A00002 - RFI Responses.pdf

PDF 210 KB Posted

Attached to
127EAW26Q0041 - Cone Peak Road Repairs
Solicitation number
127EAW26Q0041
Issued by

About this file

This is a Standard Form 30 Amendment of Solicitation/Modification of Contract for the USDA Forest Service Cone Peak Road Repairs project (Solicitation 127EAW26Q0041). The amendment, issued on August 13, 2026, by the Procurement Operations Construction and A-E Division West, incorporates RFI responses and updated project plans (dated March 2026) into the solicitation. All interested vendors must acknowledge receipt of this amendment prior to the deadline specified in the original solicitation or face potential rejection of their offer.

The RFI Log contains 44 questions and government responses addressing critical project requirements for the road repair work at seven sites. Key responses clarify that contractors must hire third-party geotechnical firms for compaction testing and soil sampling; water is available from Pacific Valley Fire Station (2,000 gallons/day maximum, with Forest Service demand taking precedence); work is limited to daylight hours with weekend work allowed only with written CO approval; staging is permitted at the service road entrance and Nacimiento station site; the contractor is responsible for developing and implementing a Stormwater Pollution Prevention Plan (SWPPP) and erosion control measures; clear and grub operations are required at all seven sites with 3.0 miles of brushing along the road; blasting is not permitted; native soil analysis must be performed by the contractor to determine suitability; the performance period is 180 days including options; and all work must follow the revised March 2026 project plans and specifications. Contractors are instructed that failure to use the revised documents will result in non-responsive proposals.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A00002

GREGORY L. CUNNINGHAM

The purpose of this amendment is to post RFI responses, and updated drawings.

Attached is "127EAW26Q0041 - RFI Log" and "4. Cone Peak Road Project Plans - Updated March 2026" which are hereby incorporated into any subsequent contract award. Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.

USDA FOREST SERVICE

PROCUREMENT OPERATIONS

CONSTRUCTION AND A-E, DIVISION WEST

ALL INTERESTED VENDORS 127EAW26Q0041

1 4

08/13/2026

07/15/2026

Updated 8/13/2026 8:01

RFI # RFI Question Government RFI Response Notes 1 What is the percent of bid price required for the Bid Guarantee? bid bond percentage is 20% of the quote amount.

2 Is there an engineers estimate for this project? The engineers estimate is not releasable and “FAR 36.204 Disclosure of the magnitude of construction projects” is no longer applicable under the FAR Overhaul (https://www.acquisition.gov/far-overhaul).

3 In reference to Quote Evaluation & Basis for Award Item IV, Contractors

License, please advise if offerors can hold and submit an active and valid

California Class A or B contractor’s license.

Solicitation requirement for a California Class A General Engineering

Contractor contractor’s license will not be revised to include Class B.

4 Who is responsible for compaction testing Contractor to hire third party geotech

5 Who is responsible for sampling Contractor to hire third party geotech testing company.

6 Who will be responsible for staking. Construction staking by Contractor. Staking to be approved by COR on site.

7 Where is the closest water source and what limitations/quantities are there for daily use

Yes - Pacific Valley Fire Station (US Forest Service facility) has a well and water available. Pacific Valley fire station is location along

Highway 1, 4 miles south of the intersection of CA Hwy 1 and

Nacimiento Fergusson Road, and 13+ miles from the project site.

Contractor water draw shall not exceed 2,000 gallons per day or

10,000 gallons per week. Forest Service water demand shall take precendence (example - fire suppression needs or if the well production is unable to meet the demands of both the Forest

Service admin site and the project). If Forest Service water is not sufficient (2,000 gallons/day), theclosest known water source is Fort

Hunter Liggett. Contractor to confirm the availability of water source and secure agreements. Drafting is not allowed on Forest

Service property

8 What are the hours of work allowed Work allowed during daylight hours

9 Will weekend work be allowed Yes, with prior written CO approval

10 Can the contractor stage equipment and materials at the service road entrance

Short term storage of equipment and material allowed at service road entrance. Storage and staging also allowed at Nacimiento station site on asphalt surfaces only. Nacimiento station located

400 yards to the east along Nacimiento Ferguson Road. Additional staging areas may be identified after award.

11 Will the dept be providing the inspectors and biologist if needed Government will provide Heritage and Biological monitoring, if needed.

12 Are there any protected species that will cause a stop work if sighted. Yes, it's possible, however based on surveys of the area, it's unlilely that endangered species will be encountered. Areas of avoidance will be flagged prior to work start if needed, for avoidance purposes.

