Attachment 1 Schedule of Items.docx
DOCX document 22 KB Posted
- Attached to
- Removal of Aboveground Storage Tanks (AST)
- Solicitation number
- 12467020R0085
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pre-bid meeting notes Amendment 2.docx | DOCX document | |
| SF30 Amned 2.pdf | ||
| amendment 2 Enoree Work Center Pre-bid Photos.pdf | ||
| Amendment 2 Long Cane Edgefield AST Photos.pdf | ||
| Amendment 2 Pre-bid meeting sign-in sheet.pdf | ||
| Attachment 2 REVISED Specs.pdf | ||
| Attachment 1 REVISED Schedule of Items.pdf | ||
| SF 30 Amendment 1.pdf | ||
| Attachment 2 Specs.docx | DOCX document | |
| Attachment 3 AST project photos.docx | DOCX document | |
| Attachment 5 map EN AST.pdf | ||
| Attachment 6 Edgefield wage rates.pdf | ||
| Attachment 4 map Edgefield AST.pdf | ||
| R0085.docx | DOCX document | |
| Attachment 8 EXperience Questionaire.docx | DOCX document | |
| Attachment 7 Enoree wage Rates.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ABOVE GROUND STORAGE TANK REMOVAL
SCHEDULE OF ITEMS
| BID ITEM |
| DESCRIPTION |
| MM |
| UNIT |
| QTY. |
| UNIT |
PRICE
TOTAL
LOCATION A - Edgefield Work Center, Edgefield County, SC
| 1 |
| Remove two aboveground storage tanks connected to a now defunct fueling island and one free-standing tank. Tank sizes: 2,000, 550, and 525 gallons. Blow out all underground fuel lines and permanently cap lines below ground. |
| LSQ |
| LSQ |
| 1 |
| $______ |
| $______ |
| 2 |
| Remove fuel island; pump and concrete pad. Install new concrete slab, level with the existing/surrounding parking surface. |
| LSQ |
| LSQ |
| 1 |
| $______ |
| $______ |
| 3 |
| Remove UST vent pipe behind gashouse and patch hole in roof. |
| LSQ |
| LSQ |
| 1 |
| $______ |
| $______ |
| 4 |
| Solid waste/recyclable materials to removed and properly disposed; up to 2,000 lbs of metal/bulky waste materials. |
| LSQ |
| LSQ |
| 1 |
| $______ |
| $______ |
| 5 |
| Pole barn floor hoist; 1) Remove the suspected 50-gallons of hydraulic oil in the underground tank by pumping; 2) Dispose of the oil (for concentration greater than 50 ppm, dispose by approved incineration); and 3) Dispose of hydraulic oil-containing components (filters etc.). |
| LSQ |
| LSQ |
| 1 |
| $______ |
| $______ |
LOCATION B – Enoree Work Center, Newberry County SC
| 6 |
| Remove three aboveground storage tanks the connected fueling island. Tank sizes: 2,000, 1,000, and 2,000 gallons. Blow out all underground fuel lines and permanently cap lines below ground. |
| LSQ |
| LSQ |
| 1 |
| $______ |
| $______ |
| 7 |
| Remove the fuel island; pump, associated structure/roof, and concrete pad. Install new concrete slab, level with the existing/surrounding parking surface. |
| LSQ |
| LSQ |
| 1 |
| $______ |
| $______ |
| Total: |
| $______ |
LSQ -- Lump Sum Quantity, MM -- Method of Measurement
File details come from the government source that posted it. Updated .