12905B24R0008.pdf
PDF 507 KB Posted
- Attached to
- Building 92 and 66 renovation in Dubois, ID
- Solicitation number
- 12905B24R0008
About this file
This document is a solicitation (RFP 12905B24R0008) for the remodeling and renovation of buildings 92 and 66 at the USDA ARS Range Sheep Production Efficiency Research Unit in Dubois, ID. The work includes complete demolition of existing interior functions, installation of new roofing, siding, HVAC, plumbing, electrical, and other building systems for the two buildings. The estimated contract value is between $1,000,000 and $5,000,000, and the contract will be set aside 100% for small businesses under NAICS code 236220 - Commercial and Institutional Building Construction. The period of performance is estimated to be 240 days after notice to proceed. Potential offerors are responsible for monitoring the solicitation site for amendments. A site visit is scheduled for April 17, 2024.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
1120783
USDA ARS PWA AAO ACQ/PER PROP
800 BUCHANAN STREET
ALBANY CA 94710
ARS-12905B
ROBERT SKIPPER
1x 04/12/2024
12905B24R0008
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Title: 12905B24R0008 - Remodel Building 92 and 66_Dubois, ID
The United States Department of Agriculture (USDA), Agricultural Research Service
(ARS), PWA RANGE SHEEP PRODUCTION EFFICIEN has a construction requirement to provide the remodeling and renovation of building(s) 92 and 66 at 19
Office Loop, Dubois, ID 83423.
The Contractor shall provide all labor, equipment, materials, supplies, transportation, and supervision performing all required work in accordance with the plans and specifications for this requirement. In accordance with Federal
Acquisition Regulation (FAR) 36.204 the magnitude of this construction project is between $1,000,000 and $5,000,000.
USDA will issue a Firm Fixed Price Construction Contract.
The requirement will be reserved 100% for small businesses under NAICS Code 236220 -
- Commercial and Institutional Building Construction with a size standard of $45M.
Completion timeframe for the resulting contract is estimated to be 240 days after notice to proceed.
Potential Offerors are responsible for monitoring this site for release of the RFP
Continued ...
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
14 240 calendar days and complete it within ________________ ________________ calendar days after receiving
05/13/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 8/2014)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
USDA ARS PWA AAO ACQ/PER PROP
800 BUCHANAN STREET
ALBANY CA 94710
ARS-12905B
MICHAEL T. HASSETT
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 8/2014) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 114
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12905B24R0008 package and any amendments. All offerors shall be registered with the System for Award Management Registration per
FAR Clause 52.204-7 and 52.204-8. No paper copies of the solicitation will be mailed and telephone requests will not be honored.
Delivery: 240 Days After Notice to Proceed
Delivery Location Code: ARS-120207
PWA RANGE SHEEP PRODUCTION EFFICIEN
19 OFFICE LOOP
DUBOIS ID 83423 US
Period of Performance: 05/21/2024 to 01/16/2025
0001 Remodel of Building 92 1 LS
Work will include complete demolition of all existing interior functions ie: all electrical, mechanical, plumbing, and animal pens. Work will also removal and installation of new metal roofing with insulation, the removal and installation exterior metal siding with new insulation. Reconfigured interior space will include 3 new workrooms, a chem lab, new electrical service and distribution, IT, Led lighting, access control, new HVAC, new plumbing, and new septic system.
Solicitation 12905B24R0008 and all amendments are incorporated into the contracts.
Product/Service Code: Z2JZ
Product/Service Description: REPAIR OR ALTERATION
OF MISCELLANEOUS BUILDINGS
0002 Option: Remodel of Building 66 1 LS
The project includes complete demolition of existing functions except for the restroom and have the building converted to cold storage. There will be new LED lighting and new overhead door.
Solicitation 12905B24R0008 and all amendments are incorporated into the contracts.
(Option Line Item)
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 114
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12905B24R0008
Product/Service Code: Z2JZ
Product/Service Description: REPAIR OR ALTERATION
OF MISCELLANEOUS BUILDINGS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
RFP 12905B24R0008
Remodel Building 92 and 66_Dubois, ID
CONTINUATION OF SF1442
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Definitions:
a. CLIN – Contract Line Item Number.
PRICE SCHEDULE
CLIN Supplies or Service Quantity and Unit Amount
0001 Remodel of Building 92
Work will include complete demolition of all existing interior functions ie: all electrical, mechanical, plumbing, and animal pens.
