Attachment 2 REVISED Specs.pdf
PDF 393 KB Posted
- Attached to
- Removal of Aboveground Storage Tanks (AST)
- Solicitation number
- 12467020R0085
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-bid meeting notes Amendment 2.docx | DOCX document | |
| SF30 Amned 2.pdf | ||
| amendment 2 Enoree Work Center Pre-bid Photos.pdf | ||
| Amendment 2 Long Cane Edgefield AST Photos.pdf | ||
| Amendment 2 Pre-bid meeting sign-in sheet.pdf | ||
| Attachment 1 REVISED Schedule of Items.pdf | ||
| SF 30 Amendment 1.pdf | ||
| Attachment 2 Specs.docx | DOCX document | |
| Attachment 3 AST project photos.docx | DOCX document | |
| Attachment 5 map EN AST.pdf | ||
| Attachment 6 Edgefield wage rates.pdf | ||
| Attachment 4 map Edgefield AST.pdf | ||
| Attachment 1 Schedule of Items.docx | DOCX document | |
| R0085.docx | DOCX document | |
| Attachment 8 EXperience Questionaire.docx | DOCX document | |
| Attachment 7 Enoree wage Rates.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
12467020R0085 Amendment A00001 REVISED 8/5/2020
Attachment 2
ABOVE GROUND STORAGE TANK REMOVAL
STATEMENT OF WORK
DIVISION 1 – GENERAL REQUIREMENTS
01010 – SUMMARY OF WORK
Removal and disposal work for this project shall consist of the following:
LOCATION A - Edgefield Work Center, Edgefield County, SC:
Address: 1013 Plum Branch Rd, Edgefield, SC 29824
1. Remove two aboveground storage tanks connected to a now defunct fueling island and one free-standing tank. Tanks sizes: 2,000, 550, 525 gallons. Blow out all underground fuel lines and permanently cap lines below ground.
2. Remove fuel island: pumps, and concrete pad. Install new concrete slab, level with the existing/surrounding parking surface.
3. Remove UST vent pipe behind gashouse and patch hole in roof.
4. Solid waste/recyclable materials to removed and properly disposed: up to 2,000 lbs of metal/bulky waste materials.
5. Pole barn floor hoist; 1) Remove the suspected 50-gallons of hydraulic oil in the underground tank by pumping; 2) Dispose of the oil (for concentrations of polychlorinated biphenyls (PCBs) greater than 50 ppm, dispose by approved incineration); and 3) Dispose of hydraulic oil-containing components (filters etc.).
LOCATION B – Enoree Work Center, Newberry County SC:
Address: 20 Work Center Road, Whitmire, SC 29178
6. Remove three aboveground storage tanks the connected fueling island. Tank sizes: 2,000, 1,000, 2,000 gallons. Blow out all underground fuel lines and permanently cap lines below ground.
7. Remove the fuel island: pump, associated structure/roof, and concrete pad. Install new concrete slab, level with the existing/surrounding parking surface.
See attached Location Map.
01060 – REGULATORY REQUIREMENTS
All material to be removed shall be disposed of in accordance with Federal and SC State Regulations.
S.C. Department of Health and Environmental Control (DHEC) does not regulate aboveground storage tank (AST) systems. However, it is the responsibility of the contractor to comply with federal and state laws regarding waste disposal. The fuel tanks have been pumped empty, but residual undrained fuels likely remain, and must be disposed of or recycled properly. The hydraulic tank may contain up to 50 gallons of
PCB-containing oil that must be properly disposed of.
01300 – SUBMITTALS
Submittals shall include the following unless otherwise required in the specification:
