This document is a Scope of Work (SOW) for the ACP LTR Bridge Trail Crossing Fence Replacement project for the USDA U.S. Forest Service at the Savannah River Site. The project involves removing and replacing 9,200 linear feet of fence line at three locations: Patterson Mill Road (3,640 ft), Boiling Springs Road (3,650 ft), and Highway 125 (1,900 ft). The work includes removing existing 3-strand barbed wire fencing with wooden posts and replacing it with new 3-strand barbed wire and steel T-posts, replacing corner, end, and intermediate bracing, and installing new boundary signs.

The contractor will be responsible for providing all labor, materials, tools, equipment, and personal protective equipment, as well as implementing traffic control measures and following specific site regulations. The project requires a safety plan submission, and a RadCon inspector will be present to survey equipment in soil contaminated areas. Government-furnished equipment includes a Motorola radio, property and PACA passes, a remote worker map, and site boundary signs. The Contracting Officer Representative contacts are Travis McCullough and Jeremy Prince, with contact numbers provided in the document.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ACP LTR Bridge Trail Crossing Fence Replacement Scope of Work

USDA U.S. Forest Service – Savanah River

June 2025

1) INTRODUCTION:

Remove existing 3 strand barb wire fencing with wooden posts and replace with new 3 strand barb wire and steel T-posts at locations adjacent to located at HWY 125, Boiling Springs, and Patterson Mill Road. Remove and replace all corner, intermediate, and end bracing with new in-kind replacement wooden posts set in concrete.

Patterson Mill Road: 3,640 ft of fence replacement Boiling Springs Road: 3,650 ft of fence replacement Highway 125: 1,900 ft of fence replacement

2) SCOPE:

a) Remove and replace a total of 9,200 linear feet of fence line at the three locations in the SRS Tail Bridge Crossing areas. Work includes providing all labor, material, tools, equipment, Personal Protective Equipment (PPE), supervision, mobilization, and other incidentals necessary to construct and clear the boundary fence line. When needed, clearing limits are 3 feet from both sides of the fence line (total 6 feet).

b) Remove all existing wooden fence posts from the fence line and replace with steel t-posts. Existing wooden fence posts will be cut at ground level. Remove all existing corner, end and intermediate braces with new wooden posts and hardware. Bracing posts being replaced within a soil contamination area, will be cut at ground level and a new post shall be driven adjacent with post in-kind set in concrete. Attach 3-strands barbed wire to the top, middle and bottom, of steel tee line post as described in the fence detail sheet.

c) Gates will be reused. Hardware for the mounting of gates and wooden posts gates are mounted too will be replaced.

d) For the corner, end, intersection, immediate line brace, and gate brace panel of woven wire fences and 3-strand barbed wire fences: furnish and install brace panel with 9-gage twisted tension brace wires or 4-in diameter diagonal brace post with post set in concrete.

e) Replace any missing SRS boundary signs at 50 ft – 100 ft intervals along the replaced fence line.

f) Remove and dispose all existing fence material offsite or at the C&D landfill on SRS as designated by the COR.

3) Traffic Control

a) Contractor shall provide all necessary traffic control measures, personnel and obtain permitting required to perform this work as required referencing the Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD) and/or SCDOT MUTCD supplement/requirements.

3) PERSONAL QUALIFICATIONS

None, except for the contractor’s requirements.

4) GOVERNMENT-FURNISHED EQUIPMENT (GFE) AND MATERIALS

1. Site Motorola Radio

2. Property Pass & PACA Pass

3. Remote Worker Map

4. Site boundary signs

5) REGULATIONS/POLICIES

a) Contractors must furnish all labor, personnel, materials, quality assurance, supervision, transportation, equipment, tools, and supplies (including safety supplies).

b) Following all specifications for moving and maintenance for Post Closure Projects for EC-ACP, no limit to, within the boundaries of the Savannah River Site. (SRS)

c) The contractor must provide a safety plan prior to commencing work and submit it to the COR for review by the U.S. Forest Service Safety manager.

d) The contractor is not required to be RadCon-trained unless they disturb SCA (Soil Contaminated Area) or enter the creek. RadCon inspector will be present and survey the equipment in case the soil accidently gets disturbed. All equipment will be surveyed by Radcon before/after working in an SCA.

6) TRAINING

The contractor is responsible for all training for its employees on proper use of equipment.

7) POINT OF CONTACT (POC)

• Contracting Officer (CO):

• Contracting Officer Representative: (COR) Travis McCullough (803) 226-1166

• Alt. Contracting Officer Representative: (COR) Jeremy Prince (828) 644-6793