See attached "Project Manual and Drawings"
1 LS $
Optional
CLIN
Option: Remodel of Building 66
The project includes complete demolition of existing functions except for the restroom and have the building converted to cold storage. There will be new LED lighting and new overhead door.
See attached "Project Manual and Drawings"
1 LS $
TOTAL FOR PRICE SCHEDULE: $
End of Section B
SECTION C – DESCRIPTION/SPECIFICATIONS
C.1 STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-72) (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services, and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
C.2 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS (AGAR 452.211-
73) (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
C.3 BONDING
Bid Guarantee: A bid guarantee is not required for proposalss less than $150K.
If a proposal is above $150K, a bid guarantee is required in an amount not less than 20 percent of the proposed price but shall not exceed $3,000,000 (for proposals of $35,000 or more). Failure to furnish the required bid guarantee in the proper form and amount, by the time set for receipt of proposals, shall require rejection of the proposal in all cases except those listed in Federal Acquisition Regulation (FAR) 28.101-4. Bid Bonds must be provided using Standard Form 24 (see FAR 28.106-1) electronic versions of Bid Guarantee will be accepted. Individual sureties have to be acceptable to the Contracting Officer (see FAR 28.203) and be accompanied by Standard Form 28 Affidavit of Individual Surety. Other forms of offer security are acceptable as denoted in solicitation provision FAR Part 28.203-2. The cost of a Bid Guarantees will not be reimbursed.
After award, in accordance with Contract Clause 52.228-15, and FAR 28.102, Contractors are reminded that any amount awarded over $35,000.00 shall require a Payment Bond (SF 25A), and awards exceeding $150,000.00 shall require both Payment and Performance Bonds (SF 25).
Payment and Performance bonds are due no later than 10 days after notification of award.
C.4 BIOBASED PRODUCTS REQUIREMENTS
This procurement requires the use of biobased products to the extent that such products are reasonably available, meet agency or relevant industry performance standards, and are reasonably priced. Where available, these products should first be acquired from among qualified products that fall under the umbrella of items designated through the USDA BioPreferred SM Program.
The Contractor must comply with the Farm Security and Rural Investment Act of 2002 (FSRIA), 7 U.S.C. 8102; the Food, Conservation and Energy Act of 2008 (FCEA), 7 U.S.C. 8102; the Federal Acquisition Regulation; Executive Order (EO) 13514, “Federal Leadership in Environmental, Energy and Economic Performance,” dated October 5, 2009; EO 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” dated January 24, 2007; and Presidential Memorandum, “Driving Innovation and Creating Jobs in Rural America through Biobased and
Sustainable Product Procurement,” dated February, 2012 to provide biobased products.
The Contractor shall utilize products and material made from biobased materials (e.g. biobased greases; biobased hydraulic fluids, biobased absorbents) to the maximum extent possible without jeopardizing the intended end use or detracting from the overall quality delivered to the end user.
All supplies and materials shall be of a type and quality that conform to applicable Federal specifications and standards. All supplies and materials to be used in the performance of work described herein are subject to the approval of the Contracting Officer Representative (COR).
The following is an example list of products that may be used in this minor construction contract for which biobased products are available and the designated biobased content. The list is not all inclusive. It is desirable that vendors be able to supply the greatest number of biobased products listed meeting the health and environmental specifications.
• Adhesive and Mastic Removers – 58 percent
• Asphalt and Tar Removers - 80 percent
• Asphalt Restorers – 68 percent
• Carpet – 7 percent
• Carpet and Upholstery Cleaners – 54 percent and Spot Removers – 7 percent
• Composite Panels – Acoustical – 37 percent; Interior Panels – 55 percent; Plastic Lumber –
23 percent;
• Structural Interior Panels – 89 percent; Structural Wall Panels – 94 percent and Countertops and Solid
• Surface -_ 89 percent
• Concrete and Asphalt Cleaners – 70 percent
• Concrete and Asphalt Release Fluids – 87 percent
• Dust Suppressants – 85 percent
• Erosion Control Materials – 77 percent
• Floor Coverings (Non Carpet) – 91 percent
• General Purpose Cleaners - 54 percent
• Hand Soaps and Cleaners – 64 percent
• Industrial Cleaners – 41 percent
• Insulating Foam – 7 percent
• Leather, Vinyl, and Rubber Care Products – 55 percent
• Paint- Interior Paints and Coatings, Latex – 20 percent and Oil-based – 67 percent
• Paint Removers – 41 percent
• Roof Coatings – 20 percent
• Wastewater Systems Coatings – 47 percent
• Water Tank Coatings – 59 percent
• Wood and Concrete Sealers – Membrane Concrete Sealers- 11 percent and Penetrating
Liquids – 79
• percent
• Wood and Concrete Stains – 39 percent
Reporting is required by Sections 9002 of the Food Conservation and Energy Act of 2008 and the Agricultural Act of 2014. The Contractor shall provide quantities, product types and dollar value of any USDA-designated biobased product purchased by the Contractor. This important data shall be submitted to the COR for the current quarter and current contract year. A brief explanation shall include the methodology used to calculate the dollar value of USDA-designated products used or supplied.
