1282D719R0002_-_Bridge_Maintenance.pdf
PDF 978 KB Posted
- Attached to
- Bridge Maintenance Federal contract opportunity
- Solicitation number
- 12850819R0002
- Issued by
- Department of Agriculture Forest Service
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 12850819R0002_-_Bridge_Maintenance_-_Amend_3.pdf | ||
| Attachment_10_-_Work_Item_List.xlsx | XLSX spreadsheet | |
| B-1._-_Pre-bid_Meeting_-_Questions_and_Answers.pdf | ||
| B-1._-_Pre-Bid_Meeting_Minutes.pdf | ||
| B-1._-_Pre-Proposal_Conference_Slides.pdf | ||
| 12850819R0002_-_Bridge_Maintenance_-_Amend_2.pdf | ||
| 1282D719R0002_-_Bridge_Maintenance_-_Amend_1.pdf | ||
| Attachment_1_-_Excerpts_from_FS_Sign_Installation_Guide.pdf | ||
| Attachment_5_-_Drawiings.pdf | ||
| Attachment_4_-_Bridge_Sketch.pdf | ||
| Attachment_7.1_-_WD_-_Colorado.pdf | ||
| Attachment_7.2_-_WD_-_Wyoming.pdf | ||
| 1282D719R0002_-_Bridge_Maintenance_-_r.pdf | ||
| Attachment_3_-_FS_Supplemental_Specifications.pdf | ||
| Attachment_2_-_Maps.pdf | ||
| Attachment_8_-_Section_K_to_Return.pdf | ||
| Attachment_9_-_Perfomance_Certification.docx | DOCX document |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
955565
WHITE RIVER NATIONAL FOREST
900 GRAND AVENUE
GLENWOOD SPRINGS CO 81602-0948
82D7
Email: robert.e.hall@usda.gov
ROBERT HALL 970-945-3217
1x 06/04/2019
12850819R0002
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
C.1 Scope of Contract Medicine Bow/Routt National Forests and Thunder Basin National
Grassland¿s (MBRTB) Bridge Maintenance is located within the boundary of the
Medicine Bow/Routt National Forests.
C.2 Description of Work The project includes the following work on/adjacent to road bridges on the MBRTB:
- Roadside brushing along the approaches and adjacent to bridge abutments and wingwalls;
- Replacing timber running planks (wearing surface);
- Replacing timber bumper strips at ends of bridges;
- Installing/replacing[1] W5-3 (One Lane Bridge) warning signs adjacent to bride approaches; and
- Installing/replacing1 OM-3 Type 3 Object Markers adjacent to bridge approaches
The Government estimates the value of this contract to be between $100,000 -
$250,000.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
30 365 calendar days and complete it within ________________ ________________ calendar days after receiving
07/03/2019
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
WHITE RIVER NATIONAL FOREST
900 GRAND AVENUE
GLENWOOD SPRINGS CO 81602-0948
82D7
ROBERT E. HALL
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 45
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
12850819R0002
Medicine Bow-Routt NF - Bridge Maintenance
Contract
This is a Request for Proposals for bridge mainteance in accordance with Section C.
Contracting Officer: Robert Hall -robert.e.hall@usda.gov - 970-945-3217
Delivery: 09/30/2020
Delivery Location Code: 8508
MEDICINE BOW NATIONAL FOREST
2468 JACKSON ST
LARAMIE WY 82070 US
Period of Performance: 08/01/2019 to 09/30/2020
001 MBRTB Bridge Maintenance - See Section B for
Schedule of Items
Product/Service Code: Z1LB
Product/Service Description: MAINTENANCE OF
HIGHWAYS/ROADS/STREETS/BRIDGES/RAILWAYS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
12850819R0002 MBRTB NF - Bridge Maintenance Page 3 of 45
Table of Contents
SECTION B--SCHEDULE OF ITEMS
SECTION C-- STATEMENT OF WORK/DESCRIPTION/SPECIFICATIONS
SECTION D--PACKAGING AND MARKING
SECTION F--DELIVERIES OR PERFORMANCE
SECTION G--CONTRACT ADMINISTRATION DATA
SECTION H--SPECIAL CONTRACT REQUIREMENTS
SECTION I--CONTRACT CLAUSE
SECTION—J--LIST OF ATTACHMENTS
SECTION—K--REPRESENTATIONS, CERTIFICATIONS
SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS
SECTION M--EVALUATION FACTORS FOR AWARD
12850819R0002 MBRTB NF - Bridge Maintenance Page 4 of 45
PART I—THE SCHEDULE -
SECTION B--SCHEDULE OF ITEMS
B-1 - SCHEDULE OF ITEMS
ITEM
NO.
