This file is a Supplemental Specifications document for the Bushy Knoll Crush and Stockpile Project, which modifies the Federal Highway Administration's Standard Specifications for Construction of Roads and Bridges (FP-24 U.S. Customary Units, 2024) for Forest Service projects. The specifications establish technical requirements for pit and quarry development, material extraction, crushing, and stockpiling of aggregate materials, including clearing, grubbing, rock blasting, and disposal of construction debris. Key technical requirements include Forest Products Utilization Standards specifying minimum merchantable timber specifications (saw logs minimum 14 inches diameter at small end, 16-foot maximum length; non-saw logs minimum 9 inches; pole logs minimum 6 inches), surface aggregate gradation limits (R3-G classification with 7-19 percent passing No. 200 sieve), Los Angeles abrasion of 35 percent maximum, durability index of 35 minimum, and 75 percent fractured faces minimum. The specifications require contractors to submit erosion control plans 30 days prior to construction start, obtain all necessary permits from Arizona Department of Environmental Quality, comply with Mine Safety and Health Administration regulations (30 CFR Part 56) and Forest Service Manual 7190 for explosives and blasting, limit public traffic delays to 30 minutes maximum per passage when roads remain open, and implement comprehensive quality control and traffic control supervisor requirements. Material disposal methods include windrowing, scattering, chipping, debris matting, decking, and removal to designated locations, with merchantable timber decked at designated government locations. The contract is a Total Small Business Set-Aside with a 500-employee size standard under NAICS code 212321 (Construction Sand and Gravel Mining), and requires a bid guarantee of 20 percent of the bid price.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUSHY KNOLL CRUSH AND STOCKPILE PROJECT

FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS

STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS (FP-24 U.S. CUSTOMARY UNITS) (2024) The Standard Specifications of Roads and Bridges on Federal Highway Project (FP-24 U.S. Customary Units), 2024 are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.

The 902-page book entitled “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24 U.S. Customary Units), is available from:

Headquarters Washington DC David K. Green Construction Standards Engineer Internet: David.Green@fhwa.dot.gov Mail: Federal Highway Administration

HFPD-3

400 Seventh Street, SW Washington, DC 20590 https://flh.fhwa.dot.gov/resources/specs/

Contents

PREFACE3
Section 101. – TERMS, FORMAT, AND DEFINITIONS3
Section 102. - BID, AWARD, AND EXECUTION OF CONTRACT7
Section 103. – SCOPE OF WORK7
Section 104. – CONTROL OF WORK7
Section 105. – CONTROL OF MATERIAL7
Section 106. – ACCEPTANCE OF WORK7
Section 108. - PROSECUTION AND PROGRESS7
Section 109. - MEASUREMENT AND PAYMENT8
Section 153. – CONTRACTOR QUALITY CONTROL9
Section 155. – SCHEDULES FOR CONSTRUCTION CONTRACTS9
Section 156. – PUBLIC TRAFFIC10
Section 157. – SOIL EROSION AND SEDIMENT CONTROL12
Section 201. - CLEARING AND GRUBBING12
Section 203. - REMOVAL OF STRUCTURES AND OBSTRUCTIONS13
Section 205. - ROCK BLASTING14
Section 314. - STOCKPILED AGGREGRATES15
Section 703. - AGGREGATE16
Section 703. - R3-G FOREST SERVICE SURFACE AGGREGATE16

PREFACE

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-24 for construction of National Forest System Roads. The Forest Service Supplemental Specifications (FSSS) shall be incorporated in the FP-24. The applicable specifications for the project will be the FP-24 as modified by the FSSS.

Section 101. – TERMS, FORMAT, AND DEFINITIONS Add the following paragraph to Subsection 101.01 Meaning of Terms:

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

Section 101. – TERMS, FORMAT, AND DEFINITIONS Add the following to Subsection 101.03 Abbreviations:

(a) Acronyms.

