Midewin National Tallgrass Prairie FY 2019

July 10, 2019

PART I - THE SCHEDULE

SECTION A –ITEMS

Groups 8, 9, and 64 Abatement Contract

SUMMARY SCHEDULE OF ITEMS

Item No./Title
Description
Qty
Total Cost
1. Asbestos Analysis/Certification
Provide ACM inspection performed and signed by an Illinois Licenced ACM inspector to satisfy State of Illinois requirements prior to demolition.
1 (includes all Group 8 and 9 buildings)

2. Abatement of buildings in Group 8 in preparation for demolition

Remove and dispose/recycle off-site ACM ROOFING, SIDING, FLOOR TILE and other ACM identified by the inspection in line item 1. Also include all PCB ballasts, and fluorescent bulbs. Recycle and or dispose all misc. debris removed in order to get at transite.

Footprint of 10 buildings total approx. 21,400 square feet PLUS 950 linear feet of transite covered walkways

3. Abatement of buildings in Group 9 in preparation for demolition

Remove and dispose/recycle off-site

ACM ROOFING, SIDING, FLOOR TILE and other ACM identified by the inspection in line item 1. Also include all PCB ballasts, and fluorescent bulbs. Recycle and or dispose all misc. debris removed in order to get at transite.

Footprint of 11 buildings total approx. 31,000 square feet

4. OPTIONS: Remove transite roofs in Warehouse Group 64
Remove all roof panels, capping and misc. debris. From roof.
13,950 square feet of transite per building

GRAND TOTAL

SECTION C - GENERAL SPECIFICATIONS

C.1

SCOPE OF CONTRACT

Provide labor, materials, and equipment required to complete the following items on the Midewin National Tallgrass Prairie, 30239 South State Route 53, Wilmington, IL, 60481.

Mandatory Field Inspection: A Field Inspection date has been scheduled for the following date and place:

Location:

Midewin National Tallgrass Prairie Office

30239 S. State Route 53

Wilmington, Il 60481

Date:

August 15, 2019 Time:

9:00 AM CDT

This contract will include all pre-demolition abatement of Asbestos Containing Materials (ACM) , PCB’s, mercury, or other special waste as described in the 4 Items below:

Item 1. Asbestos Analysis/Certification

Provide ACM inspection performed and signed by an Illinois Licenced ACM inspector to satisfy State of Illinois EPA requirements prior to demolition. A copy of the EPA form is attached for reference as Attachment C.

This inspection is intended to identify all possible ACM, PCB’s, mercury, or other materials requiring special waste disposal and tracking associated with this project. At a minimum this will include the roofing, siding, light ballasts, light switghes, light bulbs, and floor tile located in the Groups 8 & 9 buildings only.

The Group 64 warehouses will not require an inspection because only the roofs will be removed from theses buildings and previous inspections have confirmed the transite to be ACM.

NOTE: In addition to the ACM, the peeling paint within the building should be considered to be lead based paint, based on the age of the buildings. It is the responsibility of the contractor to handle this material in accordance with all associated regulations where applicable.

ACM may include roofing, siding, floor tile, mastic, or other building materials.

Include only the cost for inspection, analysis, and reports in Item 1.

Item 2 Detail. Group 8 Buildings

ID
Name
Total SQFT
Floor tile $
Light Ballasts $
Misc. DEBRIS $
Transite $$
TOTAL $$
8-1
BLACK POWDER SERVICE MAG
183
N/A
N/A
8-6
BLACK POWDER FAN HOUSE
564
N/A
N/A
8-9
PRIMER REST HOUSE
808
N/A
N/A
8-10
SERV MAG PERCUS ELEMENTS
183
N/A
N/A
8-11
PRIMER PREPARATION*
9,428

N/A

8-12
POWER HOUSE
1,563
N/A
N/A
8-13
CHANGE HOUSE*
5,175
8-14
CHANGE HOUSE*
3,408
8-19
GUARD HOUSE
85
N/A
N/A
8-39A
LATRINE
36
N/A
N/A
Walkways ( 950 LINFT )
28,500
N/A
N/A

TOTAL ITEM 2

21,433
$_________
$________
$_______
$_________
*$________

*Enter this total in the Summary Schedule of Items above.