13 What is the length of the stop work if a species is spotted To be determined based on situation that arises.

14 Will clear and grub be limited to as needed to acess the road and gain acess. Clear and grub required at all seven sites. 3.0 miles of brushing also required along length of road to access sites.

15 Can clear and grub vegetation be disposed of where cut or will it need to be hauled off

Material to be hauled off and disposed of off Forest.

16 If it is neccesary to excavate the uphill side of the road to gain acess are there any special requirements to be taken

Current site conditions need no excavation for access.

17 Will crews be provided additional work days beyond the 180 days if the alternative bid items are awarded

Period of performance is 180 days, including options. The contractor may propose an extension, if needed for CO review but not guarenteed.

18 What are the quantities of loose debri/dirt/rock at each site that will need to be removed prior to backfilling

To be estimated and determined by the contractor.

19 Project specifications refrence blasting of rock, is this expected at this site , if so who is responsible.

Blasting will not be needed/allowed for this project.

20 Project plans and spec refrence backfill of native soils,has a soil analysis been performed and is there a geo technical report

Soil analyis has not been performed by the Forest Service. Soil analysis will need to be completed by the contractor to confirm if native soils are suitable.

21 Is use of native soil/stockpile or excavation is approved, how far is the material source

Soil analyis has not been performed by the Forest Service. Soil analysis will need to be completed by the contractor to confirm if native soils are suitable. Borrow pit not an option for this project.

Commercial sources required for any imported material.

22 What is the compaction percentage required Per drawings and specs

23 If the contractor elects to use a new service road not yet exsisting to acess the middle sites if elected, will there be additional cost paid for reimbursment to the GC

Due to the steep nature of this area, there is no possibly for a new service road.

24 Should the contractor include costing for a SWPPS plan or will the department be providing one

SWPPP and associated SWPPP compliance, erosion control measures, thoughout the duration of the contract, will be the responsibility of the contractor. Long term erosion control measures(straw waddles, etc.) will become property of the

Government, at the completeion of the project.

"Erosion Control" line item included in the schedule of items. All

SWPPP and erosion control work to be captured in this line item.

PROJECT 127EAW26Q0041 - Cone Peak Road Repairs RFI responses will be responded to as necessary in amendment format which will be posted to the solicitation via https://sam.gov/

Telephone requests for information will not be accepted or returned. Information provided at the site visit shall not alter the terms and conditions of the solicitation and terms of the solicitation and specifications remain unchanged unless the solicitation is amended in writing. Offerors are required to submit all questions in writing to the Contracting Officer following the site visit.

25 Please confirm if the Site #1-7 CAD files can be provided to the design team upon award.

Yes Note: This RFI question is from the prior solicitation.

26 Has there been any past geotechnical exploration or geologic mapping conducted at each of the site locations? If so, can you provide this information upon award?

A comprehensive geotechnical analysis was not performed at these sites. These sites failed due to erosion from significant concentrated flows. It is assumed that global stability is not an issue at these sites. The stability of the reinforced fill is the requirement of the contractor, but must meet the minimum dimensions shown on the drawings. The contractor is not required to provide a global stability analysis, but they are required to ensure that the base (bottom elevation) of the rienfoced fill is adaquate to ensure that the fill and reinforcement cannot be undermined due to erosion a tthe base of the wall.

Note: This RFI question is from the prior solicitation.

27 Has a slope stability analyses been performed for the proposed sites, specifically based on subsurface cross section profiles? Or are contractors expected to include in their design?

A comprehensive geotechnical analysis was not performed at these sites. These sites failed due to erosion from significant concentrated flows. It is assumed that global stability is not an issue at these sites related to deeper seated landslide activity. The stability of the reinforced fill is the requirement of the contractor, but must meet the minimum dimensions shown on the drawings. The contractor is not required to provide a global stability analysis related to deeper seated instability (see item 2 above).

Note: This RFI question is from the prior solicitation.

28 Please confirm if the culvert sizing is based on a hydrologic analysis of the upstream tributary area. If so, can you provide any sizing calculations upon award?

Culvert sizing was completed on the main channel only (site 1).

Streamstats was used for the hydrologic results. The sizing of the culvert was based on FHWA nomagraphs, assuming inlet control.

Those data can be provided.

Note: This RFI question is from the prior solicitation.

29 What is the largest vehicle anticipated on this roadway? Forest Service Fire Engine Note: This RFI question is from the prior solicitation.

