Attachment_1___Schedule_of_Items.xlsx
XLSX spreadsheet 18 KB Posted
- Attached to
- Construction IDIQ Federal contract opportunity
- Solicitation number
- 12467018R0010
About this file
Atch 1 Schedule of Items
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| scan0068.pdf | ||
| Attachment_1__A_Statement_of_work.doc | DOC document | |
| Attachment_2_A_Statement_of_Work.pdf | ||
| Attachment_3_Experience_Questionnaire.docx | DOCX document | |
| Attachment_2_Schedule_of_Items.xlsx | XLSX spreadsheet | |
| RFP_12467018R0010.pdf | ||
| Attachment_1_B_Drawings.pdf | ||
| Attachment_1_C_DOL_WAGE_RATES.pdf | ||
| Attachment_2_C_DOL_WAGE_RATES.pdf | ||
| Attachment_2_B_Drawings.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table
| Quantities | ||
| Room | Area (SF) | Floor Type |
| Living | 250 | Vinyl |
| Hallways | 71 | Vinyl |
| Sleeping #1 | 138 | Vinyl |
| Sleeping #2 | 130 | Vinyl |
| Sleeping #3 | 130 | Vinyl |
| Bath #1 | 94 | Vinyl |
| Bath #2 | 60 | Vinyl |
| Laundry/Mech | 115 | Vinyl |
| Kitchen | 171 | Vinyl |
| Back Porch | 85 | Vinyl |
| Total | 1244 |
Estimate
| ITEM | DESCRIPTION | MM | QTY | UNIT | UNIT PRICE | TOTAL AMOUNT | Days | |
| A | Building 124 | |||||||
| A1 | Remove current floor finish, vinyl and carpet. Clean and prepare concrete for finished surface and stain aplication. | LSQ | 1 | LS | $ 6,000.00 | $ 6,000.00 | 5 | 03 35 43.10 |
| A2 | Stain Crew Quarters Concrete Floor with acrylic based stain. (2 coats) | CQ | 1244 | SF | $ 2.50 | $ 3,110.00 | 4 | |
| A3 | Seal Concrete floor stain with solvent-based acrylic sealer followed by a topcoat of a water-based acrylic sealer | CQ | 1244 | SF | $ 4.00 | $ 4,976.00 | 4 | |
| A4 | Furnish and place entrance mat at each building door. Grainger Indoor Entrance Mat, 3 ft. L, 24" W, 5/16" Thick, Rectangle, Black | CQ | 6 | EA | $ 50.00 | $ 300.00 | 1 | |
| Sub-Total | $14,386.00 | 14 | ||||||
| B | Building 126 | |||||||
| B1 | Remove current floor finish, vinyl and carpet. Clean and prepare concrete for finished surface and stain aplication. | LSQ | 1 | LS | $ 6,000.00 | $ 6,000.00 | 5 | 03 35 43.10 |
| B2 | Stain Crew Quarters Concrete Floor with acrylic based stain. (2 coats) | CQ | 1244 | SF | $ 2.50 | $ 3,110.00 | 4 | |
| B3 | Seal Concrete floor stain with solvent-based acrylic sealer followed by a topcoat of a water-based acrylic sealer | CQ | 1244 | SF | $ 4.00 | $ 4,976.00 | 4 | |
| B4 | Furnish and place entrance mat at each building door. Grainger Indoor Entrance Mat, 3 ft. L, 24" W, 5/16" Thick, Rectangle, Black | CQ | 6 | EA | $ 50.00 | $ 300.00 | 1 | |
| Sub-Total | $14,386.00 | 14 | ||||||
| C | Building 128 | |||||||
| C1 | Remove current floor finish, vinyl and carpet. Clean and prepare concrete for finished surface and stain aplication. | LSQ | 1 | LS | $ 6,000.00 | $ 6,000.00 | 5 | 03 35 43.10 |