DESCRIPTION
PAY
UNIT
EST.
QTY.
UNIT
PRICE
TOTAL
PRICE
15101
Mobilization
Lump Sum 1
23050
Roadside Brushing
Mile 1.2
55701A
Treated Structural Timber and Lumber, Running
Planks
MFBM 15.1
55701B
Treated Structural Timber and Lumber, Bumper Strips
MFBM 0.15
63304
Sign, W5-3 One Lane Bridge
Each 30
63307
Object Marker, Type 3
Each 116
MBFM – Thousand Board Feet Mile
Payment will be made on actual work performed as described in FP-14 109.01 unless otherwise noted.
B-2 NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction
Contracts, shall not be in addition to the contract price. Include bond payments under General Requirements.
12850819R0002 MBRTB NF - Bridge Maintenance Page 5 of 45
SECTION C-- STATEMENT OF WORK/DESCRIPTION/SPECIFICATIONS
C.1 Scope of Contract Medicine Bow/Routt National Forests and Thunder Basin National Grassland’s (MBRTB) Bridge Maintenance Contract is located within the boundary of the Medicine Bow/Routt National Forests. The contract will be awarded based on a best value to the
Government determination.
C.2 Description of Work
The project includes the following work on/adjacent to road bridges on the MBRTB:
Roadside brushing along the approaches and adjacent to bridge abutments and wing walls;
Replacing timber running planks (wearing surface);
Replacing timber bumper strips at ends of bridges;
Installing/replacing[1] W5-3 (One Lane Bridge) warning signs adjacent to bride approaches; and
Installing/replacing1 OM-3 Type 3 Object Markers adjacent to bridge approaches and other incidental work related to the above items in accordance with the plans, specifications, and other applicable contract documents. Contractor shall provide all necessary heavy equipment, manpower, transportation and operating supplies and other incidentals to accomplish this work.
Bridges included in this contract include: (Route Number, Milepost, Bridge Name, Lat/Long)
100 2.1 North Brush Creek 41.36951872, -106.5230664
100 14.9 Turpin Creek 41.46555129, -106.3972386
100 19.4 Medicine Bow River 41.51465358, -106.3710302
101 1.1 North Fork Little Laramie 41.35100782, -106.1647433
101 13.25 North Fork Rock Creek 41.45930846, -106.2297817
105 7.67 Medicine Bow River 41.43285900, -106.3475320
105 12.36 Turpin Creek 41.44561000, -106.3872000
206 1.7 South French Creek(Lower) 41.24184574, -106.4555317
219 0.1 North Brush Creek 41.40625750, -106.4800252
225 12.3 South French Creek 41.25914453, -106.4155690
236 2.8 South French Creek 41.27438554, -106.3690820
241 0.1 North Brush Creek 41.37379522, -106.5122571
261 22.25 Main Fork Bow River 41.52589297, -106.3921023
330 0.2 North Fork Little Laramie 41.35460400, -106.1690750
338 14.0 Douglas Creek 41.22237158, -106.2347491
443 6.94 South Spring Creek 41.22300111, -107.0177111
452 8.5 Jack Creek 41.28602386, -107.1206695
452 11.38 North Spring Creek 41.26871164, -107.0839944
498 6.53 South Fork Big Creek 41.01606569, -106.5268174
500 19.16 North Mullen Creek 41.23561651, -106.3667459
500 26.0 French Creek 41.22540268, -106.4852988
503.1 3.0 King Solomon Creek 40.90893647, -106.9339804
509 2.5 Lake Creek 41.12017761, -106.2269199
512 8.5 Douglas Creek 41.11605638, -106.2459886
543 4.5 Douglas Creek 41.16810117, -106.2622336
543 5.0 Keystone Creek 41.16979000, -106.2664000
543 6.2 Horse Creek 41.18158000, -106.2745000
740.1 3.1 S. Fork Michigan River 40.49146998, -106.0083208
770.1 0.1 S. Fork Michigan River 40.47168023, -106.0089706
[1] (i.e. Install new signs and posts where none currently exist; replace existing signs and posts where they exist. Old signs and posts become property of the Contractor and shall be removed legally from NFS lands)
12850819R0002 MBRTB NF - Bridge Maintenance Page 6 of 45
780.1 0.1 S. Fork Michigan River 40.48158000, -106.0071140
807 3.27 Battle Creek 41.08394560, -107.1731237
More detailed descriptions of work required are described in Section C.2.1-C.2.5 and in the plans and specifications:
C.2.1 Roadside Brushing
Cut all limbs, residual slash, live roadside brush, and small trees (6 inches diameter, or less, at the point of cut) inside the brushing limits (see drawings) no higher than 4 inches above ground level (6 inches for machine brushing). If large rocks or other large obstructions are encountered, cut no higher than 6 inches above the obstruction. Branches on remaining trees shall be trimmed to a clearing height 14 feet above the road surface, or to a limit of 60% of the tree’s height, whichever is less. Limbs of trees shall be cut so as to not protrude within the clearing limits. Trees shall be limbed on all sides of the tree trunk. Cut limbs flush with the bole without damaging bole.