The Contractor should also note that USDA-designated biobased products are available for purchase through the AbilityOne Program (formerly known as the Javits- Wagner-O’Day (JWOD) Program). Under this program, members of organizations including the National Industries for the Blind (NIB) and the National Institute for the Severely Disabled (SourceAmerica) offer products and services that are mandatory by Federal agencies. A search of the AbilityOne Program’s online catalog (www.ability.gov) indicated biobased products that include but are not limited to: cleaners (glass, hand, and multipurpose), graffiti removers, and sorbents.
For more information regarding the Department of Agriculture Biobased Program go to:
http://www.biopreferred.gov.
C.5 PERMITS AND LICENSES
Pursuant to FAR 52.236-7 Permits and Responsibilities, the Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state, and local laws and regulations.
C.6 DIRECTIVES, INSTRUCTIONS AND REFERENCES
Only the Contracting Officer shall issue directives/instructions defining the roles and responsibilities and appointment of a Contracting Officer Representative (COR); Location Monitor (LM); Project Manager (PM); Occupational Health & Safety Manager and/or any other functional appointment as deemed necessary for the scope of work.
C.7 WORK MANAGEMENT
The Contractor shall manage the total work effort associated with the services required in each task order to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality control. The Contractor shall provide a staff with the necessary management expertise to assure performance objectives and standards are met.
C.8 SERVICE INTERRUPTIONS/UTILITY OUTAGES
If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the Contracting Officer Representative ten calendar days in advance to allow notification of affected tenants and customers. If the discontinued service is due to an emergency breakdown the Contractor shall notify the Contracting Officer Representative as soon as practicable.
At a minimum, include the location of the outage, utilities being affected, duration of outage and any necessary sketches. Once approved, and prior to beginning work on the utility system requiring http://www.biopreferred.gov/ shut down, attend a pre-outage coordination meeting with the Contracting Officer to review the scope of work and the lock-out/tag-out procedures for worker protection. No work will be performed on energized electrical circuits unless proof is provided that no other means exist.
C.9 EMPLOYEE REQUIREMENTS
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety and environmental requirements associated with the work they perform. Competent personnel shall be provided as required by each contract.
C.10 OSHA COMPLIANCE
Contractor must maintain a workplace and ensure that workplace conditions conform to applicable OSHA standards.
C.11 EMPLOYEE CONDUCT/REMOVAL OF EMPLOYEES
Contractor employees and Subcontractor employees shall conduct themselves in a proper, efficient, courteous, and businesslike manner.
The Contractor shall remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of Agricultural Research Service.
End of Section C
SECTION D – PACKAGING AND MARKING
There are no clauses in this section.
End of Section D
SECTION E – INSPECTION AND ACCEPTANCE
E.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52-252-2)
FAR NUMBER TITLE DATE
52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
E.2 INSPECTION AND ACCEPTANCE (AGAR 452.246-70) (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at:
800 Buchanan Street Albany, CA 94710
E.3 FINAL INSPECTION
(a) A final inspection shall be made only when all the materials have been furnished, all the work has been performed, and all the construction provided for by the contract has been completed in accordance with the terms, conditions, specifications, and drawings set forth in this contract. If, upon examination by the Contracting Officer, his/her designated representative, and Government inspection personnel, the project is determined not sufficiently completed to have warranted a final inspection, the Contractor may be held financially liable for any additional cost of re-inspection when material and workmanship are not ready at the time specified by the Government for project inspection.
(b) Contractor shall give the Contracting Officer ten (10) calendar days advance notice, in writing, of the date the work will be fully completed and ready for final inspection.
