127EAX26R0001 QA4.docx
DOCX document 16 KB Posted
- Attached to
- FSR 535/536 Recondition & Resurfacing - Coconino NF Federal contract opportunity
- Solicitation number
- 127EAX26R0001
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a Questions and Answers (Q&A) file for Solicitation Number 127EAX26R0001, focusing on road reconditioning work in the Coconino National Forest near Flagstaff, Arizona. The Q&A addresses three specific inquiries from potential contractors about the project, providing detailed references to specific plan sheets for aggregate thickness, road width, and work area limits. Contractors are directed to reference sheets G-03, C-01, C-05, and C-06 for precise details on road dimensions, mileposts, and project specifications.
The related federal contract opportunity involves reconditioning and resurfacing approximately 4.00 miles on Forest Service Roads (FSR) 535 and 536, which includes removing and replacing 6 culverts. The project is under the Department of Agriculture Forest Service and will involve work on aggregate surfaced roads running east to west, connecting with AZ-89A, FSR 231, and FSR 538. The exact milepost limits can be staked in the field by the Contracting Officer's Representative (COR) prior to the start of work.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 127EAX26R0001 QA3.docx | DOCX document | |
| 127EAX26R0001 QA2.docx | DOCX document | |
| 127EAX26R0001 QA1.docx | DOCX document | |
| 127EAX26R0001.pdf | ||
| Timber Sales Roads Prep for 535 536 SOI.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
127EAX26R0001 Coconino NF FSR 535/536 Road Reconditioning Q&A #4
1. Aggregate Thickness: Is there an intended or typical resurfacing thickness for this project, or should contractors assume a standard depth per Forest Service specifications?
A: Yes. Reference sheets C-05 (p. 50 of 66, 127EAX26R0001.pdf) and C-06 (p. 51 of 66, 127EAX26R0001.pdf) of the plans or the SOI included in the solicitation for the specific depths.
2. Is there an anticipated or typical road width that contractors may use for estimating purposes?
A: Yes. Reference sheets C-01 (p. 46 of 66, 127EAX26R0001.pdf), C-05 (p. 50 of 66, 127EAX26R0001.pdf), or C-06 (p. 51 of 66, 127EAX26R0001.pdf) of the plans for typical road dimensions.
3. Are there defined start and end points, stationing, mileposts, or an official map identifying the exact limits of work for FSR 535 and FSR 536?
A: Yes. Reference sheet G-03 (p. 44 of 66, 127EAX26R0001.pdf) in the plans for approximate mileposts of all work. Exact milepost can be staked in the field by the COR prior to the start of work.