the end of each section or as specified in the contract.

Add the following to the second paragraph:

Detailed inspection results including deficiencies observed and corrective actions taken.

153.05 Acceptance. Add the following:

If chronic deficiencies are noted in the Contractor's inspection or testing systems, the CO may order supplemental inspection and/or testing to be performed. The Government will charge to the Contractor all costs associated with such supplemental inspection or testing.

Delete the text for Measurement and Payment and substitute the following:

Measurement

153.06 Contractor quality control will be measured by the lump sum.

Payment

153.07 The accepted quantity, measured as provided above, will be paid at the contract price per unit of measurement for the pay item listed below that is shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

The Contractor quality control lump sum will be paid as follows:

(1) 25 percent of the lump sum, not to exceed 0.5 percent of the original contract amount, will be paid after all testing facilities are in place, qualified sampling and testing personnel have been identified, and the work being tested has started.

(2) Payment for the remaining portion of the lump sum will be prorated based on the total work completed.

18 | P a g e

Table 153-1 Schedule of Minimum Sampling and Testing For

Process Control (to be performed by the Contractor)

Material Property or

Test Method or Specification Frequency Sampling Point Characteristic

Embankment Classification and AASTHO M 145 1 per material/type. Source of material.

Construction Moisture Density AASHTO T 99 or

AASTHOT 180

Composition of (minimum of 5 proctor points).

Roadbed in Cuts In-place density and AASHTO T 310 2 per lift, but not less Compacted embankment, moisture content than 2 every 1000 cubic subgrade as applicable.

yards.

R-value AASHTOT 190 1 per 2500 feet, or Sample depth:

(Tested by FHWA Central Lab). change in material type. 0-12 inches.

Bedding/Backfill Classification and AASTHOM 145 1 per material/type. Source of material.

for Structures and Moisture Density AASHTO T 99 or

Culvert Pipe

AASTHO T 180

(minimum of 5 proctor points).

In-place density and AASHTO T 310 1 per 50 feet/lnft. Compacted bedding or moisture content Minimum 2 per lift. backfill as applicable.

19 | P a g e

155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004

155 Delete.

Delete Section 155 in its entirety.

20 | P a g e

201 - Clearing and Grubbing 201.00_nat_us_08_05_2009

201.01 Description

Replace with the following

This work consists of clearing and grubbing within clearing limits and other designated areas.

201.02 Material:

Delete Tree wound dressing material reference.

201.03 General.

Delete the last sentence.

201.04 Clearing.

Delete the last sentence of (d).

21 | P a g e

204 - Excavation and Embankment 204.14_nat_us_03_02_2005

204.14 Disposal of Unsuitable or Excess Material.

Delete the text of the first paragraph and substitute the following:

Dispose of unsuitable or excess material at designated sites or legally off of the project.

22 | P a g e

Section 207 – EARTHWORK GEOTEXTILES

Delete the text of this Section and substitute the following:

Description

207.01 This work consists of furnishing and placing geotextile as a permeable separator, stabilizer, or permanent erosion control measure.

This work also consists of furnishing and placing geogrid as a soil reinforcement element.

Geotextile types are designated as shown in Subsection 714.01.

Material

207.02 Conform to the following Subsection:

Geotextile 714.01

Geogrid 714.01

Construction Requirements

207.03 General. Submit test results to the CO verifying the proposed products meet the criteria as outlined in Section 714.

Where placing a geotextile on native ground, cut the trees and shrubs flush with the ground surface. Do not remove the topsoil and vegetation mat. Remove all sharp objects and large rocks. Fill depressions or holes with suitable material to provide a firm foundation.

Replace or repair all geotextile or geogrid that is torn, punctured, or muddy. Remove damaged area and place a patch of the same type of material by overlapping 3 feet beyond the damaged area.

Furnish geogrid packaged in a sheathing or container suitable to protect the geogrid from damage due to ultraviolet light during storage and handling. Store, handle, and haul all the materials in accordance with the manufacturer’s specifications and as directed by the CO. Furnish geogrid that is visibly labeled with the name of the manufacturer, identification of the geogrid product, date of manufacture, lot number, length, width, and quantity.

207.04 Separation and Stabilization Applications. Where placing a geotextile on a subgrade, prepare the subgrade according to Subsection 204.13(c) and (d).

Place the geotextile smooth and free of tension, stress, or wrinkles. Fold or cut the geotextile to conform to curves. Overlap in the direction of construction. Overlap the geotextile a minimum of 2 feet at the ends and sides of adjoining sheets, or sew the geotextile joints according to the manufacturer’s recommendations. Do not place longitudinal overlaps below anticipated wheel loads. Hold the geotextile in place with pins, staples, or piles of cover material.

23 | P a g e

End dump the cover material onto the geotextile from the edge of the geotextile or from previously placed cover material. Do not operate equipment directly on the geotextile. Spread the end-dumped pile of cover material maintaining a minimum lift thickness of 12 inches.