(c) The Contracting Officer will notify the Contractor of any discrepancies and/or omissions noted at the final inspection by providing a "punchlist" as to the discrepancies/omissions, replacement of materials and performance or re-performance of any unsatisfactory work necessary for final acceptance. This notification shall not in any way be deemed an extension of the contract completion date. If all construction required by the contract is found completed and all contractual documents (i.e. payrolls, shop/as-builts/red-line drawings, release from claims, etc.) have been submitted, the Contracting Officer shall notify the Contractor of such in writing by processing the final payment for the project.
(d) Acceptance shall be final and conclusive, except for latent defects, fraud, or such gross mistakes as may amount to fraud, or regarding the Government’s right under any warranty or guarantee.
E.4 FINAL ACCEPTANCE
Upon written notification that all deficiencies identified during the final inspection have been corrected, the Contracting Officer will schedule a final acceptance inspection of the work. If all construction required by the contract is determined to be complete and all requisite contract deliverables (e.g., certified payroll records, as-built drawings, warranty documents, etc.) have been submitted and approved by the Government, the Contracting Officer shall notify the Contractor in writing of such acceptance. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
End of Section E
F.1 CLAUSES INCORPORATED BY REFERENCE (FAR 52.252-2) (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:
http://acquisition.gov
FAR CLAUSE TITLE DATE
52.242-14 SUSPENSION OF WORK APR 1984
F.2 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR
52.211-10), ALT I (APR 1984)
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by August 28, 2023. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
F.3 LIQUIDATED DAMAGES-CONSTRUCTION (52.211-12) SEPT 2000
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $424.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
End of Section F http://acquisition.gov/
SECTION G – CONTRACT ADMINISTRATION DATA
G.1 This contract shall be administered by the USDA/ARS/PWA, 800 Buchanan St, Albany, CA, 94710.
G.2 POST-AWARD CONFERENCE
(a) Prior to the Contractor starting work, a post-award conference (as described in FAR Subpart 42.5), will be convened by the contracting activity or contract administration office. The Contractor's Project Manager shall attend the conference. If the contract involves subcontractors, a representative of each major subcontractor is also required to attend.
(b) The conference will be held at a time/location to be determined.
(c) The Contracting Officer and the Contractor will agree to the date and time of the conference after award of the contract. In event of a conflict in schedules, the Contracting Officer shall establish the date for the conference.
(d) The Contractor shall include any associated costs for attendance at the conference, in its offer.
G.3 AUTHORITIES AND DELEGATIONS
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
The COR will be named at time of award.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
G.4 CONSTRUCTION PROGRESS AND PAYMENT SCHEDULE (a) Within 14 days after the date of receipt of award, the contractor shall prepare and submit to the Contracting Officer for approval, the original copy of ARS Form 371 (Attachment 3), Construction Progress and Payment Schedule. This form will serve as a Schedule of Estimates, Progress Schedule, and when used with ARS Form 372 (Attachment 2), it will be the basis for Requests for Partial Payment. The values employed in making the schedule will be used only for determining partial payments and will not be considered as establishing a basis for additions to or deductions from the contract. A copy of the approved schedule will be returned to the contractor. The need by an offeror for partial or progress payments, when authorized in the payment provisions of this request for proposals, will not be treated as a handicap in making the award.
G.5 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS - INVOICE
PROCESSING PLATFORM (IPP)
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform System (IPP). The IPP website address is:
https://www.ipp.gov.
Include an ARS Form 372, signed by the ARS program manager or COR in the ‘Recommended for Payment’ block.
https://www.ipp.gov/
“Payment requests” means any request for contract financing payment or invoicing payment by the Contractor. To constitute a proper invoice, the payment request shall comply with the applicable Prompt Payment clause included in the contract, the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts, or the requirements identified in FAR 52.232-27, Prompt Payment for Construction Contracts, and include the items listed in paragraphs (a)(2)(i) through (a)(2)(xi) of the this clause.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3-5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone
(866) 973-3131.
Invoices shall not include information that would compromise Personally Identifiable Information, such as full social security numbers, dates of birth, etc.
The final invoice shall be submitted and will be approved in accordance with the payment terms and conditions contained in the contract, after all, if any, settlement actions are complete. The contractor must clearly identify the last payment as the “Final Invoice”.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
Both ARS-371 and 372 forms need to be signed by Govt before they can upload into IPP for payment.
End of Section G mailto:ippgroup@bos.frb.org
SECTION H – SPECIAL CONTRACT REQUIREMENTS
Clause Title Date
AGAR 452.236-72 Use of Premises NOV 1996
Before any camp, quarry, borrow pit, storage, detour, or bypass site, other than shown on the drawings, is opened or operated on USDA land or lands administered by the USDA, the Contractor shall obtain written permission from the Contracting Officer. A camp is interpreted to include the campsite or trailer parking area of any employee working on the project for the Contractor.
