This statement of work outlines improvements to be made to three road segments and two parking lots located near Carr and Brown Canyons on the east side of the Huachuca Mountains in the Sierra Vista Ranger District. Work includes hauling and compacting 4 inches of coarse aggregate surface material on the roads and parking lots, establishing 14-foot-wide road prisms with v-ditches and 2-3% out-sloped drainage. The main bid item covers 0.75 miles of road and 24,500 square feet of parking at Brown Canyon. Additive bid items include surfacing 2.1 miles of Carr Canyon Road, 0.25 miles of additional Carr Canyon Road, and 8,500 square feet of Parking Lot 2. The total contract performance time is 60 days from notice to proceed. The contractor must submit and receive approval of a temporary traffic control plan complying with MUTCD standards. Carr Canyon Road will be closed on weekdays with flagging for occasional resident use, and open weekends. Brown Canyon Road will be closed on weekdays except for contractor vehicles. The related federal contract opportunity is solicitation 127EAX23Q0075 from the USDA Forest Service for the Brown & Carr Canyon Road improvements on the Coronado National Forest.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IMPROVE SIERRA VISTA RECREATION ACCESS, ROADS AND TRAILS
RESURFACE BROWN AND CARR CANYON ROADS
Sierra Vista Ranger District Statement of Work January 10th, 2023
Work consists of improving three separate existing road segments totaling 3.2 miles and two parking lots totaling 0.85 acres. The project area is located near Carr and Brown Canyons on the eastside of the Huachuca Mountains. Features to be improved are designated Parking Lot 1, Parking Lot 2, Brown Canyon Road, Carr Canyon Road, and Carr Canyon Road Additional (See Location Map). The road segments and parking lots are comprised of native surface material with minimal drainage features. The improvement work is meant to increase the drivability and durability roads and parking lots.
Improvement work includes:
1) Hauling, spreading, and compacting 4 inches of surface coarse aggregate (grade G), conforming to Forest Service standards, on road segments and parking lots.
2) Establishing 14-foot-wide, 4% crowned road prisms with 1.5-foot-deep, 2:1 v-ditches on road segments (See Location Map)
3) Establishing 2-3% out-sloped drainage on parking lots.
Main bid item:
1) Parking Lot 1 And Brown Canyon Road Surfacing. 0.75 miles of road and 24,500 square feet of parking area Additive bid items:
1) Carr Canyon Road Surfacing. 2.1 miles of road
2) Carr Canyon Additional Road Surfacing. 0.25 miles of road
3) Parking Lot 2 Surfacing. 8,500 square feet of parking area Total contact time from Notice to Proceed to completion shall be no more than 60 days.
Prior to mobilization, the contractor shall submit and receive approval on a Temporary Traffic Control Plan. Such a plan must comply with the most current version of the Manual on Uniform Traffic Control Devices (MUTCD). Contact the COR for such approval.
Temporary traffic control for Carr Canyon Road will close the road to all use during weekdays except for the occasional use of the road by an elderly resident (or family/visitors) who lives up Carr Canyon. During daylight hours a flagman must be provided at the road closure point (the existing swing gate at the end of pavement) to operate the gate for this resident (or family/visitors) as well as to accommodate contractor’s delivery vehicles while excluding the public. Occasional use by Border Patrol should be expected as well. The segment of road involved in the contract shall be fully open and made drivable by a standard passenger car for the duration of each weekend (Friday at sunset to Monday at 5 am) during construction.
Temporary traffic control for Brown Canyon Ranch Road will close the road to all use during weekdays only, except to accommodate contractor’s delivery vehicles while excluding the public. The road shall be fully open and made drivable by a standard passenger car for the duration of each weekend (Friday at sunset to Monday at 5 am) during construction.
The contractor is responsible for providing all equipment, supplies, labor, and incidentals to perform the work described in this contract. Any sources of materials described herein are shown as “or approved equal”. No water or other utilities exist at the area. The work at each road location will be staked on the ground and available for viewing during a pre-bid showing. All work in this project shall be included in the pay items shown. All work must comply with the Standard Specifications For Construction of Roads and Bridges on Federal Highway Projects (FP-14) and Forest Service Supplemental Specifications (FSSS).