Attachment 1 - Statement of Work.pdf

PDF 415 KB Posted

Attached to
Bushy Knoll Pit Crush & Stockpile
Solicitation number
127EAX27Q0017
Issued by

About this file

Statement of Work Summary

This is a Statement of Work (SOW) for the Bushy Knoll Crush and Stockpile project issued by the U.S. Department of Agriculture Forest Service for the Coconino National Forest in the Southwestern Region. The project encompasses material extraction, aggregate production, and stockpiling operations at a virgin pit site located on the Mogollon Rim Ranger District. Work activities include mobilization, surveying, clearing and grubbing, drilling, material extraction via blasting or excavation, sampling and testing, stockpile surveying for quality control, crushing and stockpiling of aggregate material, and creation of an access road. The contractor must obtain all required permits from the Arizona Department of Environmental Quality (ADEQ) for operational methods and furnish all labor, materials, equipment, tools, transportation, and supplies necessary for completion.

The period of performance extends from June 1, 2026, through September 30, 2027, with a contract duration of 180 calendar days. Technical requirements reference the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24), specifically Divisions 100, 150, 200, 300, and 700, as incorporated by reference. Forest Service Supplemental Specifications (FSSS) contained in Attachment A amend the FP-24 standards across 18 specification sections covering bid and award, scope of work, work control, material control, acceptance, prosecution and progress, measurement and payment, quality control, construction schedules, public traffic, erosion control, clearing and grubbing, structure removal, rock blasting, stockpiled aggregates, and aggregate specifications. Contractors must submit nine deliverables including plans of operations, traffic control, blasting, soil erosion control, work schedules, hazardous spill procedures, quality control protocols, equipment mobilization notification, and aggregate gradation documentation according to specified timelines ranging from 14 days prior to prework meetings to during aggregate production.

View the file

Other files

File Type Posted
Attachment 2 - Specifications.docx DOCX document
Attachment 5 - Site Plan.pdf PDF
Attachment 6 - Wage Determination.pdf PDF
Attachment 4 - Fire Plan.pdf PDF
127EAX27Q0017 Bushy Knoll Pit Crush and Stockpile.pdf PDF
Attachment 3 - Schedule of Items.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION C - STATEMENT OF WORK

SOUTHWESTERN REGION

COCONINO NATIONAL FOREST

BUSHY KNOLL CRUSH AND STOCKPILE

U.S. Department of Agriculture (USDA)

3/16/26 i

Contents

PROJECT SCOPE

PROJECT LOCATION

PERIOD OF PERFORMANCE

TECHNICAL REQUIREMENTS

FP Standard Specifications

Forest Service Supplemental Specifications

GOVERNMENT FURNISHED

SUBMITTALS/DELIVERABLES

ATTACHMENTS

PROJECT NAME

Bushy Knoll Crush and Stockpile

PROJECT SCOPE

Bushy Knoll Crush and Stockpile Project: This project will include mobilization, surveying, clearing and grubbing, drilling, material extraction through blasting or excavation, sampling and testing, stockpile surveying for quality control and crushing and stockpiling of aggregate material in accordance with the plans and specifications. It will also include the creation of an access road to gain access to the proposed work area. The Contractor shall be responsible to obtain all permits as required by Arizona Department of Environmental Quality (ADEQ) for the Contractor’s methods of operation(s).

The Contractor shall furnish labor, material, equipment, tools, transportation, and supplies necessary to complete the work according to the contract.

PROJECT LOCATION

Bushy Knoll is a virgin pit located on the Mogollon Rim Ranger District. This pit consists of an existing hill with a low flat area at the northwest aspect of the hill. The contractor will remove the overburden, create a staging area, and utilize existing materials for barriers for the safety of the operation within the designated NEPA boundary. See travel directions and contract map in the plan set.

PERIOD OF PERFORMANCE

The period of performance for this project is 6/1/26-09/30/27. Contract time is 180 days.

TECHNICAL REQUIREMENTS

The requirements contained in the following specifications are hereby made a part of this solicitation and any resultant contract. No changes to the specifications, terms, or conditions of this statement of work shall be made without the prior written approval of the Contracting Officer.

FP Standard Specifications The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24) U.S. Customary Units), are included by reference, applicable to this project, and are hereby made a part of this solicitation and any resultant contract. The 902-page book entitled “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-24 U.S. Customary Units), is available from: https://highways.dot.gov/federal-lands/specs

The following Standard Specifications (FP-24) and those referenced contain the technical requirements of this project:

Division 100 - GENERAL REQUIREMNETS Division 150 - PROJECT REQUIREMENTS Division 200 - EARTHWORK Division 300 - AGGREGATE AND BASE COURSES Division 700 - MATERIAL

Forest Service Supplemental Specifications Forest Service Supplemental Specifications (FSSS) are made part of this solicitation and any resultant contract. FSSS modify the FP-24. They may add to, delete from, or modify the FP-24 standard specifications.

https://highways.dot.gov/federal-lands/specs

The following Forest Service Supplemental Specifications (FSSS), contained in Attachment A, amend Standard Specifications contained in FP-24:

Section 102. - BID, AWARD, AND EXECUTION OF CONTRACT Section 103. - SCOPE OF WORK Section 104. - CONTROL OF WORK Section 105. - CONTROL OF MATERIAL Section 106. - ACCEPTANCE OF WORK Section 108. - PROSECUTION AND PROGRESS Section 109. - MEASUREMENT AND PAYMENT Section 153. - CONTRACTOR QUALITY CONTROL Section 155. - SCHEDULES FOR CONSTRUCTION CONTRACTS Section 156. - PUBLIC TRAFFIC Section 157. - SOIL EROSION AND SEDIMENT CONTROL Section 201. - CLEARING AND GRUBBING Section 203. – REMOVAL OF STRUCTURES AND OBSTRUCTIONS Section 205. - ROCK BLASTING Section 314. - STOCKPILED AGGREGRATES Section 703. - AGGREGATE Section 703. - R3-G FOREST SERVICE SURFACE AGGREGATE

GOVERNMENT FURNISHED

N/A

SUBMITTALS/DELIVERABLES

Contractor shall submit the following items for review or as deliverable(s). This list is not all inclusive. Submittals requiring Forest Service approval shall be submitted according to timelines specified to allow adequate review time.

Item No. Description Timeline

1 Plan of Operations 14 days prior to prework meeting.

2 Traffic Control Plan 14 days prior to prework meeting.

Blasting Plan

14 days prior to drilling and blasting operations.

4 Soil Erosion Control Plan 14 days prior to prework meeting.

5 Work Schedule At prework meeting.

6 Hazardous Spill Plan Before beginning any work.

7 Contractor Quality Control Plan Before beginning any work.

Equipment Mobilization Notification

14 days prior to moving equipment onto National Forest administered land.

Aggregate Gradation

During aggregate production. Gradation R3-G (FSSS Table 703-1).

ATTACHMENTS

Attachment A - Schedule of Items Attachment B - Construction Drawings Attachment C - Forest Service Supplemental Specifications Attachment D - Maps Attachment E - Forest Fire Plan and Guidelines

File details come from the government source that posted it. Updated .