Item 3 Detail. Group 9 Buildings

ID
Name
Total SQFT
Floor tile $
Light Ballasts $
Misc. DEBRIS $
Transite $$
TOTAL $$
9-14
DETONATOR RUMBLING BLDG
1,968
N/A
N/A
9-15
FINAL INSPECTION BLDG
1,603
N/A
N/A
9-17
DETONATOR TESTING
640
N/A
N/A
9-19
FIRST AID BLDG
800
N/A
N/A
9-20A
CHANGE HOUSE*
4,521
9-20B
CHANGE HOUSE*
3,513
9-26
SEWAGE PUMPING STATION
299
N/A
N/A
9-33
CHANGE HOUSE*
7,029
9-36
ADMINISTRATION BLDG*
9,207

N/A

9-38
INCINERATOR*
882
9-42
EMERGENCY GEN BUILDING
285
N/A
N/A
TOTAL ITEM 3
30,747
$__________
$_________
$_________
$__________
*$__________

Enter this total into the Summary Schedule of Items above.

Item 4 Detail. OPTION ITEMS - GROUP 64 WAREHOUSE ROOFS

BLDG ID
Name
Total SQFT

(Note: this is the actual SF of ACM transite to be removed as confirmed on past removals)

Misc. Debris $$
Transite $$
TOTAL $$
64-1
Group 64 Roof - OPTION 1
13,950
64-2
Group 64 Roof - OPTION 2
13,950
64-3
Group 64 Roof - OPTION 3
13,950
64-4
Group 64 Roof - OPTION 4
13,950
64-5
Group 64 Roof - OPTION 5
13,950
64-7
Group 64 Roof - OPTION 6
13,950
64-9
Group 64 Roof - OPTION 7
13,950
64-10
Group 64 Roof - OPTION 8
13,950
64-11
Group 64 Roof - OPTION 9
13,950
64-12
Group 64 Roof - OPTION 10
13,950
64-13
Group 64 Roof - OPTION 11
13,950
64-15
Group 64 Roof - OPTION 12
13,950
64-20
Group 64 Roof - OPTION 13
13,950
64-22
Group 64 Roof - OPTION 14
13,950
64-24
Group 64 Roof - OPTION 15
13,950
64-25
Group 64 Roof - OPTION 16
13,950
64-26
Group 64 Roof - OPTION 17
13,950
64-27
Group 64 Roof - OPTION 18
13,950
64-28
Group 64 Roof - OPTION 19
13,950
64-29
Group 64 Roof - OPTION 20
13,950
64-30
Group 64 Roof - OPTION 21
13,950
64-31
Group 64 Roof - OPTION 22
13,950
64-32
Group 64 Roof - OPTION 23
13,950
64-33
Group 64 Roof - OPTION 24
13,950
64-34
Group 64 Roof - OPTION 25
13,950
64-35*
Mobilization (if an option is awarded after initial demob has occurred)
Per mobilization
N/A
N/A

Total Item 4 (enter this total in the summary schedule above)

*We only expect to have funding for between six and ten of these optional items at the time of award. If any of the remaining options are exercised after demobilization, the contractor will be paid for line item 64-35 for each required re-mobilization.

Remove and dispose off-site all identified ACM, PCB containing, or other special waste materials for all of the above listed buildings and structures in Group 8, 9, and 64 (Items 2, 3, and 4 above). A map of each location is included with the attachments. All work shall comply with appropriate federal, local and state regulations.

Previous projects have identified the following ACM materials so please include the following in your costs for this contract. If additional materials are discovered during the inspection, removal costs will be negotiated as a contract modification.

ACM Transite Roof - Entire roof covering all the buildings unless indicated with an “N/A” in the transite column of the lists above is to be removed and properly disposed off-site. The square footages provided for each building is the area of floor space the building occupies except for Group 64 buildings. Contractor is responsible for field measurements taking into account the slope of the roof, any overlap in panels, and including transite roof caps and price as a lump sum for each group of buildings in areas 8 & 9. For Group 64 the square footage listed is the actual square foot measure of ACM transite material removed during earlier demolition projects and is priced per building. Any roof vents, stacks, or other items associated with the roof removal shall also be proerly disposed or recycled as misc. debris.

ACM Floor Tile – Buildings with marked with an asterisk in the lists above indicate that ACM floor tile has been identified within that building. The majority of the tile is located in large open rooms that were former cafeterias, large meeting rooms, and offices. If the contractor encounters additional ACM floor tile other than where indicated, please notify the COR for confirmation before continuing with removal.