C.2.2 Running Plank Replacement
Remove existing timber running planks, including spikes and bolts. Minimize damage to the existing bridge deck and bulkhead planks underneath. Dispose of all materials off of NFS lands in accordance with all applicable local, state, and federal laws and regulations.
Thoroughly Clean and sweep the bridge deck, including between deck planks, visible tops of stringers, and drainage scuppers to remove all wood chips, splinters, dirt, gravel and any other deleterious material; provide a smooth surface for new running planks.
Minimize debris entering stream as much as practicable.
Provide and install new 3x12 (S1S1E), No. 2 or Better, West Coast Douglas Fir-Larch running planks, treated according to the requirements on Sheet G-02 of the plans. Install atop existing deck planks in one (1) 12 feet wide section as shown on the plans.
Minimum length of any plank is 12 feet, except where required to be cut at joint with bumper strips. Stagger plank end joints at least 3 feet. Lay running planks heart side and cup side down. Install planks snugly against each other and so that the entire width of running plank group is centered between the existing curbs.
Pre-drill ¼-inch pilot holes and field treat holes as described on Sheet G-02 of the plans before driving nails. Fasten the planks with 6-inch x 3/8-inch diameter galvanized ring shank nails, maintaining 2 inch edge spacing and 4 inch end spacing on all members. Space nails at ±2 feet, alternating edges in driving each spike. Counter-sink all nail heads minimum flush with driving surface.
C.2.3 Bumper Strip Replacement
Remove existing timber bumper strips, including spikes and bolts. Minimize damage to the existing bridge deck and bulkhead planks underneath. Dispose of all materials off of NFS lands in accordance with all applicable local, state, and federal laws and regulations.
Thoroughly Clean and sweep the bridge deck, including between deck planks, visible tops of stringers, and drainage scuppers to remove all wood chips, splinters, dirt, gravel and any other deleterious material; provide a smooth surface for new bumper strips.
Minimize debris entering stream as much as practicable.
Provide and install new 3x12 (rough sawn), No. 2 or Better, West Coast Douglas Fir-Larch bumper strips, treated according to the requirements on Sheet G-02 of the plans. Install flush with outboard face of bulkhead planks. Lay the bumper strips heart side and cup side down. Pre-drill ¼-inch pilot holes and field treat holes as described on Sheet G-02 of the plans before driving nails. Fasten the planks with 6-inch x 3/8-inch diameter galvanized ring shank nails, maintaining 2 inch edge spacing and 4 inch end spacing on all members. Space nails at ±2 feet, alternating edges in driving each spike. Counter-sink all nail heads minimum flush with driving surface.
C.2.4 W5-3 (One Lane Bridge) Sign Replacement
Provide and Install/Replace* two (2) new 30"x30" standard W5-3 'One Lane Bridge' signs per bridge. Substrate shall be at least
0.08" thick aluminum with Diamond Grade or High Intensity Prismatic (HIP) fluorescent yellow retroreflective sheeting with black silk screened print.
Mount on new 4x4 treated posts with 3/8” dia. tamper-proof bolts in accordance with the MUTCD (current edition) and Forest
Service Sign Installation Guide (applicable excerpts included as attachment J.1).