AGAR — Agriculture Acquisition Regulations AFPA — American Forest and Paper Association FSSS – Forest Service Supplemental Specifications MSHA — Mine Safety and Health Administration NESC — National Electrical Safety Code WCLIB — West Coast Lumber Inspection Bureau

(d) Miscellaneous unit abbreviations.

MP - milepostlocation
ppm - parts per millionvolume
STA – stationlocation
MFBM - thousand feet board measurevolume

Section 101. – TERMS, FORMAT, AND DEFINITIONS Make the following changes to Subsection 101.04 Definitions:

Delete these definitions and replace with the following:

Bid Schedule — The Schedule of Items.

Bridge — A structure, including supports, erected over a depression or an obstruction such as water along a road, a trail, or a railway and having a deck for carrying traffic or other loads.

Contractor — The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “Purchaser”.

Culvert — Any structure with a bottom, regardless of fill depth, depth of invert burial, or presence of horizontal driving surface, or any bottomless (natural channel) structure with footings that will not have wheel loads in direct contact with the top of the structure.

Drawings —Design sheets or fabrication, erection, or construction details submitted to the CO by the Contractor.

Neat Line — A line defining the proposed or specified limits of an excavation or structure.

Notice to Proceed — (Public Works Contracts) Written notice to the Contractor to begin the contract work. (Timber Contracts) does not apply, replace NTP with Contract Award.

Right-of-Way — A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following definitions:

Adjustment in Contract Price — “Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change — “Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Forest Service — The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Forest Service Supplemental Specifications – The Forest Service uses supplemental specifications to modify the FP-24 to meet the agency needs and intents. FSSS revise the FP-24 by adding, deleting, replacing, revising, replacing part of entire sections or subsections or adding new sections to the FP..

Pioneer Road — Temporary construction access built along the route of the project.

Purchaser — The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse — A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order — An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Utilization Standards — The minimum size and percent soundness of trees described in Public Works contract specifications or Timber Sale and stewardship contract provisions to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms

Section 102. - BID, AWARD, AND EXECUTION OF CONTRACT Delete Section 102 Bid, Award, and Execution of Contract in its entirety.

Section 103. – SCOPE OF WORK Delete all of Section 103 Scope of Work except Subsection 103.01 Intent of Contract.

Section 104. – CONTROL OF WORK Delete Subsection 104.07 Coordination of Contract Documents.

Section 104. – CONTROL OF WORK Add the following Subsection 104.12 Use of Roads by Contractor:

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

Section 105. – CONTROL OF MATERIAL Delete second paragraph and subparagraphs (a) and (b) in Subsection 105.05 Use of Material Found in the Work and replace it with the following:

The right to use and process material found in the work excludes the use and processing of material for nongovernment contract work, except for the disposal of waste material. Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. Place excess material at government-approved agreed to location(s), at no additional cost to government.

Section 106. – ACCEPTANCE OF WORK Delete the 3rd and 4th paragraphs in Subsection 106.01 Conformity with Contract Requirements.

Section 108. - PROSECUTION AND PROGRESS Delete Section 108 Prosecution and Progress in its entirety.

Section 109. - MEASUREMENT AND PAYMENT Delete Subsections 109.06 Pricing and Adjustments, 109.07 Estimated Work, 109.08 Progress Payments, and 109.09 Final Payment.

Section 109. - MEASUREMENT AND PAYMENT Delete Table 109-1 of Subsection 109.01 Measurement of Work and replace with the following:

Table 109-1 Decimal Accuracy of Quantities for Payment

Pay Item
Level of Precision
Acre
0.01
Cubic Foot
1
Cubic Yard
1
Cubic Yard Exception - Structure Excavation; Sheathing; Materials; Bedding, Bed Course, and Backfill, Materials; Gabions;
0.1
Cubic Yard Exception – Concrete; Masonry
0.01
Day
1
Each
1
Gallon
1
Hour
0.1
Linear Foot
1
Linear Foot Exception - Timber, Steel, and Concrete Piles
0.1
M-Gallon
0.1
Mile
0.01
Month
0.1
Pound
1
Square Foot
0.1
Square Yard
0.1
Station
0.1
Thousand Board Feet Measure
0.01
Ton
0.1
Ton Exception - Calcium Chloride; Sodium Chloride; Hydrated Lime; Bituminous Materials; Pavements; Bed Course Materials
0.01
Week
0.1