Unless accepted elsewhere in the contract, the Contractor shall (i) provide and maintain sanitation facilities for the workforce at the site and (ii) dispose of solid waste in accordance with applicable Federal, State and local regulations.
AGAR 452.236-75 Maximum Workweek – Construction Schedule NOV 1996
Within 10 (ten) calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:
A schedule as required by FAR clause 52.236-15 Schedules for Construction Contracts – APR 1984 and The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work. The maximum work week that will be approved is 7:00 a.m. to 5:00 p.m., Mon. thru Fri., excluding Federal holidays and weekends.
End of Section H
SECTION I – CONTRACT CLAUSES
52.252-2 Clauses Incorporated by Reference FEB 1998 This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address:
http://acquisition.gov
52.202-1 Definitions JUN 2020 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions on Subcontractor Sales to the Government
Alternate I – JUN 2020
JUN 2020
52.203-7 Anti-Kickback Procedures JUN 2020 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity MAY 2014 52.203-12 Limitation on Payment to Influence Certain Federal Transaction JUN 2020 52.203-17 Contractor Employee Whistleblower Rights and Requirement to
Inform Employees of Whistleblower Rights
JUN 2020
52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements
JAN 2017
52.204-1 Approval of Contract DEC 1989 52.204-2 Security Requirements
Alternate II - APR 1984
MAR 2021
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content MAY 2011 52.204-9 Prohibition on Requiring Certain Internal Confidentiality
Agreements or Statements
JAN 2011
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards
JUN 2020
52.204-13 System for Award Management Maintenance OCT 2018 52.204-14 Service Contract Reporting Requirements OCT 2016 52.204-18 Commercial and Government Entity Code AUG 2020 52.204-19 Incorporation by Reference of Representations and Certifications DEC 2014 52.204-23 Prohibition on Contracting for Hardware, Software, and Services
Developed or Provided by Kaspersky Lab and Other Covered Entities
NOV 2021
52.204-25 Prohibition of Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
NOV 2021
52.204-27 Prohibition on a ByteDance Covered Application JUN 2023
52.208-9 Contractor Uses of Mandatory Sources of Supply or Services MAY 2014 52.209-6 Protecting the Governments Interest when Subcontracting with
Contractors Debarred, Suspended, or Proposed for Debarment
JUN 2020
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
NOV 2021
http://acquisition.gov/
52.209-10 Prohibition on Contracting with Inverted Domestic Corporations NOV 2015 52.215-8 Order of Precedence – Unifor Contract Format OCT 1997 52.219-6 Notice of Total Small Business Set-Aside NOV 2020 52.219-8 Utilization of Small Business Concerns OCT 2022 52.219-28 Post-Award Small Business Program Representation OCT 2022 52.222-1 Notice to the Government of Labor Disputes FEB 1997 52.222-4 Contract Work Hours and Safety Standards – Overtime
Compensation
MAY 2018
52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1998 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance with Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1998 52.222-15 Certification of Eligibility MAY 2014 52.222-20 Contracts for Materials, Supplies, Articles, and Equipment
Exceeding $15,000
JUN 2020
52.222-21 Prohibition of Segregated Facilities APR 2015 52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal
Employment Opportunity for Construction
FEB 1999
52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for Construction APR 2015
52.222-36 Equal Opportunity for Workers with Disabilities JUN 2020 52.222-37 Employment Reports on Veterans JUN 2020 52.222-40 Notification of Employee Rights Under the National Labor
Relations Act
DEC 2020
52.222-50 Combating Trafficking in Person NOV 2021
52.222-54 Employment Eligibility Verification MAY 2022
52.222-55 Minimum Wages Under Executive Order 13658 JAN 2022
52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022
52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts
SEP 2013
52.223-3 Hazardous Material Identification and Material Safety Data FEB 2021
52.223-5 Pollution Prevention and Right to Know Information MAY 2011
52.223-6 Drug-Free Workplace MAY 2001
52.223-11 Ozone-Depleting Substance and High Global Warming Potential Hydrofluorocarbons
JUN 2016
52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners
JUN 2016
52.223-15 Energy Efficiency in Energy-Consuming Products DEC 2007
52.223-17 Affirmative Procurement of EPA-designated Items in Service And Construction Contracts
AUG 2018
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving
JUN 2020
52.223-20 Aerosols JUN 2016 52.223-21 Foams JUN 2016 52.225-5 Trade Agreements DEC 2022 52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.227-1 Authorization and Consent JUN 2020 52.227-2 Notice and Assistance Regarding Patent and Copyright
Infringement
JUN 2020