Embed posts firmly in ground to Minimum Burial Depth and drill holes in posts for breakaway capability in accordance with the
MUTCD (current edition) and Forest Service Sign Installation Guide (applicable excerpts included as attachment J.1).
12850819R0002 MBRTB NF - Bridge Maintenance Page 7 of 45
C.2.5 OM-3 (Type 3 Object Marker) Replacement
Provide and Install/Replace* four (4) new 12"x36" standard Type 3 Object Markers, one at each corner of the bridge. Substrate shall be at least 0.08” thick aluminum with Diamond Grade or High Intensity Prismatic (HIP) fluorescent yellow retroreflective sheeting with black silk screened print.
Mount on new 4x4 treated posts with 3/8”pro dia. tamper-proof bolts in accordance with the MUTCD (current edition) and Forest
Service Sign Installation Guide (applicable excerpts included as attachment J.1).
Embed posts firmly in ground to Minimum Burial Depth and drill holes in posts for breakaway capability in accordance with the
MUTCD (current edition) and Forest Service Sign Installation Guide (applicable excerpts included as attachment J.1).
C.3 Location of Project
The project area is described herein and shown on the attached maps (See Section J, attachment J.2). The work is located at or near
31 individual road bridges within the boundary of the Medicine Bow/Routt National Forests. Upon request, more detailed digital maps of bridge locations superimposed on Motor Vehicle Use Maps (MVUM) will be made available to prospective bidders; these files contain geospatial information, can be used with mobile applications such as Avenza, and are very large. After award, MVUMs with hand drawn locations of all bridges will be made available to the Contractor.
C.4 Performance of the Work
All work shall be conducted in a safe and expedient manner and in conformance with the specifications referenced in Section C.8 and Section J, attachment J.3. When applicable, traffic control shall be in accordance with standards set forth in the most current edition of the Manual on Uniform Traffic Control Devices (MUTCD). Traffic Control shall be considered incidental to other pay items. All work shall be conducted by personnel fully qualified to perform such tasks assigned and shall be supervised by an on-site designated Contractor’s Representative.
C.5 Equipment All equipment shall be in good repair, and capable of accomplishing assigned tasks in a safe and environmentally acceptable manner. Where applicable, all equipment shall be fitted with approved spark arrestors. All repairs to equipment under this contract shall be made and paid for by the Contractor. Equipment may be owned, rented, or subcontracted.
All equipment shall be cleaned of earthen and vegetative materials that may contain weed seed prior to delivery onto National Forest
Lands. If using equipment on multiple other contracts at one time, or if there are long mobilization distances between sites on the same contract, the Contracting Officer may require cleaning of equipment between the project sites (bridge sites).
C.6 Equipment and Materials Storage & Staging Upon concurrence from the Contracting Officer, certain areas on the National Forests may be used on a case-by-case basis for storage of equipment and/or materials during active construction and/or maintenance periods. The Contractor shall be responsible for protection of items stored on Government property, and shall ensure adequate safety measures are maintained at such sites.
C.7 References in the Statement of Work/Specifications
Any reference in this solicitation to Engineer, Forest Engineer, Project Engineer, Forest Service, COR, shall be replaced with
Contracting Officer.
C.8 Standard Specifications
“Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-14,” U.S. Customary Units, is applicable for this project, and is included by reference only. The requirements contained in these Standard Specifications are hereby made a part of this solicitation and any resulting work. These specifications can be viewed at no cost on the FHWA website, which also gives ordering information: https://flh.fhwa.dot.gov/resources/specs/. At least one (1) copy of these specifications is expected to be on-site with the contractor’s personnel at all times for reference.
Section J, attachment J.3 of this contract contains Forest Service Supplemental Specifications (FSSS) that supplement and/or modify the Standard Specifications. The Standard, and Supplemental Specifications shall all be used in conjunction with each other to properly determine the correct specification for each Pay Item in the Schedule of Items.
C.9 Price Range
The price range for the contract is between $100,000 and $250,000.
https://flh.fhwa.dot.gov/resources/specs/
12850819R0002 MBRTB NF - Bridge Maintenance Page 8 of 45
C.10 Government-Furnished Property
Government-Furnished property will not be provided.
