This is Amendment A00002 to solicitation 127EAW25R0003 for Phase I Road maintenance on Buckhorn Road at Los Padres National Forest, CA. The amendment provides responses to seven Request for Information (RFI) questions submitted by potential offerors.

Key clarifications include: there is no creek crossing but there is a very steep rocky grade requiring a bulldozer for grading and rolling dip shaping; no water is required for grading or compaction; some damaged drains will need to be removed with disposal handled by the Forest Service; the Restore Drainage Function uses pay item 839(1) with no water; Road Blading uses pay item 811 and requires addressing the steep rocky section without lifting the blade; mobilization is to be priced as a lump sum rather than per mile; and bonding costs should be included in the mobilization line item. The amendment must be acknowledged by offerors prior to the solicitation closing date. The effective date of the amendment is February 13, 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED 16C. DATE SIGNED

PAGE OF PAGES

CODE

(X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

2. AMENDMENT/MODIFICATION NUMBER

A00002

6. ISSUED BY

USDA FOREST SERVICE

PPS FPO SW ZONE CSA-6

TANYA TORRES

CONTRACT SPECIALISTALIST

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)

ALL OFFERORS

9A. AMENDMENT OF SOLICITATION NUMBER

127EAW25R0003

1 2

02/13/2025

9B. DATED (SEE ITEM 11)

01/13/2025

1142702

7EAWAW

X 1

X

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PROJECT: Phase I Road maintenance, Buckhorn Road Los Padres National Forest, CA.

A00002

The purpose of this solicitation amendment is to provide Request For Information (RFI) Responses.

See page 2 for additional information.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

JEREMY B. BEDNER

AMENDMENT OF SOLICITAITON/MODIFICATION OF CONTRACT PAGE NO. 2 OF 2

CONTINUATION PAGE

CONTRACT NO:

127EAW25R0003

ORDER NO: MODIFICATION NO:

A00002

14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED)

A.Below are the Request For Information (RFI) responses which are hereby incorporated into any subsequent contract award.

Failure to use the revised documents and requirements revised within will result in your proposal being non-responsive.

RFI #1 –The Statement of Work references creek crossings that are full of large boulders and a requirement for a bulldozer for completing the work. From the map it does not appear that there are any large creek crossings so can additional guidance be provided? If there are no crossings, will a bulldozer still be required?

Answer: The creek crossing was a left-over item from a previous task order. There is no creek crossing but there is a very steep grade that is extremely rocky, and this section will need a bulldozer for grading and rolling dip shaping.

RFI #2 –Will water be required for any of the work?

Answer: No water is required for grading or compaction.

RFI #3 – Will new overside drain installation require removal of old drains and if so, will old overside drains need to be removed from the site for disposal?

Answer: There will be a few damaged drains that will need to be pulled. The Forest will handle the disposal.

RFI #4 – Is the Restore Drainage Function 839 Unit Price on the Solicitation Schedule of Items based on 839 (1) or 839 (2) as referenced in the Supplemental Specification Pay Items?

Answer: 839(1) no water.

RFI #5 Which Pay Item on the Supplemental Specifications is the Road Blading (Bulldozer) Unit Price on the Solicitation Schedule of Items?

Answer: 811 Road Blading. The Forest wants to ensure that the Contractor will address the steep rocky section and not lift the blade. The rest of the road can be bladed with a typical road grader.

RFI #6- Section B Schedule of Items Item 805 Mobilization – In the description for this Item the Pay Unit in the Supplemental Specifications is listed as per mile. Is it to be assumed that the Unit Price in the Schedule of Items is the total cost for mobilization? Or should it be based on a per mile cos.

Answer: No, per the schedule on page 8 it is a lump sum item for total cost, not per mile.

RFI#7- Solicitation states bonding costs should be included in the contract price. In the Solicitation Schedule of Items, under which of the Construction Items should the cost of bonding be included?

Answer: The cost of bonds can be included in the mobilization line item.

B. All other terms and conditions remain unchanged.

///////////////////////////////////////////////LAST ITEM//////////////////////////////////////////////////

STANDARD FORM 30 (CONTINUATION)

A00001 - 127EAW24R0017 - Crestline Group CG Renovation
Amendment - A00001 - 127EAW23R0011 - Sky Ranch Road

SF 30 Continuation Page

File details come from the government source that posted it. Updated .