Section 109. - MEASUREMENT AND PAYMENT Delete Subsection 109.02(c) Measurement Terms and Definitions, Contract quantity and replace with:

(c) Contract quantity. The quantity to be paid is the quantity listed in the bid schedule. The contract quantity will be adjusted for authorized changes that affect the quantity or for errors made in computing this quantity when that error exceeds 15% or more. If there is evidence that a quantity specific as a contract quantity is incorrect by 15% or more, submit calculations, drawings, or other evidence indicating why the quantity is in error and request in writing that the quantity be adjusted.

Section 153. – CONTRACTOR QUALITY CONTROL Delete Subsection 153.02 Qualifications and replace with the following:

153.02 Qualifications. Submit the following for approval with the quality control plan:

(a) Quality control manager (QCM). Furnish a QCM who has experience in construction, inspection, quality control and material testing on construction projects of similar type and scope.

(b) Testers. Provide testers with at least 1 years' experience in the type of sampling and testing required, and with one of the following for the type of sampling and testing performed:

(1) National Institute for Certification in Engineering Technologies (NICET) Level II certification in construction materials testing for similar material types or equivalent state or industry certification;

(2) Certification by a state or regional certification program, such as Western Alliance for Quality Transportation Construction or Northeast Transportation Technician Certification Program; or

(3) At least 1 year of employment by an AASHTO accredited laboratory performing equivalent sampling and testing with competence according to AASHTO R 18.

Section 155. – SCHEDULES FOR CONSTRUCTION CONTRACTS Delete Section 155 Schedules for Construction Contracts in its entirety and replace with the following:

155.01 General. Provide a construction schedule showing all major activities start and end dates for completion the period of performance for the contract.

Section 156. – PUBLIC TRAFFIC Delete Subsections 156.02 Qualifications, 156.06 Limitations on Construction Operations, 156.08 Traffic Control Supervisor and replace with the following:

156.02 Qualifications. Provide a traffic control supervisor (TCS) with at least 1 year of experience supervising traffic control.

156.06 Limitations on Construction Operations. When the roadway is open to public traffic, perform the following:

(a) Limit construction-caused delays to public traffic to no more than 30 minutes per passage through the project.

(b) Operate equipment in the direction of traffic, where practical.

(c) Provide minimum lane widths of 10 feet where practicable. Use barricades, drums, or other approved devices to delineate traffic lanes through areas where the edge of pavement or intended path has been obliterated by construction operations. Notify and coordinate with the oversize load permitting authority for lane width limitations before reducing lane width or closing roadway shoulders.

(d) Locate staging areas outside the clear zone or behind approved traffic barriers. Obtain approval of the location and access to staging areas. Store unused traffic control devices at staging areas.

(e) Park equipment outside of the clear zone or behind approved traffic barriers.

(f) Provide parking areas for employee’s personal vehicles in approved areas.

(g) Provide uninterrupted two-way communications between flaggers and between flaggers and pilot cars unless flaggers can see each other and communicate. Citizen band radios are unacceptable. Make communication devices available to the CO as necessary or if requested.

(h) Maintain existing guardrails, barriers, and bridge railings until removal is necessary for construction. Use a temporary barrier or appropriate channelizing devices while the guardrails and bridge rails are absent. Install permanent barriers, guardrails, and bridge rails as soon as possible.

Add the following to the end of Subsection 156.06 Limitations on Construction Operations as a separate paragraph:

Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).

