Site Visit Schedule.pdf

PDF 459 KB Posted

Attached to
National Forests and Grasslands in Texas Facilities Construction Federal contract opportunity
Solicitation number
127DF520R0007
Issued by
Department of Agriculture Forest Service R8-Southern Region

View the file

Other files for this federal contract opportunity

Other files attached to National Forests and Grasslands in Texas Facilities Construction, newest first.
File Type Posted
Additional Q-A.pdf PDF
Site Visit Notes and Sign-In Sheets.pdf PDF
Task Order 3 Package.pdf PDF
Confined Spaces.pdf PDF
Performance Relevancy.pdf PDF
Task Order 1 Package.pdf PDF
Financial Info.pdf PDF
DBWD TX20200116.pdf PDF
Task Order 4 Package.pdf PDF
Task Order 2 Package.pdf PDF
Solicitation 127DF520R0007.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

127DF520R0007

Road and Facility Construction

National Forests and Grasslands in Texas Revised Page 44 of 46

(c) Task Order Technical Proposal Instructions

Task Order technical proposals shall include a Plan of Operations, which provides a narrative that describes how the specific work will be organized and managed so that all activities are completed in accordance with project specifications and within the allotted contract time. At a minimum, provide a general plan for the sequence of work across the project, including all work items. Any work items noted in the Schedule of Items should be specifically addressed in the proposal.

(d) Price Proposal Instructions

(1) Complete and submit price proposal per Section B - Schedule of Items for each of the two seed Task Orders.

(2) Prices proposals shall be submitted for all task orders, even if the offeror opts out of being awarded one of the task orders. Prices should be reasonable and realistic and based on the realization that an award could be made and the offeror would be expected to perform the required work at the offered price.

(End of Provision)

AGAR 452.237-71 Pre-Bid/Pre-Proposal Conference. (FEB 1988)

(a) However, a series of site visits will be conducted for the individual task orders per the following schedule:

Caney Creek Amphitheater Decommissioning Project – 06/10/2020 at 2:00PM Sam Houston Communication Building Renovations – 06/11/2020 at 10:00AM Lufkin Exterior Fence Painting and Repair – 06/10/2020 at 10:00AM Lufkin Warehouse Roofing and Ceiling Repair – 06/10/2020 at 10:00AM

(b) Offerors shall submit all questions in writing no more than five (5) business days after the last site visit. An amendment to the solicitation containing an abstract of the questions and answers will be posted at www.fbo.gov within five (5) business day thereafter.

(c) The Government assumes no responsibility for any expense incurred by an offeror prior to contract award.

(End of Clause)