Section 00151 - Mobilization.docx
DOCX document 15 KB Posted
- Solicitation number
- 127EAX24R0005
- Issued by
-
Department of Agriculture Forest Service
About this file
This document contains a pre-solicitation notice and project specifications for a federal construction contract opportunity. The United States Forest Service is seeking proposals from small businesses for improvements to the Echo Amphitheater Recreation Site located in Canjilon, New Mexico. Phase II of the project will include extending the water distribution line to provide new fill stations and hydrants, installing underground electric lines with associated site work, improving campground drainage and surfaces, adding retaining walls and fencing, replacing an informational kiosk, and installing campsite units. Interested firms must be small businesses registered in SAM.gov. A formal RFP will be posted on January 31, 2024 containing specifications, drawings and submission requirements. The estimated cost for the total project is between $500,000 and $1,000,000.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Section 16400 - Underground Cable.doc | DOC document | |
| Section 02510 - Water Distribution.doc | DOC document | |
| Section 02101 - Road and Campsite Resurfacing.doc | DOC document | |
| Section 02104 - General Recreation Site.doc | DOC document | |
| ECHO Drawings.pdf | ||
| Section 02316 - Excavation Trenching and Backfilling for Utility Systems.doc | DOC document | |
| Section 02100 - Timber Retaining Walls and Gravel Pad.doc | DOC document | |
| 127EAX24R0005.pdf | ||
| Wage determination.pdf | ||
| Section 02103 - Split Rail Fence.doc | DOC document | |
| Section 02102 - Clearing and Grubbing.doc | DOC document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section 00151. — MOBILIZATION
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing work necessary before beginning work at the project site. This work also includes obtaining permits, insurance, and bonds.
Payment
151.02 The accepted quantities will be paid at the contract price per unit of measurement for the Section 151 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section.
Progress payments for mobilization by the lump sum will be paid as follows:
(a) Bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from pay items (not including mobilization), 50 percent of the mobilization pay item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from pay items (not including mobilization), 100 percent of the mobilization pay item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization pay item in excess of 10 percent of the original contract amount will be paid after final acceptance.