127EAX26Q0015 Black Mesa Quarter Updating Apache-Sitgreaves NF QA4.docx

DOCX document 18 KB Posted

Attached to
Black Mesa Ranger District Quarters Update - Apache-Sitgreaves NF
Solicitation number
127EAX26Q0015
Issued by

About this file

This is a Questions and Answers (Q&A) document for federal contract solicitation 127EAX26Q0015, which addresses clarifications regarding remodeling scope for three residential structures at the Black Mesa Ranger District, Apache-Sitgreaves National Forest in Overgaard, Arizona. The Q&A addresses specific renovation requirements for two mobile home units (11-33 and 11-60) and one Ranger House (11-38).

For mobile homes 11-33 and 11-60, clarifications confirm that only mismatched carpet rooms are replaced (not common areas), seven door slabs are replaced per unit, interior bedroom doors receive keypad entry locks (with lockable keypad door handles acceptable), and identical specifications apply to both units. For the Ranger House 11-38, no door slabs are replaced, no keypad locks are required, blinds replacement is excluded from scope, the bathtub is replaced with a tile shower surround, kitchen appliances are furnished and installed by the government, and interior wall painting is limited to only the areas being remodeled. The solicitation requires all supervision, materials, equipment, labor, and transportation for the remodeling work. A mandatory site visit was scheduled for April 2, 2026 at 10:00 AM Mountain Standard Time. Questions required submission by April 10, 2026 at 1:00 PM Pacific Time to the Contracting Officer, Blaine Greenwalt, at blaine.greenwalt@usda.gov, with proposals due according to the date specified in Block 13 of the solicitation document.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

127EAX26Q0015 - Black Mesa Quarters Updating – Apache-Sitgreaves NF Q&A #4 11-33 (mobile home)

1. Does the Living Room/common area carpet get removed and replaced with new?

A: No only mismatched rooms

1. How many door slabs get replaced in this unit.

A:7

1. Which doors are to receive a keypad entry lock?

A: Interior doors for bedrooms

1. Do the doors requiring keypad entry lock need to have a lockable handle with keypad dead bolt above or will a lockable keypad doorhandle be acceptable.

A: Lockable keypad door handles are acceptable 11-60 (mobile home)

1. Does the Living Room/common area carpet get removed and replaced with new?

A: Same as 11-33

1. How many door slabs get replaced in this unit.

A: Same as 11-33

1. Which doors are to receive a keypad entry lock?

1. A: Same as 11-33

1. Do the doors requiring keypad entry lock need to have a lockable handle with keypad dead bolt above or will a lockable keypad-door handle be acceptable.

A: Same as 11-33 11-38 (Ranger House) RFI’s

1. Is removing the old blinds and installing new faux wood, cordless blinds part of 11-38’s scope? If Yes, which CLIN on the bid schedule should we build the price into? B6.1/Kitchen Remodel?

A: No

1. Will the bathtub get removed and replaced with walk-in shower, or remove and replace tub?

A: Tile shower surrouond

1. Are the appliances in the kitchen going to be furnished and installed by the government?

A: Yes

1. Are there seven interior door slabs to replace in 11-38?

A: No

1. How many door slabs get replaced in this unit.

A: None

1. Which doors are to receive a keypad entry lock?

A: None

1. Do the doors requiring keypad entry lock need to have a lockable handle with keypad dead bolt above or will a lockable keypad doorhandle be acceptable.

A: N/A

1. Do all the interior walls require painting or just the rooms being remodeled?

A: Just areas being remodeled