Table 156-1 Temporary Road Closures

Road Number
From Terminus
To Terminus
Maximum Consecutive Days of Closure
Minimum Consecutive Days Open
Remarks
211D
COC-211
MP 1.0
1
NA
Potential closure for pit blasting

156.08 Traffic Control Supervisor. Provide a TCS according to Subsection 156.02 during construction operations and as necessary to inspect the devices as defined below. Provide the TCS’s name and 24-hour telephone numbers at the preconstruction conference.

During the contract, including periods of suspensions and work stoppages, perform the following:

(a) Implement the temporary traffic control plan and monitor the effectiveness of the plan.

(b) Coordinate traffic control operations. Include those of subcontractors and suppliers.

(c) Ensure the condition, position, and applicability of traffic control devices in use.

(d) Immediately correct traffic control deficiencies.

(e) Coordinate and ensure that traffic control devices are provided, installed, maintained, removed, stored, replaced, relocated, and cleaned according to Section 635. Ensure unused traffic control devices are properly handled and stored.

(f) Inspect traffic control devices, including those in staging, storage, material source, and disposal areas, as follows:

(1) Daily, during daylight hours and during hours of darkness;

(2) (Monthly) during:

(a) Daylight hours and hours of darkness when work is suspended for periods of more than one week; and

(b) Periods of winter suspension.

(3) Additional inspections, day or night, as directed; and

(g) Before winter suspension, conduct an inspection of the project with the CO to ensure proper provisions are made for winter travel during the period of suspension.

(h) Provide temporary flagging assistance.

Section 157. – SOIL EROSION AND SEDIMENT CONTROL Add before first sentence in Subsection 157.04 General:

Thirty (30) days prior to the start of construction, submit a written plan according to subsection 104.04 with all necessary permits that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction.

Section 201. - CLEARING AND GRUBBING Delete paragraph (c) in Subsection 201.04(c) Clearing and replace with the following:

(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to maximum stump height shown in table below.

Fall and buck the merchantable material at lengths longer than the minimum lengths listed, or in multiples thereof (i.e. 8 ft, 16 ft, 24 ft, 32 ft), not to exceed 16 feet in length to allow for transportation of the material. Merchantable timber shall be decked at designated location(s).

Forest Products Utilization Standards:

Species
Product
Max. Stump Height
Minimum Specifications

Piece Required to be Removed

Length (feet) Diameter Inside Bark at Small End (inches)

1/

All
Saw
6
10
14
6.67
All
Non-saw
6
10
9
NA
All
POL
6
10
6
NA

1/ Enter Merchantability Factor (Merch. Factor) or Net Scale in % of Gross Scale, whichever is appropriate.

Section 201. - CLEARING AND GRUBBING Delete Subsection 201.06 Disposal and replace with the following:

201.06 Disposal. Merchantable timber is Government property. Dispose of clearing and grubbing debris according to Subsection 203.07.

Section 203. - REMOVAL OF STRUCTURES AND OBSTRUCTIONS Add the following to Subsection 203.07 Disposing of Material:

Dispose of unsuitable and excess material according to the specified method(s) as follows:

(a) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toe line of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees.

(b) Scattering. Scatter construction slash in designated areas without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations. When scattering for erosion control, place construction slash as flat as practicable on the completed slope.

(c) Chipping. Use an approved chipping machine to chip slash longer than 3 feet. Deposit chips on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.

(d) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.

(e) Decking. Remove brush from designated log deck areas. Limb and top logs.

Logs not meeting the Utilization Standards described in Subsection 201.04(c) shall be cut to lengths less than 10 feet and decked in designated log deck location.

Merchantable timber not associated with an existing timber sale shall be cut to length meeting the Utilization Standards described in Subsection 201.04(c).

Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.

(f) Removal to designated locations. Remove construction slash to designated locations.

(g) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps.

Section 205. - ROCK BLASTING Add the following to Subsection 205.03 Regulations:

(e) Forest Service. For projects in National Forest Service lands, comply with Forest Service Manual (FSM) 7190, Explosives and Blasting Materials.

