Additional Q-A.pdf
PDF 73 KB Posted
- Attached to
- National Forests and Grasslands in Texas Facilities Construction Federal contract opportunity
- Solicitation number
- 127DF520R0007
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Site Visit Notes and Sign-In Sheets.pdf | ||
| Site Visit Schedule.pdf | ||
| Task Order 3 Package.pdf | ||
| Confined Spaces.pdf | ||
| Performance Relevancy.pdf | ||
| Task Order 1 Package.pdf | ||
| Financial Info.pdf | ||
| Task Order 4 Package.pdf | ||
| Task Order 2 Package.pdf | ||
| Solicitation 127DF520R0007.pdf | ||
| DBWD TX20200116.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Apply to all projects:
1. Will local or county permits be required?
Contractor is responsible for any permits however, no known permits required for the work in these four projects.
2. Are licensed trades required for projects?
Licensed trades required for any electrical and plumbing installations.
3. Will government consider all projects together?
Award of individual task orders are separate and independent from other award decisions.
Caney Creek
1. Please verify if there is septic to pump and cap. If there is septic, please provide location or survey of area showing all improvements?
No septic to pump. There is a water fountain to remove and that drain (if to a sewer) must be capped.
2. Is the old water fountain brick structure and pad to be removed?
Yes
3. Is there a well location on site?
No
4. Is there a diagram of the amphitheater area with square footage? General survey or drawing showing bounds of project?
No drawing available. The limits are the items that make up the amphitheater including the buried trash pit, water fountain/base, asphalt path, lights and wire in trees and pole mounted lights, and pipe pedestals.
5. What bounding areas are the limits of this project scope, either from center of the amphitheater or other landmarks?
From the center of the amphitheater sitting area the scope would include approximately 150’. See items listed in previous question #5.
6. Is there a buried covered trash pit and if so, will it be included in the removal?
Yes, this was located and discussed at the site visit.
Sam Houston Ranger District Office
1. The door is rotted, will this be part of SOW?
2. There is damaged wall insulation is it included in SOW
3. Will it be possible to park our truck and trailer inside fence area close to work area?
4. How long can power be disconnected to complete repairs?
Minimal. This must be scheduled with the COR to minimize effects on radio communication.
5. Will we need to notify a third party of power down of communications and weather station?
COR
Fence repairs-
1. Will contractor have access to road ROW on both sides of fence for equipment during project?
Yes. The contractor will be responsible for repairing any ruts or ground disturbances to include supply and placement of soil to backfill and seeding according to the seeding schedule.
Warehouse Roof-
1. Is the detachment and resetting of gutters expected in the SOW?
Gutters will be replaced with new
2. Are any needed gutter repairs included in the SOW?
No repairs, they are to be replaced with new
3. Is the painting of gutters/downspout included in SOW?
4. Has the owner performed any lead or asbestos testing on Task Order #4 for the demolition of the existing roof, Fascia, existing paint, etc.?
Records indicate roof replaced in 2008; some asbestos testing conducted in 2009.
5. If not, will contractor need to provide a cost in bid for testing?
For purposes of preparing bids you can presume NO testing will be required. If further investigation determines it is required, such will be handled separately.