Compact the cover material with rubber tired or non-vibratory smooth drum rollers. Avoid sudden stops, starts, or turns of the construction equipment. Fill all ruts from the construction equipment with additional cover material. Do not regrade ruts with placement equipment.

Place subsequent lifts of cover material in the same manner. Vibratory compactors may be used for compacting subsequent lifts. If foundation failures occur, repair the damaged areas and revert to the use of non-vibratory compaction equipment.

207.05 Permanent Erosion Control Applications. Place and anchor the geotextile on an approved smooth-graded surface. For slope or wave protection, place the long dimension of the geotextile down the slope. For stream bank protection, place the long dimension of the geotextile parallel to the centerline of the channel.

Overlap the geotextile a minimum of 12 inches at the ends and sides of adjoining sheets or sew the material according to manufacturer’s recommendations. Overlap the uphill or upstream sheet over the downhill or downstream sheet. Offset end joints of adjacent sheets a minimum of 5 feet. Pins may be used to hold geotextile sheets in place. Space pins along the overlaps at approximately 3-foot centers.

Place aggregate, slope protection, or riprap on the geotextile starting at the toe of the slope and proceed upward. Place riprap onto the geotextile from a height of less than 12 inches. Place slope protection rock or aggregate backfill onto the geotextile and cover material in the same day.

207.06 Soil Reinforcement Applications. Install the geogrid reinforcement according to the manufacturer’s recommendations. Place the geogrid reinforcement at the elevations and to the extent shown on the plans. Place the geogrid reinforcement in continuous longitudinal strips such that the principle strength (highest strength) axis is perpendicular to the slope or wall face.

If unable to complete the required length with a single continuous length of geogrid, a joint may be made with the approval of the CO. Only one joint per length of geogrid will be allowed.

Construct this joint for the full width of the strip using a similar material, conforming to the requirements of Subsection 714.03(a), and follow the manufacturer’s recommendations. Pull and hold taut joints in geogrid reinforcement prior to backfilling. After a layer of geogrid reinforcement has been placed, use suitable means, such as pins or small piles of soil, to hold the geogrid reinforcement in position until the subsequent layer of backfill can be placed. Do not operate track-mounted equipment on the geogrid reinforcement until at least 6 inches of soil has been placed over the geogrid. Keep equipment turning to a minimum to prevent displacement of embankment and damage to the geogrid material. If approved by the CO, rubber tired equipment may pass over the geogrid reinforcement at speeds less than 10 miles per hour. If during embankment placement waves, wrinkles, or slack develop in the geogrid, remove the embankment and pull the geogrid taut to remove slack.

Place only the amount of geogrid reinforcement required for immediately pending work to prevent undue damage. During construction, the surface of the fill should be kept approximately horizontal. Place geogrid reinforcements within 3 inches of the design elevations and extend to

24 | P a g e the length shown in the plans unless otherwise directed by the CO. Place uniaxle (primary) and biaxle (secondary) geogrid reinforcement as show on the plans or as directed by the CO. Place and compact embankment soils according to Subsections 204.10 and 204.11. Do not place sharp or angular rock and rock larger than 4 inches in diameter with 6 inches of the geogrid reinforcement. After the specified soil layer has been placed, install the next layer of geogrid reinforcement. Repeat the process for each subsequent layer until final grade is reached.

207.07 Acceptance. Material for earth work geotextile will be evaluated under Subsections 106.02, 106.03, and 714.01. Material for geogrid will be evaluated under Subsections 106.02, 106.03, and 724.03.

Earthwork geotextiles installation will be evaluated under Subsections 106.02 and 106.04.

Measurement

207.08 Measure the Section 207 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Payment

207.09 The accepted quantities will be paid at the contract price per unit of measurement for the Section 207 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

25 | P a g e

Section 301 – UNTREATED AGGREGATE

301.05 Compacting

Delete and replace with the following:

Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.

Compact the aggregate using the following method:

Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).

For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface.

26 | P a g e

404 - Minor Hot Asphalt Concrete 404.04_nat_us_03_02_2005

404.04 Weather Limitations.

Change 35o F to 45o F:

404.07_nat_us_03_02_2005

404.07 Compacting (a).

Delete and replace with the following:

(a) Roadway paving. Thoroughly and uniformly compact the surface a minimum of three passes with rollers that meet one of the following requirements:

(1) Steel-wheeled rollers, other than vibratory type, capable of exerting a force of not less than

1.5 ton/feet of width of the compression roll or rolls.

(2) Vibratory steel-wheel rollers with a minimum mass of 5 ton, equipped with amplitude and frequency controls, and designed to compact asphalt concrete.

(3) Pneumatic-tire rollers with smooth tread tires of equal size that provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 lbf/in2.

Perform initial compaction while the mixture is above 250 °F. Perform finish rolling with steel-wheel rollers and continue until no roller tracks remain.