52.227-3 Patent Indemnity JUN 2020 52.227-4 Patent Indemnity – Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance-Work on a Government Installation JAN 1997 52.228-12 Prospective Subcontractors Requests for Bonds DEC 2022 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds – Construction JUN 2020 52.229-3 Federal, State, and Local Taxes FEB 2013 52.232-5 Payments Under Fixed-Price Construction Contracts MAY 2014 52.232-16 Progress Payments NOV 2021 52.232-17 Interest MAY 2014 52.232-23 Assignment of Claims MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017 52.232-33 Payment by Electronic Funds Transfer – System for Award
Management
OCT 2018
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business Contracts MAR 2023 52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract claim OCT 2004 52.236-1 Performance of Work by the Contractor APR 1984
52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Accident Prevention NOV1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Specifications and Drawings for Construction
Alternate I – APR 1984
FEB1997
52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-1 Changes – Fixed Price
Alternate I – APR 1984
APR 1984
52.243-4 Changes JUN 2007 52.244-2 Subcontracts JUN 2020 52.244-5 Competition in Subcontracting DEC 1996 52.244-6 Subcontracts for Commercial Products and Commercial Services MAR 2023 52.245-9 Use and Charges APR 2012 52.246-12 Inspection of Construction AUG 1996 52.246-21 Warranty of Construction MAR 1994 52.248-3 Value Engineering-Construction OCT 2020 52.249-2 Termination for Convenience of the Government (Fixed-Price)
Alternate I (SEP 1996)
APR 2012
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991
52.217-7 Option for Increased Quantity-Separately Priced MAR 1989 Line Item
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of clause)
52.219-14 Limitations on Subcontracting OCT 2022
(a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
B.1 (i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
B.2 (ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are— B.3 (i) Set aside in accordance with subparts 19.8, 19.13, 19.14, https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/19.000#FAR_19_000 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/16.505#FAR_16_505 https://www.acquisition.gov/far/19.504#FAR_19_504 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F);
or
B.4 (ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(a) Independent contractors. An independent contractor shall be considered a subcontractor.
(b) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded.
When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;
(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded; or
(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.
(c)The Contractor shall comply with the limitations on subcontracting as follows:
https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/8.405-5#FAR_8_405_5 https://www.acquisition.gov/far/16.505#FAR_16_505 https://www.acquisition.gov/far/subpart-19.8#FAR_Subpart_19_8 https://www.acquisition.gov/far/subpart-19.13#FAR_Subpart_19_13 https://www.acquisition.gov/far/subpart-19.14#FAR_Subpart_19_14 https://www.acquisition.gov/far/subpart-19.15#FAR_Subpart_19_15 https://www.acquisition.gov/far/19.504#FAR_19_504
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause—
[Contracting Officer check as appropriate.]
By the end of the base term of the contract and then by the end of each subsequent option period; or
X By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph (e) of this clause will be performed by the aggregate of the joint venture participants.
(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protégé in the joint venture must be more than administrative functions.
(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.
(End of clause)
52.222-35 Equal Opportunity for Veterans JUN 2020
(a) Definitions. As used in this clause-
"Active duty wartime or campaign badge veteran," "Armed Forces service medal veteran," "disabled veteran," "protected veteran," "qualified disabled veteran," and "recently separated veteran" have the meanings given at Federal Acquisition Regulation (FAR)22.1301.
(b) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR 60-300.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified protected veterans, and requires affirmative action by the Contractor to employ and advance in employment qualified protected veterans.
(c) Subcontracts. The Contractor shall insert the terms of this clause in subcontracts valued at or above the threshold specified in FAR 22.1303(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary of Labor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
(End of clause)
52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items
MAY 2008
(a) Definitions. As used in this clause-
Postconsumer material means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item.
Postconsumer material is a part of the broader category of "recovered material."
"Recovered material" means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall-
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to the Contracting Officer.
(End of clause)
52.225-9 Buy American – Construction materials OCT 2022
(a) Definitions. As used in this clause—
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.
However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including…
This is the start of the file's text. The full file is on GovTribe.