1. Dates and revision dates.
2. Project name and contract number.
3. Names of contractor, subcontractor, supplier and manufacturer.
4. Specifications section number.
5. Field dimensions and relation to adjacent structures.
6. Applicable standards such as ASTM or State/Federal Specifications.
7. Contractor's stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents.
8. Provide all submittals within 14 calendar days of contract award unless otherwise required by the specification.
The following submittals are required:
Title Applicable Contract clause or
Specification
Time for Government
Approval After
Submittal
Traffic Control Plan Standard specifications 7 days
Safety Plan Accident Prevention clause
[FAR 52.236-13] Section 2.14
7 days
Engineered Spill Prevention Plan Landscape Preservation and
Hazardous Materials clause
[FAR 52.236-13] Section 2.15
7 days
Proposed Progress Schedule Schedules for Construction
Contracts
[FAR 52.236-15]
7 days
Designation of Contractor's Representative Superintendence by the
Contractor
[FAR 52.236-6]
7 days
Drug Free Workplace Policy Drug-Free Workplace
[FAR 52.223-6]
7 days
SF1413 - Statement and Acknowledgement for each Subcontractor including Owner/Operators and other Sole Proprietorship Subcontractors [not required for material suppliers]
Subcontracts (Labor Standards)
[FAR 52.236-11]
Before "Notice to
Proceed" is issued.
Title Applicable Contract clause or
Specification
Time for Government
Approval After
Submittal
Generator copy of all waste manifests and certificates of disposal.
01060 – REGULATORY
REQUIREMENTS
Submit to COR before 7 days before final invoice.
01510 – TEMPORARY UTILITIES
A. Electricity – Electricity is available within about 100 feet of the work site.
B. Water – Water is available at the work sites.
C. Sanitary – Restrooms are available at the work sites and can be accessed with the assistance of
Forest Service personnel on site. All work times shall be pre-coordinated with COR to ensure contractor has access.
01635 – PROTECTION OF ADJACENT AREAS
A. The Contractor is responsible for repairing all damage to areas caused by construction/demolition activities or equipment at no additional cost to the government as directed by the Contracting
Officer (CO).
DIVISION 2 – SITE WORK
SECTION 02050 – DEMOLITION
PART 1 – GENERAL
A. All work shall comply with EPA, state, and all applicable regulations.
B. For hazardous materials encountered that are beyond the normal scope of this project, immediately notify the Contracting Officer Representative (COR) or CO.
PART 2 – PRODUCTS
A. Backfill Material – Backfill is not anticipated for this contract, however, small quantities may facilitate the restoration of cut and removed areas, such as the fuel island slabs, or below-ground pipe terminations, prior to installing new concrete. If required, contractor shall be responsible for furnishing all backfill material necessary for backfilling, including compaction. Material shall be approved by the COR prior to installation.
B. Concrete - See section 03300 below for details.
PART 3 – EXECUTION
A. Locate, identify, shut off, disconnect, and cap off all utility connections to the tanks, fuel island, and other removed items.
B. Conduct demolition operations and remove debris to prevent injury to people and damage to adjacent buildings and site improvements.
C. Ensure all "hot work" related to fuel systems are pre-planned to mitigate all fire and explosion hazards. "Hot work" means riveting, welding, flame cutting or other fire or spark-producing operations. See OSHA regulations for safety requirements, including: 29 CFR 1910.252(a)(3)(i), 29 CFR 1917.152. OSHA Publication FS-3586 describes eliminating explosive atmospheres by purging with inert gases by qualified individuals.
D. All material removed as part of this contract shall be considered non-salvageable and shall be removed from the project site and disposed legally. Do not burn demolished materials.
E. Contractor shall prevent demolition debris, nails, glass, etc., from falling on walkways and road areas. Site shall be left in a neat and safe condition at the end of each working day.
F. Contractor shall not remove or otherwise damage existing trees unless otherwise directed by COR.
G. All areas disturbed during construction shall be graded smooth and contoured to the natural slopes of the surrounding ground. The area shall then be seeded and mulched as specified.
H. Contractor is responsible for payment of all required cost/fees associated with disposal of all waste materials generated for this contract.
SECTION 03300 - CAST-IN-PLACE CONCRETE
PART 1 - GENERAL
A. This section covers cast-in-place concrete, including curing and finishing of concrete.
B. The latest editions of the following specifications and recommended practices shall govern:
1. ACI 301 - Specifications for Structural Concrete for Buildings.
2. ACI 306 - Recommended Practice for Winter Concrete.
3. ACI 305 - Recommended Practice for Hot Weather Concrete.
http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=9853&p_table=standards http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=9853&p_table=standards http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=9853&p_table=standards http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=9853&p_table=standards http://www.osha.gov/pls/oshaweb/owadisp.show_document?p_id=9853&p_table=standards https://www.osha.gov/laws-regs/interlinking/standards/1917.152 https://www.osha.gov/Publications/OSHA_FS_3586.pdf
PART 2 - PRODUCTS
A. Aggregate shall conform to the requirements of South Carolina Department of Transportation, or
US DOT, FP-14, Sampling, Testing, and Acceptance Requirements, Table 301-1. Aggregates shall be well graded from fine to coarse within designated limits for structural concrete.
