This document is an Amendment (A00001) to Solicitation 127EAW25R0017 for the Upper Silver Creek Trail Bridge Replacement project in Stanislaus National Forest, California. The amendment extends the proposal due date to May 9, 2025, at 11:00 AM PST and provides responses to seven Request for Information (RFI) queries from potential contractors regarding site access, vegetation removal, and project constraints.
Key RFI responses include: contractors may submit proposals for minor earth and vegetation work (with Forest Service review), trees under 10 inches in diameter can be removed with prior approval, fallen trees can be relocated, and driving over bushes is permissible with minimal disturbance. The Forest Service acknowledges site inspection challenges due to snow but confirms the site remains accessible by foot. The project is a small business set-aside with an estimated value between $100,000 and $250,000, and the Notice to Proceed (NTP) will be issued within 10 days following award.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED 16C. DATE SIGNED
PAGE OF PAGES
CODE
(X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
A00001
6. ISSUED BY
USDA FOREST SERVICE
PPS FPO SW ZONE CSA-6
TANYA TORRES
CONTRACT SPECIALISTALIST
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)
ALL OFFERORS
9A. AMENDMENT OF SOLICITATION NUMBER
127EAW25R0017
1 2
04/17/2025
9B. DATED (SEE ITEM 11)
03/27/2025
1144600
7EAWAW
X 1
X
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PROJECT: Upper Silver Creek Trail Bridge Replacement Stanislaus National Forest, CA.
A00001
The purpose of this solicitation is to provide Request For Information (RFI) Responses and to extend the solicitation due date. The new extended proposal due date is 05/09/2025 at 11:00 AM PST.
See page 2 for additional information.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
JEREMY B. BEDNER
AMENDMENT OF SOLICITAITON/MODIFICATION OF CONTRACT PAGE NO. 2 OF 2
CONTINUATION PAGE
CONTRACT NO:
127EAW25R0017
ORDER NO: MODIFICATION NO:
A00001
14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED)
A. Below are the Request For Information (RFI) responses which are hereby incorporated into any subsequent contract award.
Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.
1. We have many questions about how flexible USFS will be on disturbance, plantings, and access down the walkway path?Can earthwork be performed to make an unimproved road for crane access? ?
Answer: A proposal for minor earth and vegetation work may be submitted by the contractor for review by the Forest Service to evaluate potential resource concerns. No additional compensation will be provided for the development of access routes, and all disturbances must be restored to their original condition upon completion of the work.
2. Can standing trees be removed?
Answer: Trees with a diameter at breast height (DBH) of less than 10 inches may be removed with prior approval from the Forest Service. For the removal of larger trees, the contractor may submit a proposal, which will be reviewed by the Forest Service to assess any potential resource concerns. It should be noted that no additional payment will be made for the removal of trees.
3. Can down trees be moved to allow access?
Answer: Yes, fallen trees may be relocated to facilitate access.
4. Can bushes and shrubs be driven over?
Answer: While it is permissible to drive over bushes and shrubs, the Contractor is expected to minimize any disturbance to the vegetation to the greatest extent possible.
5. Due to the time of year and bid closing date, the site is not able to be thoroughly inspected for access. Also, we cannot visit the site due to snow. Can the proposal due date be pushed back?
Answer: The Forest Service recognizes the significance of site inspections for the preparation of your solicitation. Please be advised that the site remains accessible by foot, enabling you to perform the necessary evaluations. Be aware that snow levels at the site may fluctuate. Consequently, we are extending the contract due date to Friday, May 9, 2025 - 11:00 am PST.
It is imperative to adhere to the expected project timeline to ensure completion within this field season. Accordingly, the Notice to Proceed (NTP) will be issued within 10 days following the award.
6. The pictures provided do not provide enough detail on the topography and elevation changes behind the ecology blocks in camp site 16.
Answer: At this time, no additional pictures are available.
7. What is the thickness of the existing asphalt path and what is the subbase?
Answer: The existing thickness of the asphalt path and the subbase has not been determined.
///////////////////////////////////////////////LAST ITEM//////////////////////////////////////////////////
B. All other terms and conditions remain unchanged.
| A00001 - 127EAW24R0017 - Crestline Group CG Renovation |
| Amendment - A00001 - 127EAW23R0011 - Sky Ranch Road |
SF 30 Continuation Page
File details come from the government source that posted it. Updated .