30 Please confirm the source of the existing contour information on the plans and when this data was collected.

Source was Lidar from 2017_ Significant changes have occurred, but was the best dat aavailable at the time. Some attempt was made to incorporate known changes, but government recognizes that there are likely inaccuracies.

Note: This RFI question is from the prior solicitation.

31 Section 6 on page 7 of the Statement of work mentions "a water pollution prevention plan will be developed by the Forest Service or its contractors.."

Page 8 item 21 has similar mention of a Water Pollution Control Plan developed by the contractor. Please confirm the offeror shall include preparation of a Stormwater Pollution Prevention Plan (SWPPP) and any required construction monitoring as a line item in the bid (should the project's soil disturbance exceed 1 acre). Also, please confirm a SWPPP will address the items requested in Sections 6 and 21. Finally, will the government still require these items if the project disutrbs less than 1 acre and therefore does not require a SWPPP?

SWPPP and associated SWPPP compliance, erosion control measures, thoughout the duration of the contract, will be the responsibility of the contractor. Long term erosion control measures(straw waddles, etc.) will become property of the

Government, at the completeion of the project.

"Erosion Control" line item included in the schedule of items. All

SWPPP and erosion control work to be captured in this line item.

32 Page 7 of the Statement of Work mentions "Road maintenance activities will occur during the normal operating season from April 15 to October 15 unless otherwise approved by the CO or CO's Representative." However, Section 4.0 on PDF page 4 notes a performance duration that starts around

9/1/2026 and extends 180 days into the winter months. Please confirm that the project's anticipated start date and period of performance will be per

Section 4.0 of the Statement of Work.

It's possible that work may proceed outside the normal operating period (April 15 to October 15), but will require Forest Service surveys and District Ranger approval.

33 Referencing section 29, based on the existing property boundary, are there any state or county easements or right of way lines that could impact the project? Does the government anticipate the need for any State or County permits for the work associated with this project?

No state or county permits anticipated.

34 Can the design team provide a substantiated analysis justifying that a fewer number of culverts or outfalls are acceptable at particular sites?

No, quptes are to be per plans and solciitation documents.

35 Are RFI responses from the prior solicitation still considered valid and apart of the solicitation documents?

Prior RFI responses are valid.

36 Through the RFI process, the prior solicitation issued revised plans (from

March 2026) with some printing errors, label errors, and quantity inconsistencies corrected. However, these revised plans were not issued apart of the latest solicitation. Only the December 2025 plans were provided. Please clarify if the revised plans from March of 2026 will govern for bidding purposes.

The March plan revisions will govern and supercede previous plans.

37 Can onsite materials be reused if deemed suitable by the project geotechnical engineer?

Yes, if the contractor's geotech can confirm onsite materials meet project specifications.

38 Is there a water source for this project? Closest known water source is Fort Hunter Liggett. Contractor to confirm the availability of water source and secure agreements.

Forest Service water source (well or drafting) not available.

39 Is the use of onsite borrow material acceptable for use in lieu of import material?

Yes, if the contractor's geotech can confirm onsite materials meets project specifications.

40 How will excavation and fill qunaties of native be billed as it is unlikely the topo and RFI response from the first round is accurate? If a site is marked as

600 cy ecavation in RFI round one #17 and the actual quantity is closer to

1000 cy?

If there are discrepancies between bid quantities and actual quanties, we would explore the possibility of a change order, and process to verify quantity discrepancy.

41 Since there is no SWPPS plan or BMP qunatities, how can we price the erosion control so that all bidders are using the same quantities of silt fence and fiber rolls?

SWPPP and associated SWPPP compliance, erosion control measures, thoughout the duration of the contract, will be the responsibility of the contractor. Long term erosion control measures(straw waddles, etc.) will become property of the

Government, at the completeion of the project.

"Erosion Control" line item included in the schedule of items. All

SWPPP and erosion control work to be captured in this line item.

42 Does the department require a new tech narrative since the site work may be limited to 1,2, & 6 and the approach would be different?

Technical approach narrative to match the current breakdown of base bid and bid option items.

43 If road repairs are necessary to gain acess to site 6 (perfoming main bid only option) will the department be adding a pay item or would they prefer the costing combined in an exsisting pay item?

Road was graded/maintained four weeks ago, and was sufficient for all contractors that attended pre-bid site visit. No road repairs anticipated.

44 There does not appear to be a geocompisite under drain system in site 1 drawings.Please provide detail

Detail not included in Forest Service Geotech design