PCB Light Ballast and Fluorescent Bulbs – PCB containing ballasts and fluorescent bulbs are known to be present in several, but not all buildings. The Contractor shall identify, remove and dispose these items in accordance with applicable environmental laws, both State and Federal.

Misc. Debris - Remove and dispose/recycle all wood, metal, glass, or other construction debris generated during transite removal. Because the transite comprises the entire wall structure of the walkways, some items must be detached in order to get at the transite. Materials include, but is not limited to doors, frames, windows, roof fans, roof vents, wood knee walls. All metals are to be seperated and recycled whenever possible.

It the responsibility of the contractor to divert as much waste as possible away from the landfill. This shall be accomplished by adhering to the methods described in the Demolition Material Reuse/Recycle and Disposal matrix included below.

The following is offered to clarify the issue of free tipping fees at the Prairie View Landfill (PVL) located immediately south of the MNTP: (This is provided for information only and is subject to change and is not within the control of the USDA Forest Service it only represents the current situation at the Prairie View Landfill.

· PVL is accepting ACM. It is handled differently than other wastes. PVL can't handle huge amounts per day due to the way they are required to bury ACM. There are also placarding, handling, and paperwork differences. Contractor should contact PVL scale house for details.

· When PVL goes into a new cell (first layer over plastic liner), they will not be able to accept certain materials, it it up to the contractor to coordinate with PVL.

C.2

LOCATION AND DESCRIPTION

Location – Groups 8 and 9 are located ¼ mile east of Route 53, just north of Prairie Creek, on the Midewin National Tallgrass Prairie, in Wilmington, IL. Group 64 is located approximately 5 miles east of Groups 8 & 9. A map depicting the area is included as Attachment A. Layout of Group buildings is in Attachment B.

C.3

TECHNICAL REQUIREMENTS

A. Equipment Requirements Equipment shall be furnished on a fully operated basis, of modern design, and in good operating condition, with a competent qualified operator. Exhaust stacks on all engines, except those with exhaust-driven turbo-chargers, shall be equipped with spark arresters that will prevent the expulsion of sparks from the engine into the atmosphere. All fuel, supplies, repairs, and incidentals shall be furnished by the Contractor.

1. Inspection of Equipment Equipment will be inspected at the time it is delivered to the job. Equipment shall be clean, such as equipment that has been through a truck wash and not carrying invasive plants or seeds. Equipment that does not meet contract specifications may be rejected. Rejected equipment will be replaced or the deficiencies corrected within four (4) calendar days after notice of rejection. If the equipment cannot perform on site it must also be removed or replaced.

2. Operator The Contractor shall furnish a qualified, experienced and competent operator, capable of operating the equipment in terrain similar to that where the work is to be performed. The Government may require the replacement of an operator who is considered incompetent, careless, or otherwise objectionable. Operator shall wear OSHA approved safety gear while operating equipment and comply with the Occupational Safety and Health Act of 1970 (as amended).

B. Safety The contractor and its employees and subcontractors shall comply with all State and local safety requirements and will be thoroughly familiar with the Forest Service Safety Code for work of this type. This code is available for review at the closest Forest Service office. Protective devices, including but not restricted to hard hats, shall be worn. All efforts shall be made to protect traffic and the contractor vehicles shall stay within the appropriate speed in the areas but not to exceed thirty miles per hour (30 mph). When working, the contractor shall make readily available spill cleanup materials and any spill greater than one (1) pint shall be immediately reported to the Contracting Officer’s Representative (COR).

Contractors must avoid contaminated Army land in or near the work area, and must be aware of the potential for discovery of CERCLA wastes, TSCA (PCB) equipment, or remnant ordnance materials (Munitions and Explosives of Concern (MEC)). Contractors shall notify the COR or Inspector of any discovered suspicious material, equipment or items encountered during work.

C.4

PERFORMANCE REQUIREMENTS

A. Contractor is responsible for any notifications, licenses or permits required to perform this work.

All material disposals shall be in accordance with all applicable federal, state and local laws/regulations. Reuse/Recycle opportunities are to be maximized. Contractor shall provide all weigh tickets or other evidence of proper disposal in a timely manner but no later than with invoice(s).

