A11_QA12970223R0014-26Jul2023.pdf
PDF 313 KB Posted
- Attached to
- Region 5 CERCLA Environmental Response IDIQ Federal contract opportunity
- Solicitation number
- 12970223R0014
- Issued by
- Department of Agriculture Forest Service
About this file
This memorandum provides answers to vendor questions regarding solicitation number 12970223R0014 for the Region 5 CERCLA Environmental Response IDIQ. The solicitation seeks proposals for environmental remediation and emergency response services for hazardous waste sites under the Comprehensive Environmental Response, Compensation, and Liability Act. Proposals are due by August 11, 2023. The Forest Service will not extend the due date in response to a question. Vendors may include cover pages, tables of contents, and lists of abbreviations in their submissions. A project manager may lead multiple activities if experienced in those areas. Example reports requested in the solicitation scenarios may be attached to proposals due to file size limitations. Sufficient detail must be included in the scenario responses to demonstrate an understanding of the anticipated task order types.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| A11_QA-Attachment1-WilliamsBrosPA2005.pdf | ||
| A11_0-RFP12970223R0014-0002-R5CERCLAIDIQ_8Aug2023.pdf | ||
| A11_QA12970223R0014-8Aug2023.pdf | ||
| A11_QA12970223R0014-31Jul2023.pdf | ||
| A11_0-RFP12970223R0014-0001-R5CERCLAIDIQ_31Jul2023.pdf | ||
| A11_QA12970223R0014-25Jul2023.pdf | ||
| A10_0-RFP12970223R0014-R5CERCLAIDIQv07132023.pdf | ||
| A10_AttachD.5_SOI-Fillable.xlsx | XLSX spreadsheet | |
| A10_AttachD.6_RepsCerts.docx | DOCX document | |
| A10_AttachD.2_ExampleScenario1.docx | DOCX document | |
| A10_AttachD.3_ExampleScenario2.docx | DOCX document | |
| A10_AttachD.4_ExampleScenario3.docx | DOCX document | |
| A10_AttachD.1_USDA-FS-Region-5-Map.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES FOREST SERVICE
PROCUREMENT & PROPERTY SERVICES
SPECIALIZED PROJECT OPERATIONS CENTER – SOUTHWEST REGION
26 July 2023
MEMORANDUM FOR RFP 12970223R0014 Vendors
FROM USFS PPS SPOC SW
SUBJECT: RFP 12970223R0014 Questions & Answers
1. Question: “Due to the unusual nature of the ‘Aircraft Public and Passenger Liability’ insurance requirement, can the contractor submit this expense as part of TO Cost/Price?”
Answer: “The intent is for the contractor to submit proof of ability to obtain Aircraft Public and Passenger Liability coverage at Task Order level. Anticipated cost may be provided in conjunction with Task Order costs. Solicitation Amendment forthcoming to reflect this.”
2. Question: “Are Cover Page, Table of Contents, and List of Abbreviations and Acronyms permitted as preface to each submission volume?”
Answer: “Yes, that is acceptable.”
3. Question: “The referenced section/language (E.1 Instruction to Offerors, E.1.2 Volume I – Technical
Proposal, b. Specialized Experience and Qualifications of Key Personnel) indicates that a project manager must be named for each activity offered. Please clarify whether it is acceptable for our project management personnel to lead multiple activities in which they are experienced.”
Answer: “Yes, that is acceptable.”
4. Question: “Will the Forest Service allow the example reports requested in each Example Scenario to be submitted as attachments to Volume I due to file size?”
Answer: “Yes, that is what was intended.”
5. Question: “Questions are due on August 9th with the proposal due August 11th. Can the due date be extended to allow for adequate time to review the answers to question and incorporate them into the proposal?”
Answer: “Answers to vendor questions will be promptly posted publicly on the SAM.gov solicitation on a rolling basis, as they are received. As of this response on 26 July 2023, the Government does not intend to extend the proposal due date.”
6. Question: “Attachment D.3 – Example Scenario 2 – Potentially Responsible Party Investigation requires the submittal of an ‘Example of a previous PRP Search Report that the firm has prepared (can be redacted as necessary).’ The PRP search reports that we have developed for our clients are highly confidential, and it would likely take more than 30 days to get approval from our client’s legal department to release even a redacted version of the report. Is a table of contents for the PRP investigation example report acceptable for the PRP Search Report?”
Answer: “Proposing vendors are encouraged to include sufficient detail in response to Example Scenario 2, such that the vendor’s understanding of and ability to respond to the types of Task Orders anticipated under the contemplated IDIQ is adequately demonstrated. Within the parameters of the Solicitation’s instructions, the content, including degree of detail, of a proposal’s response to Example Scenario 2 is largely the discretion of the proposing vendor – a response that fails to adequately demonstrate the vendor’s understanding of and ability to respond to the types of Task Orders anticipated under the contemplated IDIQ will be evaluated accordingly.”
7. Question: “Attachment D.4 – Example Scenario 3 – Phase I Environmental Site Assessment requires an ‘Example of previous ESA that the firm has prepared (can be redacted as necessary).’ It is challenging to redact all information that can be considered confidential. Would a cover page and/or table of contents be acceptable for the ESA report?”
Answer: “Proposing vendors are encouraged to include sufficient detail in response to Example Scenario 3, such that the vendor’s understanding of and ability to respond to the types of Task Orders anticipated under the contemplated IDIQ is adequately demonstrated. Within the parameters of the Solicitation’s instructions, the content, including degree of detail, of a proposal’s response to Example Scenario 3 is largely the discretion of the proposing vendor – a response that fails to adequately demonstrate the vendor’s understanding of and ability to respond to the types of Task Orders anticipated under the contemplated IDIQ will be evaluated accordingly.”