SECTION D--PACKAGING AND MARKING
None
12850819R0002 MBRTB NF - Bridge Maintenance Page 9 of 45
SECTION E--INSPECTION AND ACCEPTANCE
E-1. FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: : www.acquisition.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
Clause
Number
Title Date
52.246-12 Inspection of Construction AUG 1996
E-2. AGAR 452.246-70 Inspection and Acceptance (FEB 1988)
(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.
(b) Inspection and acceptance will be performed at the project site.
http://www.acquisition.gov/far/
12850819R0002 MBRTB NF - Bridge Maintenance Page 10 of 45
SECTION F--DELIVERIES OR PERFORMANCE
F-1. FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: http://www.arnet.gov/far/
FAR: www.acquisition.gov/far/
Clause
Number
Title Date
52.242-14 Suspension of Work APR 1984
F-2. FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 30 calendar days after the date the
Contractor receives the notice to proceed. Contract time will be a minimum of 365 days. The time stated for completion shall include final cleanup of the premises. The actual final completion date will be determined in discussions and will be based on the assumption that the successful offeror will receive the notice to proceed by July 10, 2019.
http://www.arnet.gov/far/
12850819R0002 MBRTB NF - Bridge Maintenance Page 11 of 45
F.3 REQUIRED SUBMITTALS
The following is a general summary of the required submittals. Other submittals are required as specified elsewhere in this contract.
Title Reference. When Required
Schedule of Work Section F When proposals are due and updated prior to NTP.
Bio-based and Recovered Materials Requirements Section I When proposals are due
Job Specific Safety Plan Section H Prior to Notice to
Proceed
Copy of Required Insurance coverage
Section H Prior to Notice to
Proceed
Notification of starting work
Subcontracting
Section G Prior to subcontractor
Release of Claims Form Section I Prior to final payment
Material Certifications, Section C Prior to on-site work
Submittal requirements for this Project are EXTENSIVE. They include, but are not limited to: Biobased and
Recovered materials requirements, Product Data, Product Schedules, Traffic Control, Shop Drawings, Mock-ups, Samples, Material Certifications, Individual Sections in the specifications detail most, but not all, submittals requirements for this contract. Other submittals requirements may be contained in the Drawings or otherwise referenced. It is the contractor’s responsibility to capture all the required submittals, shop drawings, certifications, testing reports, etc., as required for this Project, and develop a Submittal Schedule for approval by the Contracting
Officer as described in Section 01 3300 Shop Drawings, Product Data, and Submittals. See Submittal list in Section
01 3300.
12850819R0002 MBRTB NF - Bridge Maintenance Page 12 of 45
SECTION G--CONTRACT ADMINISTRATION DATA
G-1. AGAR 452.215-73 Post Award Conference (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled and as soon as possible or within 14 days after the date of contract award. The conference will be held at mutually agreed upon location. This meeting is also referred to as the Pre-work Meeting.
G-2. Work Progress Schedule
The Contractor shall be required to present on the solicitation due and at the pre-work conference a written plan of work providing for the orderly and timely completion of the contract requirements. This plan is subject to the approval of the Contracting Officer. The schedule may be modified in writing during the course of the contract when conditions warrant it.
If the work progress falls behind schedule, the Contractor shall take such action as necessary to ensure that the timely completion of the contract is not jeopardized. In addition, the Contracting Officer may require the Contractor to submit a revised plan of work showing how he intends to complete the project on time and in compliance with all contract requirements
G-3. Contract Release
When submitting final payment, Contractor shall provide a signed and dated contract release that includes the following information: "In consideration of receipt of final payment in the amount of $XXXXXXX, Contractor hereby releases the
United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein. Reservations:______________"
G-4. Invoices and Payments
All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System. The "Submit
Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in previous communications from USDA and Treasury.
This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm Ensure your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. Offeror must have an established account prior to commencement of work.
Invoice Processing Platform (IPP) does not allow for the contractor to change the description of the line items being invoiced against and therefore an itemized invoice must be uploaded as an attachment(s) in accordance with FAR
52.232-5 - Payments under Fixed-Price Construction Contracts (May 2014).