B. Performance Schedule

The overall performance period for completion of items 1, 2 and 3 is 120 calendar days. Work may begin on or after September 1, 2019. Each item 4 option awarded in conjunction with items 1, 2, 3 will add 16 calendar days to the 120 day performance period. The contract will remain open until December 30, 2021 to allow for exercise of remaining optional items. Remobilization shall occur within 10 days of option award and the performance period will be 16 calendar days per roof.

C. Protection of Resources & Reparation of Any Damages

Contractor shall confine operations to the designated work area, follow designated travel lanes and use existing roads, railbeds, and parking areas unless approved by a FS representative. Contractor shall avoid entering any areas enclosed by orange construction fencing, or bamboo stakes and flagging. Any soil or other resource damage (e.g. rutting deeper than six inches, tracking, etc.) shall be repaired by the contractor prior to completion of the work.

The Contractor will ensure spill cleanup materials will be available on each project at all times on the Prairie. Any spill greater than one (1) pint must be immediately reported to the COR or Inspector. Contractor personnel must have training to ensure they are qualified to identify such releases and are competent to provide proper cleanup and reporting. All spilled materials and impacted soils will be removed and properly disposed as necessary.

D. Performance Measures for Completion of Contract

The following table describes how the FS will evaluate the completion of the demolition tasks:

REQUIREMENT
TASKS/CRITICAL

SUB-TASKS

QUALITY

STDS

AQL
METHOD OF MONITORING

1.

Demolition

Removal:

Gather

Segregate

Load/haul

Staging/stockpiling

Gather all materials from demolition unless otherwise noted; properly segregate waste; load and haul materials to the staging/stockpiling area (if necessary)
Demolition materials are completely removed from the demo site and properly staged in an orderly manner at the designated staging areas only. Materials shall not exist outside their staging areas.
100%
Visual 100%

Disposal

On-site

Off-site

Special treatment

Documentation

Demolition materials designated by the USFS to be disposed on-site shall be disposed at their designated location in a timely, safe and compliant manner. Demo materials designated by the USFS for off-site disposition shall be completely removed from the USFS property and disposed in compliance with all local, state, and federal regulations. The contractor shall acquire all necessary documentation and any special waste treatments.
Materials to be disposed shall be completely vacant from the demolition and staging areas.

On-site disposal areas shall be safe and in compliance with all applicable local, state and federal rules.

Demo materials to be disposed off-site shall be disposed in a manner that complies with all local, state, and federal regulations regarding the material and will be accompanied with all necessary documents and treatments.

100%
Visual 100%

Document

Review 100%

Reuse/Recycling

Segregate

Load/haul

Documentation

Demo material designated to be reused or recycled shall be segregated from material to be disposed. Recycled material shall be loaded and hauled to designated staging or recycling area. The contractor shall obtain applicable documentation.
Recyclable or reusable material is completely removed from the demolition site, staged in the designated area and in the best condition possible from the demolition.

All applicable local, state, and federal documents are acquired.

90 – 100%
Visual 90 – 100%

Document Review 100%

Mitigation/Restoration of any environmental damage
Repair all rutting, erosion or other environmental damage
Final area will be free of any ruts, erosion or any other signs of obtrusions
100%
Visual 100%

C.5

FS FURNISHED PROPERTY, MATERIALS AND SERVICES

The FS shall provide, without cost, the facilities, equipment, materials, and/or services listed below.

FS Furnished Materials:

1. Key for contractor gate access (cost of replacement for key not returned after work is completed will be paid by the contractor at the actual cost for changing the effected locks)

FS Furnished Facilities:

1. Overnight/weekend parking for Contractor equipment (unsecured)

2. Storage areas for materials (unsecured)

C.6

CONTRACTOR FURNISHED ITEMS AND SERVICES

General: Except for those items or services specifically stated to be furnished by the FS, the contractor shall furnish everything required to perform the work of this contract to the Acceptable Quality Level indicated in said contract and attachment(s).

Demolition Material Reuse/Recycle and Disposal Matrix The contractor shall recycle all applicable demolition waste including but not limited to brick, steel and concrete, unless otherwise approved by the USDA Forest Service Contracting Officer’s Representative (C.O.R.). The contractor shall submit in a timely manner to a designated representative of the USDA Forest Service all available weight tickets for the removed materials, recycled and landfilled. Note: Not all these items are expected to be found during this abatement project.

