C05_12760426Q0212_Amendment 0002_Questions and Answers.pdf

PDF 190 KB Posted

Attached to
Dell Hardware and Firmware Maintenance
Solicitation number
12760426Q0212
Issued by

About this file

This document is an Amendment 0002 to a Questions and Answers section for RFQ 12760426Q0212, issued by the United States Department of Agriculture Forest Service for Dell Hardware and Firmware Maintenance. The RFQ is managed by the Procurement and Property Services National Procurement Operations IT Contract Branch located in Albuquerque, New Mexico. The document addresses three clarifying questions regarding contract performance dates, hardware service rows, and third-party maintenance options.

The base performance period runs from December 2, 2026, through December 1, 2027, with two option periods extending from December 2, 2027, through December 1, 2028, and December 2, 2028, through December 1, 2029. The same 25 hardware service rows apply across all periods, and contractors may complete entitlement onboarding before full support becomes active. Regarding maintenance options, the Government confirmed that third-party maintenance is acceptable as an equivalent to Dell OEM support under AGAR 452.211-70, provided the contractor can demonstrate a confirmed method of acquiring third-party support with documented processes and confirmed points of contact, and the support meets the Statement of Work requirements of 9x5 Next Business Day onsite service with failed drives retained by the Forest Service.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

United States Department of Agriculture

Forest Service

Washington Office

Procurement and Property Services National Procurement Operations IT Contract Branch 4000 Masthead ST NE Albuquerque, NM 87109

RFQ 12760426Q0212, Dell Hardware and Firmware Maintenance

Amendment 0002 Questions and Answers

1. Attachment 1 lists a base performance start date of November 17, 2026, which precedes the November 18 quotation cutoff. Please confirm the intended base and option period dates and the date by which full support must be active.

Government Response – The intended base period and option period dates are as follows:

Base Period

December 2, 2026 – December 1, 2027

Option Periods

December 2, 2027 – December 1, 2028

December 2, 2028 – December 1, 2029

2. Please confirm whether the 25 hardware service rows repeat across the two option periods as the separate Attachment 2 tabs indicate, and whether the contractor may complete entitlement onboarding before full support starts.

Government Response: It is the same hardware across all option periods. The contractor may complete entitlement onboarding before full support starts.

3. The Amendment 0001 answer to Q6 allows third-party maintenance on tags where Dell OEM support is unavailable because of end-of-service-life limits. Will the Government also accept third-party maintenance as an equal under AGAR 452.211-70 on tags where Dell OEM support is still available, provided it meets the SOW (9x5 Next Business Day onsite, failed drives retained by the Forest Service)?

Government response – This is acceptable as long as the 9x5 support model is the available support method and there is a confirmed method of acquiring (process docs, who to call, etc) for third party support.