27 | P a g e

625 - Turf Establishment 625.05_nat_us_03_30_2005

625.05 Watering.

Delete the entire subsection

625.07 Seeding.

Delete the first sentence and add:

“Apply “Regreen” sterile wheat (Triticum X Elymus) at a rate of 150 pounds per acre by the following methods:

Note: 1 acre = 4,840 square yards.

Seeding shall be placed on the prepared slope prior to any erosion control mat.

28 | P a g e

Section 703 – AGGREGATE

703.06 Crushed Aggregate

Add to the last sentence:

“and invasive weeds. Rock sources shall be inspected by personnel trained in invasive plant identification and approved by the Contracting Officer. The contractor shall provide documentation that the material is weed free by having the following form completed:

29 | P a g e

Invasive Plant-Free Aggregate Inspection Form

Site Name: ________________________________ Date: ________________

Inspector Name: ________________________________

Operator: ___________________ Designated Contact: _________________________

Street: __________________________________

City: __________________________

State: __________ County: _______________ Zip: ____________

Inspection Findings

Invasive Plant Species

Location on Site Approx. area Distance from material

Inspection Summary

Yes No Invasive Plants Observed/Comments Free of invasive plants:

Specific requirements for certification met:

Revision of plan required:

Mitigation required:

Resurvey required:

Final Supplier Rating (circle one)

Full compliance Conditional Unacceptable

30 | P a g e

Explanation for rating: ____________________________________________________

Mitigation Required:

31 | P a g e

Section 714. – GEOTEXTILE AND GEOCOMPOSITE DRAIN MATERIAL

714.01 Geotextile

(a) Physical Requirements. Add the following

(7) Uniaxial Geogrid Table 714-7

(8) Biaxle Geogrid Table 714-7

Add the following Subsection:

714.03 Geogrid. Furnish geogrid reinforcement with a regular network of integral connected polymer tensile elements having an aperture geometry and junction strength to sufficiently permit significant mechanical interlock with surrounding soil or rock. Provide geogrid with a structure dimensionally stable and able to retain its geometry under manufacture, transport, installation, ultraviolet degradation, and all forms of chemical and biological degradation encountered in the soil being reinforced.

(a) Physical requirements. Provide geogrids composed of fibers or ribs that are at least 85% by weight polyethylene, polypropylene or polyester. Form a network of fibers that will retain dimensional stability. Calculate the long-term tensile strength and pullout capacity of geogrids according to FHWA publication No. FHWA-NHI-00-043, entitled “Mechanically Stabilized Earth Walls and Reinforced Slopes Design and Construction Guidelines”. The Long-term tensile strength must take into account reduction factors for creep, durability, and installation damage as defined in FHWA -00-043. Conform to the physical requirements in table 714-7.

32 | P a g e

Table 714-7

Geogrid Physical Requirements

Property Test Method

Minimum Acceptable Values Uniaxle (Primary)

Geogrid Biaxle (Secondary)

Geogrid Wide width tensile strength (ultimate), lb/ft

ASTM D

4,800/1500 (1) 1,100/1,100 (1)

Wide width tensile strength (5% strain), lb/ft

ASTM D

1,500/500 (1) 300/300 (1)

Aperture size, inches ------------ 1.0/1.0 (1) 1.0/1.0 (1) Long Term

Design Strength, lb/ft

GRI:GG4 1,750 (2) 500 (2)

(1) Machine Direction/Cross Machine Direction

(2) Principle strength (highest strength) direction

Identify, store, and handle geogrid according to ASTM D 4873-88 and manufacturer’s recommendations. Limit geogrid exposure to ultraviolet radiation to less than 10 days.

(b) Evaluation Procedures. Geogrid will be evaluated under Subsection 106.03. Furnish to the CO three copies of the commercial certification that the geogrid supplied meets the respective index criteria, measured in full accordance with the test methods and standards set forth in these specifications. State on the commercial certification the name and manufacturer, product name, style number, chemical composition of the filaments, ribs, or yarns, and other pertinent information to fully describe the geogrid. Attest the certification by a person having legal authority to bond the contractor to supply test data from an agency approved laboratory to support the certified values submitted. Also, include the calculation of the long term design strength, with assumed reduction factors.

33 | P a g e

718 - Traffic Signing and Marking Material 718.05_nat_us_08_05_2009

718.05 Aluminum Panels

Delete the third paragraph and replace with the following:

Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.

Preface
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations.
101.04 Definitions.
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
107.06 Contractor’s Responsibility for Work.
107.09 Legal Relationship of the Parties.
107.10 Environmental Protection.
107.02 Protection and Restoration of Property and Landscape
108 - Prosecution and Progress
108 Delete.
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions.
155 - Schedules for Construction Contracts
155 Delete.
201 - Clearing and Grubbing
201.01 Description
201.02 Material:
204 - Excavation and Embankment
204.14 Disposal of Unsuitable or Excess Material.
301.05 Compacting
404 - Minor Hot Asphalt Concrete
404.04 Weather Limitations.
404.07 Compacting (a).
625 - Turf Establishment
625.05 Watering.
625.07 Seeding.
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels