127EAT25Q0047 AMD 0002 Q_A.pdf

PDF 124 KB Posted

Attached to
R5 Fire Protection, Fire Suppression Systems & Alarms, Emergency Generator, and Backflow/Valve Systems
Solicitation number
127EAT25Q0047
Issued by

About this file

This document is a Solicitation Amendment for a USDA fire protection contract (Solicitation Number: 127EAT25Q0047) issued on 7 August 2025, covering R5 Fire Protection, Fire Suppression Systems & Alarms, Emergency Generator, and Backflow/Valve Systems. The solicitation includes a comprehensive Q&A document detailing specific technical requirements, with key details including 26 interior and 6 exterior standpipe systems, a water supply from the City of Vallejo's public water tower, one main exterior backflow preventer valve, and an 8x90 pipe configuration. The contract requires a 5-year sprinkler and standpipe inspection (last completed in May 2020), potential conversion to cellular monitoring transmission, and rust prevention strategies for exterior piping in compliance with NFPA 20 standards. Attachments provide additional technical documentation including generator details, fire alarm panel information, pump testing reports, and riser pipe service records.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Number: 127EAT25Q0047 AMD 0002

SOLICITATION

127EAT25Q0047

R5 Fire Protection, Fire Suppression Systems &

Alarms, Emergency Generator, and Backflow/Valve Systems

ISSUED: 7 August 2025

28 August 2025 Amendment 0002

Question 1: Could you kindly provide the incumbent contractor’s name, the previously awarded contract number, and the total award amount?

Answer: This is a new contract.

Question 2: Provide the number of standpipe systems & hose valves.

Answer: Interior- 26ea, Exterior- 6ea

Question 3: Can you provide the date of the last 5-year sprinkler & standpipe inspection? Based on the stickers found on the base riser, it was due in 2025 but did not locate another sticker confirming this inspection was completed. I would like to confirm that this inspection should be included in our base pricing.

Answer: The last sticker indicating when the 5-year inspection was completed for the sprinkler & standpipe systems was on May 2020. A 5-year inspection needs to occur as soon as possible upon the award of the contract.

Question 4: During the bid walk, it was undetermined which area of the building was serviced by the pre-action sprinkler system. Please provide the as-builts if available or explain in detail the portion of the building protected by this system.

Answer: The fire release control panel for the sprinkler systems is in support of the entire system as far as we are aware of the system.

Question 5: Does USDA have a requirement for what means of monitoring transmission is used? Would it be acceptable to convert to a cellular dialer?

Answer: Currently, cooper line is supporting the current system. Yes, a cellular dialer could be acceptable upon review between the vendor and COR. Wanted to share, an evaluation of the current cellular services would need to be conducted by the vendor.

Question 6: Please provide a picture of the name plate on the generator, manufacture, horsepower etc

Answer: See Attachment (1.1,1.2, 1.3)

Question 7: Please send a copy of the last preventive maintenance report for the generator.

Answer: See attachments (1.1,1.2, 1.3)

Question 8: How many standpipes are there in total?

Answer: Interior- 26ea, Exterior- 6ea

Question 9: Are there any smoke detectors under the sub-floor in the data room?

Answer: There are smoke detectors as part of the HVAC Air Handler Unit inside this room.

Question 10: What location(s) of the building does the Total Pack pre-action supply?

Answer: The fire release control panel for the sprinkler systems is in support of the entire system as far as we are aware of the system.

Question 11: What specifically do you require for the rust prevention of the exterior piping at the pump house?

Answer: This is for all related systems involved in the contract for interior and exterior equipment. Note: Manufacturers and facility managers must implement corrosion protection strategies, such as: NFPA 20 outlines maintenance and protection standards for fire pumps. Compliance not only ensures safety but also enhances the longevity of your fire pump system. Requirement would involve the removal of rust as much as possible, dirt and grime, before applying appropriate coating, sealants, greases and applying the appropriate surface protections such as paint while maintaining color coding surfaces with the appropriate colors.

Question 12: Are all the facilities of your client's agency using public water, or are they on private wells?

Answer: Public water (Water Tower) – City of Vallejo

Question 13: How many backflow preventer valves does your client have to be tested annually?

Answer: One exterior main backflow preventer valve, and any smaller hidden associated backflow valves in relation to the fire suppression systems. Proper maintenance and corrosion control measures are associated with this equipment too.

Question 14: What size is each backflow preventer valve?

Answer: Based on the right-angle & left-angle pipe feeding into the backflows it indicates 8 x 90. See Attachment (1.4).

Question 15: Provide pictures of the inside and outside of the fire alarm panel as well as a copy of your last alarm inspection report.

Answer: See Attachment (1.5)

Question 16: Can you provide the Quantity and pictures of the sticker from the last time it was serviced on the Risers pipes from the main water line for the fire piping system?

Answer: See Attachment (1.6)

Question 17: To get a good estimate together, we just need to know how many rooms we need to access to visually inspect the sprinkler heads.

Answer: See Attachment (1.7)

Question 18: Can you share the past NFPA 72 and NFPA 25 reports with cover letters? This will assist us in identifying the number of devices.

Answer: This is a new contract.

Question 19: Can you share any past Fire Pump Testing Reports?

Answer: Attachment (1.8)

Question 20: How many tie-ins are there to the city water systems?

Answer: Public water (Water Tower) – City of Vallejo