| C2 | Stain Crew Quarters Concrete Floor with acrylic based stain. (2 coats) | CQ | 1244 | SF | $ 2.50 | $ 3,110.00 | 4 | |
| C3 | Seal Concrete floor stain with solvent-based acrylic sealer followed by a topcoat of a water-based acrylic sealer | CQ | 1244 | SF | $ 4.00 | $ 4,976.00 | 4 | |
| C4 | Furnish and place entrance mat at each building door. Grainger Indoor Entrance Mat, 3 ft. L, 24" W, 5/16" Thick, Rectangle, Black | CQ | 6 | EA | $ 50.00 | $ 300.00 | 1 | |
| Sub-Total | $14,386.00 | 14 | ||||||
| Total (plus 10%) | $47,473.80 | 14 | Ordering, Bonding, Weather, | |||||
| 56 |
HOT SHOT CREW QUARTERS
FLOORING RENOVATION 2018
ESTIMATE
ScheduleOfItems
| ITEM | DESCRIPTION | MM | QTY | UNIT | UNIT PRICE | TOTAL AMOUNT |
| A | Building 124 | |||||
| A1 | Remove current floor finish, vinyl and carpet. Clean and prepare concrete for finished surface and stain aplication. | LSQ | 1 | LS | $ - 0 | $ - 0 |
| A2 | Stain Crew Quarters Concrete Floor with acrylic based stain. (2 coats) | CQ | 1244 | SF | $ - 0 | $ - 0 |
| A3 | Seal Concrete floor stain with solvent-based acrylic sealer followed by a topcoat of a water-based acrylic sealer | CQ | 1244 | SF | $ - 0 | $ - 0 |
| A4 | Furnish and place entrance mat at each building door. Grainger Indoor Entrance Mat, 3 ft. L, 24" W, 5/16" Thick, Rectangle, Black | CQ | 6 | EA | $ - 0 | $ - 0 |
| Sub-Total | $ - 0 | |||||
| B | OPTION 1 Building 126 | |||||
| B1 | Remove current floor finish, vinyl and carpet. Clean and prepare concrete for finished surface and stain aplication. | LSQ | 1 | LS | $ - 0 | $ - 0 |
| B2 | Stain Crew Quarters Concrete Floor with acrylic based stain. (2 coats) | CQ | 1244 | SF | $ - 0 | $ - 0 |
| B3 | Seal Concrete floor stain with solvent-based acrylic sealer followed by a topcoat of a water-based acrylic sealer | CQ | 1244 | SF | $ - 0 | $ - 0 |
| B4 | Furnish and place entrance mat at each building door. Grainger Indoor Entrance Mat, 3 ft. L, 24" W, 5/16" Thick, Rectangle, Black | CQ | 6 | EA | $ - 0 | $ - 0 |
| Sub-Total | $ - 0 | |||||
| C | Option 2 - Building 128 | |||||
| C1 | Remove current floor finish, vinyl and carpet. Clean and prepare concrete for finished surface and stain aplication. | LSQ | 1 | LS | $ - 0 | $ - 0 |
| C2 | Stain Crew Quarters Concrete Floor with acrylic based stain. (2 coats) | CQ | 1244 | SF | $ - 0 | $ - 0 |
| C3 | Seal Concrete floor stain with solvent-based acrylic sealer followed by a topcoat of a water-based acrylic sealer | CQ | 1244 | SF | $ - 0 | $ - 0 |
| C4 | Furnish and place entrance mat at each building door. Grainger Indoor Entrance Mat, 3 ft. L, 24" W, 5/16" Thick, Rectangle, Black | CQ | 6 | EA | $ - 0 | $ - 0 |
| Sub-Total | $ - 0 | |||||
| Options may be awarded based on Available funding | Total | $ - 0 |
HOT SHOT CREW QUARTERS
FLOORING RENOVATION 2018
SCHEDULE OF ITEMS
File details come from the government source that posted it.