Itemized invoices shall include at a minimum:
Contractor Name & Address
Contract numbers
Invoice Number
Description and Line Item of Services or work completed
Date of services or completion.
https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm https://www.ipp.gov/vendors/enrollment-vendors.htm
12850819R0002 MBRTB NF - Bridge Maintenance Page 13 of 45
Percentage of Contract Completion
G-5. Forest Service Representative
Robert Hall shall serve as the Procuring Contracting Officer (PCO) and as the Administrative Contracting Officer
(ACO) on this contract. The Contracting Officer has full warrant authority over all contract issues. The CO can be reached at 970-945-3217 or robert.e.hall@usda.gov.
A Contracting Officer Representative (COR) will be appointed for this contract upon award. The COR delegated authority, responsibilities and contact information will be defined on a delegation letter issued after contract award.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H-1. FAR 52.236-4 Physical Data (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
H-2. AGAR 452.237-74 Key Personnel. (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel: CONTRACTOR
REPRESENTATIVE, FOREMAN/WOMAN, and QUALITY INSPECTOR.
(b) During the first ninely (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the
Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting
Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
H-3. Safety
Pursuant to FAR 52.236-13 Accident Prevention Alt. I, the Contractor shall prepare a Safety Plan which addresses the specific hazards of the work site, and shall include working in construction areas and asbestos abatement, and that employees meet all OSHA requirements. The Contractor shall identify the specific conditions that are considered to be hazardous.
The Contractor shall submit the safety plan shall within 10 calendar days after award of contract.
The Safety Plan shall also address the personal protective equipment and mitigating measures the Contractor will do to increase safety on the worksite. Contractor’s operations shall facilitate Forest Service’s safe and practical inspection of
Contractor’s operations and conduct of other official duties on Contract Area. Contractor has all responsibility for compliance with safety requirements for Contractor's employees. In the event that a conflict develops between the requirements of this contract or agreed upon methods of proceeding hereunder and State or Federal safety requirements, the contract shall be modified and Contractor may request an equitable adjustment. The Contracting Officer’s
12850819R0002 MBRTB NF - Bridge Maintenance Page 14 of 45
Representative (COR) has the authority to immediately suspend performance in the event that a safety of life issue is encountered on the work site.
12850819R0002 MBRTB NF - Bridge Maintenance Page 15 of 45
PART II--CONTRACT CLAUSES and PROVISIONS
SECTION I--CONTRACT CLAUSE
I-1. FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this address: www.acquisition.gov/far/
52.203-5 Covenant against Contingent Fees (May 2014) 52.203-7 Anti-Kickback Procedures (May 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (May 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (May 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (Oct 2010) 52.203-17 Contractor Employee Whistleblower Rights and Requirements (Apr 2014) 52.203-18 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements on Statements--
Representation (Jan 2017) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011) 53.204-7 System for Award Management (Oct 2018) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (OCT 2018) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-16 Commercial and Government Entity Code Reporting (JUL 2016) 52.204-17 Ownership or Control of Offeror (July 2016) 52.204-18 Commercial and Government Entity Code Maintenance (JUL 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-20 Predecessor of Offeror (July 2016) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and
Other Covered Entities (2018).
52.209-2 Prohibition on Contracting With Inverted Domestic Corporations--Representation (Nov 2015) 52,209-5 Certification Regarding Responsibility Matters (Oct 2015) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for
Debarment (OCT 2015) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (Oct 2018) 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations (Nov 2015) 52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law
(Feb 2016) 52.210-1 Market Research (Apr 2011) 52.211-18 Variation in Estimated Quantity (APR 1984) 52.215-2 Audit and Records -- Negotiation (OCT 2010) 52.217-7 Option for Increased Quantity - Separately Priced Line Item ( 52.219-6 Notice of Total Small Business Set-Aside (Nov 2011) 52.219-8 Utilization of Small Business Concerns (NOV 2016) 52.219-14 Limitations on Sub-Contracting (Jan 2017) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Work Hours and Safety Standards – Overtime Compensation (May 2018) 52.222-5 Construction Wage Requirements – Secondary Site of the Work (May 2014) 52.222-6 Construction Wage Rate Requirements (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Requirements and Related Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988)
12850819R0002 MBRTB NF - Bridge Maintenance Page 16 of 45