Delete second sentence of Subsection 205.05 Blasting Plans and replace with the following:

Blasting plans may be required for boulder reduction blasts (mudcapping or blockholing) as determined by the CO.

Add the following to Subsection 205.05(a) Blasting Plans, General blasting plan:

Notify the owners of nearby utilities at least 24 hours before blasting.

Change the following in Subsection 205.05(b) Blasting Plans - Site-specific blasting plans and general plan revisions and updates.

“days” to “business days” Add the following to Subsection 205.05(b)(11) Blasting Plans, Site-specific blasting plans and general plan revisions and updates.

Optional as determined by the CO.

Add the following to Subsection 205.06(h) Preblast condition survey and vibration monitoring and control.

(h) Limit blasting induced vibrations in saturated soils or on steep slopes as designated or as directed by the CO.

Add the following to Subsection 205.07 Test Blasting:

Test blast at all new sources, when rock type changes, and when blast layout changes due to slope or other changes.

Delete the first sentence from Subsection 205.08 Blasting and replace with the following:

Use explosives and detonators within the manufacturer’s recommended shelf life.

Delete the seventh paragraph from Subsection 205.08 Blasting and replace with the following:

Mitigate uncontrolled gas pressure loss during blasting and excessive blast noise by using appropriate (as determined by CO) stemming materials and practices.

Add the following to Subsection 205.08(c) Blasting, Revising blasting plans:

(11) Precipitation exceeds 1 inch in any 24 hour period.

(12) Precipitation exceeds 3 inches in any 96 hour period.

(13) Precipitation exceeds 4 inches in any 144 hour period.

(14) A landslide occurs within 300 feet of a blast site under any precipitation conditions.

Delete all in Subsection 205.09 Reporting except (c) Close-out.

Section 314. - STOCKPILED AGGREGRATES Add the following to Subsection 314.01 Description:

Pit or quarry development work consists of clearing, grubbing, stripping topsoil, removing overburden, constructing access roads, conducting restoration activities, and performing other incidental work required for pit or quarry development. Includes processing and crushing material to produce specified aggregates.

Add the following to Subsection 314.04 Stockpile Site after the first sentence of second paragraph:

Submit a plan of operation according to Section 105.02. Perform the work in accordance with MSHA 30 CFR, part 56.

Delete the following paragraph of Subsection 314.05 Stockpile:

Protect stockpiles with an approved cover.

Section 703. - AGGREGATE Delete Subsection 703.09(e) Chip Seal Aggregate and Replace with the following:

(e) Los Angeles abrasion, AASHTO T 96 30 percent maximum.

Section 703. - R3-G FOREST SERVICE SURFACE AGGREGATE Delete 703.05 and replace with the following:

703.05 Surface Course Aggregate.

(a) General. Provide hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming to the following:

(1) GradationTable 703-1
(2) Los Angeles abrasion, AASHTO T 9635 % maximum

(3) Soundness of aggregate using sodium sulfate AASHTO T 104, 5 cycles

(a) Coarse aggregate12 % loss maximum
(b) Fine aggregate12 % loss maximum
(4) Durability index (coarse), AASHTO T 21035 minimum
(5) Durability index (fine), AASHTO T 21035 minimum
(6) Fractured faces, AASHTO T 335 (one or more)75 % minimum

(7) Without organic matter and lumps or balls of clay.

(8) Liquid limit, AASHTO R 58 and T 89, Method A 35 maximum

Table 703-1 Surface Course Gradation R3-G and Plasticity Index Limits

Sieve Size
Percent by Mass Passing

Designated Sieve (1)

(AASHTO T 27 & T 11)

1 inch
100
3/4 inch
97 - 100
3/8 inch
66 - 87
No. 4
43 - 66
No. 16
23 - 44
No. 40
14 - 31
No. 200
7 - 19
Plasticity index (PI)*
4 - 10

*Imported bentonite can be added to meet the specification. If less than 4 PI then add 2% bentonite by weight.

(1) Statistical procedures do not apply.