QandA August-13-2020.pdf

PDF 122 KB Posted

Attached to
Roof Replacement - Stillwater, OK Federal contract opportunity
Solicitation number
12805B20Q0081
Issued by
Department of Agriculture Agricultural Research Service Field Research Implementation and Information Delivery Plains Area

View the file

Other files for this federal contract opportunity

Other files attached to Roof Replacement - Stillwater, OK, newest first.
File Type Posted
QandA August-7-2020.pdf PDF
Appendix B Downspout Photos.pdf PDF
QandA_ Aug_6_2020.pdf PDF
Sol_12805B20Q0081.pdf PDF
Attachment 1 Wage Determination OK20200063.pdf PDF
Attachment 3 ARS-371.pdf PDF
Attachment 5 FAR Deviation Accelerated Payments to Small Business.pdf PDF
Attachment 4 ARS-372.pdf PDF
Attachment 2 SOW v1.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

August 13, 2020 Questions and Answers

12805B20Q0081

1. The roof replace is a TPO membrane. Is the membrane liquid or rolled material?

SOW item 3.1.4 states “The Contractor shall provide white, 0.60”, mechanically attracted (attached) to purlins, TPO membrane roofing system.” The 0.60” thickness shows the membrane thickness for a rolled application.

2. Is this project tax exempt? This project is tax exempt IAW with Oklahoma tax procedures.

3. a) Is a Bid Bond Required with the bid submission?

Yes, see page 24-25 of the solicitation.

b) Is a Performance and Payment Bond to be included in the price of the bid?

Yes, in accordance with AGAR 452.232-70 Reimbursement for Bond Premiums—Fixed Price Construction on page 17 of the solicitation.

4. Please verify the new roof system going back on the roof, is as follows: 60 mil tpo OVER 1/2"

CoverBoard OVER eps Flute Fill Insulation. All mechanically fastened over a metal deck.

No. As stated previously in earlier Q&A’s, SOW Page 5, Paragraph 3.1.2 states “1.5” roof board insulation over existing PBR roof system”; and 3.1.3 states “1.5” roof board insulation cover board over new 1.5” roof board insulation” for a total of 3” of roof board insulation above the filled flutes between the ribs of the metal roof.

5. I did not see a bid form - I plan to send a created formal proposal (Please advise if this is incorrect.

Please follow the instructions in the solicitation under Section L.3 (page 24) Also, Where/Who do I send this proposal to specifically?

Same, see Section L.3 (page 24)

6. When will the work be performed (i.e. November 2020?... January 2021?) To be completed in

365 Days after award. Date of Award expected to be in September 2020.

7. On the eaves instead of tapered insulation. Can we install perimeter metal with 1.5" tall ribs to keep water from running over sides OR install 4 2x4 wood nailers which will be taller than roof?

That will prevent water from running over the edge also. Plus it's more structurally sound to fasten metal trim to.

Previous clarification change dated August 7, 2020, to Paragraph 3.1.7, “Gutter demolition and replacement sketches and gauges are to be submitted for review. Insulation at eaves shall be tapered from 3” to 1” thickness over 2 ft. length with 1” above the exterior wall.” is to be deleted.

Substitute “Paragraph 3.1.7, Add the following “Gutter demolition and replacement sketches and gauges are to be submitted for review. Edge nailers shall be installed on roof edges, for attachment of gutters, drip edges, and rake trim. Edge nailers shall be equivalent in thickness as insulation above the roof panel ribs, approximately 3” on eaves. Existing metal eave overhangs may be cut for the edge nailer installation to the existing metal panels and eave struts.”