B. Portland Cement shall comply with ASTM C150, Type 1. Supplier shall provide mill certification of compliance with specification.
C. Water shall be clean, fresh, and free from injurious amounts of minerals or foreign substances.
D. Air entrainment agents shall comply with ASTM C260.
E. Liquid curing membrane shall be Type 1-D or Type 2, per ASTM C-309.
F. Concrete Mix Design
1. Unless otherwise indicated all concrete shall have a minimum "compressive strength" of 3,000 psi at 28 days.
2. Concrete shall be air entrained and shall contain not less than 4 percent and not more than 7 percent entrained air determined by test procedure ASTM C138.
3. The design of the concrete mixture shall be the responsibility of the Contractor.
4. Additional amounts of Portland cement, as required by the COR is required when using pre-mix, "Sack-crete" type products.
PART 3 - EXECUTION
A. "Ready-Mixed Concrete" may be employed if the time interval between mixing at the plant and discharge into the form does not exceed 1-1/2 hours.
B. All concrete shall be placed within 1-1/2 hours from the time of mixing.
1. No concrete shall be placed after it has started its initial set.
2. No concrete with a temperature above 90 degrees F shall be placed.
C. Concrete shall be placed in such a manner as to avoid segregation of the mixture.
1. Concrete shall be spread in horizontal layers when practicable.
2. No concrete shall be freely dropped more than 5 feet.
3. Depositing a large quantity of concrete and flowing or working it along the forms will not be permitted.
D. Mechanical vibrators shall be used for consolidation of concrete.
1. Concrete shall be consolidated within 15 minutes after placement.
2. If consolidation of concrete with mechanical vibrators is impractical, hand tamping, rodding, and spading will be permitted provided approval is secured from the COR.
3. A minimum of two vibrators, in working order, shall be on the job during concrete placement.
E. Concrete shall be placed and protected as specified for temperature conditions.
F. Contractor shall have sufficient number of experienced concrete workers available for placement and finishing of concrete work at the building slab and sidewalk.
G. Concrete plant standards and truck mixer and agitator standards shall be as recommended by the
National Ready-Mix Association.
H. Finishing
1. All finishes shall be made without use of cement or other dusting materials.
2. Concrete shall be struck to proper grade and surface finished with float trowels.
3. At all exposed formed surfaces, remove all ties, fill all form tie holes and imperfections; i.e., "honeycombing," with dry cement mortar, remove all lines, and then "sack" or finish to match adjacent surfaces.
4. Exterior concrete slabs shall be finished with a steel trowel and given a broom finish to produce a uniform textured surface. All edges shall be finished with a 1/4 inch radius edging tool.
I. Concrete shall be protected against rapid drying and kept moist for 7 days by covering with curing paper with edges sealed, burlap, canvas, Type l-D or Type 2 liquid membrane curing compounds, or by sprinkling.
J. Testing (if required)
1. Concrete shall have a minimum 28-day breaking strength of 3000 psi when tested in accordance with ASTM C-39.
[These testing requirements will only apply if directed by the Contracting Officer as a contract modification.]
2. The Contractor will make test cylinders from the concrete being incorporated in the project and send them to a Forest Service-approved laboratory for testing. Contractor shall supply all material and equipment needed for testing or consult an independent testing company. Cost of testing will be paid by the Contractor.
3. Slump testing will be performed by the Contractor in accordance with ASTM Standard Method
C143. Slump shall be 3", plus or minus 1", for vibrated concrete, or no more than 5" for non-vibrated concrete. Air entrainment shall be as specified in Part 2, F.2.
END OF SECTION C (APRIL 2020)