52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-25 Minimum Wages under Executive Order 13658 (Dec 2015) 52.222-26 Equal Opportunity (SEP 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (Oct 2015) 52.222-37 Employment Report on Veterans (Feb 2016) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-55 Minimum Wages under Executive Order 13658 (DEC 2015) 52.222-62 Paid Sick Leave under Executive Order 13706 (Jan 2017) 52.223-1 Bio based Product Certification (May 2012) 52.223-2 Affirmative Procurement of Bio-based Products under Construction Contracts (SEP 2013) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-6 Drug-Free Workplace (MAY 2001) 52.223-15 Energy Efficiency in Energy-Consuming Products (Dec 2007) 52.223-17 Affirmative Procurement of EPA-Designated Items in Construction Contracts (Aug 2018) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011) 52.223-21 Foams (Jun 2016)52.225-9 Buy American – Construction Materials (MAY 2014) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (Jan 1997) 52.228-11 Pledges of Assets (JAN 2012) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds – Construction (Oct 2010) 52.229-3 Federal, State, and Local Taxes (Feb 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest Charges 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (Oct 2018)) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013) 52.233-1 Disputes (MAY 2014) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-6 Superintendence by the Contractor (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-8 Other Contracts (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equip, Utilities, and Improvements (APR 1984) 52.236-10 Operations and Storage Areas (APR 1984) 52.236-11 Use and Possession Prior to Completion (APR 1984) 52.236-12 Cleaning Up (APR 1984) 52.236-13 Accident Prevention (NOV 1991) Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984) 52.236-16 Quantity Surveys (Apr 1984) 52.236-17 Layout of Work (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) Alternate I (APR 1984) 52.236-26 Preconstruction Conference (FEB 1995) 52.236-28 Preparation of Proposal-Construction (Oct 1997) 52.242-14 Suspension of Work (Apr 1984) 52.243-4 Changes (JUN 2007) 52.244-6 Subcontracts for Commercial Items (NOV 2017) 52.245-1 Government Property (Jan 2017) 52.246-12 Inspection of Construction (AUG 1996) 52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2015)
12850819R0002 MBRTB NF - Bridge Maintenance Page 17 of 45
52.249-1 Termination for Convenience of the Government (Fixed-Price) (APR 1984) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)
452.236-71 Prohibition against the Use of Lead-Paint (NOV 1996)
452.236-72 Use of Premises (NOV 1996)
452.236-76 Samples and Certificates (FEB 1988)
452.236-77 Emergency Response (NOV 1996)
I-2. FAR 52.211-13 – Time Extensions (Sept 2000)
Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered.
(End of Clause)
I-3. FAR 52.217-7 – Option for Increased Quantity – Separately Priced Line Item (Mar 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the
Contractor before contact completion. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.
(End of Clause)
I.4. FAR 52.222-36 – Equal Opportunity for Workers with Disabilities. (Jul 2014)
(a) Equal opportunity clause. The Contractor shall abide by the requirements of the equal opportunity clause at 41 CFR
60.741.5(a), as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.
(b) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of
$15,000 unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract
Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.
I-5. FAR 52.225-9 -- Buy American–Construction Materials (May 2014)
(a) Definitions. As used in this clause--
“Commercially available off-the-shelf (COTS) item”—
(1) Means any item of supply (including construction material) that is—
12850819R0002 MBRTB NF - Bridge Maintenance Page 18 of 45
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
“Component” means an article, material, or supply incorporated directly into a construction material.
“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the
Government are supplies, not construction material.
“Cost of components” means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
“Domestic construction material” means—
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if—
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
“Foreign construction material” means a construction material other than a domestic construction material.
“United States” means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
12850819R0002 MBRTB NF - Bridge Maintenance Page 19 of 45
(1) This clause implements the 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: ______ [Contracting Officer to list applicable excepted materials or indicate “none”]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute.
(1)
(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
12850819R0002 MBRTB NF - Bridge Maintenance Page 20 of 45
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the
Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the
Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison
Construction material description Unit of measure Quantity Price (dollars) *
Item 1
Foreign construction material
Domestic construction material
Item 2
Foreign construction material
Domestic construction material
[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]
[Include other applicable supporting information.]
[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]
(End of Clause)
I-6. FAR 52.225-10 Notice of Buy American – Construction Materials (MAY 2014)
(a) Definitions. “Commercially available off-the-shelf (COTS) item,” “construction material,” “domestic construction material,” and “foreign construction material,” as used in this provision, are defined in the clause of this solicitation entitled “Buy American--Construction Materials” (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before
12850819R0002 MBRTB NF - Bridge Maintenance Page 21 of 45 submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at
FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—