Material Type
Material Examples
Example Reuse/Recycle
Comments

1. Land clearing debris

Landscape material
Shredded/chipped,

Stockpiled on Midewin Landfill roads, other landscape use. May be tailored by Midewin to specific project needs

2. Ferrous Metal

Structural steel
Reuse or recycle as scrap
Removed from Midewin
Piping/conduit/culverts and appurtenances
Reuse or recycle as scrap
Removed from Midewin
Sheet metal, decking and piling
Reuse or recycle as scrap
Removed from Midewin
Recovered concrete reinforcing
Reuse or recycle as scrap
Removed from Midewin
Non-structural framing
Reuse or recycle as scrap
Removed from Midewin
Doors window and hardware
Reuse or recycle as scrap
Removed from Midewin
HVAC
Reuse or recycle as scrap
Removed from Midewin
Light poles or mounts
Reuse or recycle as scrap
Removed from Midewin

3. Non-ferrous Metal

Structural aluminum
Reuse or recycle as scrap
Removed from Midewin
Other aluminum
Reuse or recycle as scrap
Removed from Midewin
Copper, brass, bronze
Reuse or recycle as scrap
Removed from Midewin
HVAC
Reuse or recycle as scrap
Removed from Midewin
Other
Reuse or recycle as scrap
Removed from Midewin

4. Asbestos

Friable
Properly remove, handle and landfill
No other option
Transite, non-friable
Properly remove, handle and landfill
No other option
Asbestos-containing items such as doors, boilers, window glazing, ceiling tiles
Properly remove, handle and landfill
No other option

Asbestos-containing

Floor tile

Properly remove, handle and landfill
No other option

Asbestos-containing siding

Properly remove, handle and landfill
No other option

Asbestos-containing

Refractory/fire brick

Properly remove, handle and landfill
No other option

5. concrete

Paving/masonry
Reuse, recycle as aggregate
Removed from Midewin
Drainage structures
Reuse, recycle as aggregate
Removed from Midewin
Structural
Reuse, recycle as aggregate
Removed from Midewin
Other reinforced
Reuse, recycle as aggregate
Removed from Midewin

6. Asphalt

Bituminous paving
Recycle at asphalt plant. Prairie View

Landfill may accept as road material.

Removed from Midewin

7. Brick

Pavers/flooring
Reuse, recycle as aggregate
Removed from Midewin or stockpiled as specified
Masonry
Reuse, recycle as aggregate. Prairie View Landfill may accept for roads.
Removed from Midewin
Clay, ceramic, concrete, slate roofing
Reuse, recycle as aggregate
Removed from Midewin
Brick/refractory
Reuse, recycle as aggregate

Removed from Midewin

8. Stone

Pavers/flooring
Reuse, recycle as aggregate
Removed from Midewin or stockpiled as specified
masonry
Reuse, recycle as aggregate
Removed from Midewin or stockpiled as specified
aggregate
Reuse, recycle as aggregate
Removed from Midewin or stockpiled as specified

9. Wood

Poles - any
Reuse or recycle, shredded/chipped (Wilmington Park District may accept for reuse)
Landfill may accept shredded/chipped for roads use
Structural members
Reuse or recycle, shredded/chipped
Landfill may accept shredded/chipped for roads use
Sheathing, flooring
Reuse or recycle, shredded/chipped
Landfill may accept shredded/chipped for roads use
windows
Reuse or recycle, shredded/chipped
Landfill may accept shredded/chipped for roads use

10. Light fixtures

Lighting fixtures
Reuse or recycle
Removed from Midewin
PCB ballast in fluorescent lights
See “Capacitors” in “Other” below
Lamps
Reuse or recycle
Removed from Midewin

11. Other

Capacitors – PCB or other
Recycle, if PCB then dispose
Removed from Midewin
Motor/hydraulic Oil
Recycle
Removed from Midewin
Mercury Switches
Recycle
Removed from Midewin
Glass, including reinforced glass
Recycle
Removed from Midewin
Vinyl siding
Recycle
Removed from Midewin
Rigid insulation board
Landfill or other arrangement
There may be ways to recycle these materials, but with the quantity and condition of these materials it may not be feasible.
Insulation batting
Landfill or arrange for recycle
Asphalt roofing
Landfill or arrange for recycle
Specialty doors
Landfill or arrange for recycle
Carpet and padding
Landfill or arrange for recycle
Non-ACM ceiling tile
Landfill or arrange for recycle
Equipment and furnishings
Recycle/scrap
Removed from Midewin

END

Groups 8, 9, and 64 ACM Abatement