Amd 0001_Sol_12445525B0010 with RFIs.pdf

PDF 252 KB Posted

Attached to
ACP LTR Bridge Trail Crossing Fence Replacement
Solicitation number
12445525B0010
Issued by

About this file

This document is an Amendment (0001) to Solicitation 12445525B0010 for the ACP LTR Bridge Trail Crossing Fence Replacement project, issued by the USDA Forest Service. The amendment extends the bid deadline by 7 days to Wednesday, 6/25/2025 at 3:00 PM ET and provides detailed responses to contractor requests for information (RFIs) regarding the project.

Key project details include removing and replacing 11,000 linear feet of fence line at the SRS Tail Bridge Crossing area, with a 90-day performance period. The project requires replacing various fence components, including 35 intermediate brace panels, 35 corner braces, 9 gate posts, and 9 end braces, across multiple gate configurations. Contractors must provide their own traffic control plan, bathroom facilities, and obtain necessary SCDOT permits. An additional site visit is scheduled for June 23rd, 2025, at 9 AM, with strict requirements for obtaining visitor badges. The project is valued between $100,000 and $250,000, with award to be made to the lowest-priced, responsible offeror.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12445525B0010 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

ATLANTA GA 30309-2449

STE 876S

1720 PEACHTREE ST NW

USDA-FS CSA EAST 12

06/02/20250001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/02/2025

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Project: LTR Bridge Tail Crossing Fence Replacement

The purpose of this amendment is to:

1. EXTEND the solicitation bid deadline date by 7 days to Wednesday, 6/25/2025 at 3:00 PM

ET.

Another site visit can be scheduled for June 23rd, 2025 at 9AM but you will need to request another visitor badge for anyone interested. Please fill out the badge request form and return it to Jeremy.prince@usda.gov NO LATER THAN JUNE 18, 2025 3PM EST. If you need the form please email Jeremy to obtain the form. Any badge requests submitted after this time will not be processed in time for a site visit.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

PENNY R. ZORTMAN

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

12445525B0010/0001

2. Provide government responses to RFI's received.

3. Provide UPDATED Statement of Work, and

Schedule of Items removing Rocky road location.

4. Provide boundary maps for each location.

5. Provide the "Pre-bid PowerPoint Slides" shown during site visit on 6/10/25.

No other changes are made.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Project Name: ACP LTR Bridge Trail Crossing Fence Replacement Solicitation #: 12445225B0010

Government responses are in red:

1. Can the wooden posts be disposed of with the barbed wire at the C&D Landfill on site or will they have to be separated?

Do not have to be separated however, Fence posts may need to be cut to 3’ or less in order to dispose of in the C&D Landfill on site. C&D Landfill is approx. 45 min drive from work sites.

2. What is the number of fence corner, intermediate, end and gate braces that will need to be replaced?

Total Intermediate Brace Panel

Corner Brace Gate Posts End Brace # of Gates*

35 35 9 9 7 x 12’ Gates 1 x 8’ Gate

1 x Bifold Gate (two 8’ gates)

*All Gates will be reused, only hardware to mount/attach to posts will be replaced. “Gate posts” above are simply a single 8” post, in some instances Gates are also mounted to other brace panel posts.

3. Will SRS/USDA provide a drop yard / staging site in proximity to job sites?

Equipment / Supplies may be staged off Road 9 and Hwy 125 (Approx 15 min or less from all job sites) It will be behind a locked cattle gate on SRS property that the U.S.

Forest Service will provide access to. Road 9 must not be blocked.

Location: https://maps.app.goo.gl/Fwv7DTs6fx1RtH7W7

4. Please supply GPS co-ordinates for the fence start and end: the map is completely unclear about the location.

GPS Coordinates in SC State Plane are on the drawings added to the solicitation. See attachments.

5. The bid schedule shows a quantity of Zero for “Corner, End, Intersection, intermediate line brace, and Gate Brace Panel…” Please supply the specs & quantity for the fence wire, intermediate posts, etc.

Original SOW was not clear on the quantity to be replaced. Amendment now includes revised SOW stating all fence bracing will be replaced. See the Fence Detail attachment for specifications and RFI Question# 2 above for quantities. Schedule has quantities updated.

https://maps.app.goo.gl/Fwv7DTs6fx1RtH7W7 https://maps.app.goo.gl/Fwv7DTs6fx1RtH7W7

6. Is there a separate specification for the wetland areas? An 8' pole might not be long enough to reach stable ground.

Any posts in unstable ground may be set with concrete in a gravel bed. Any brace panels, corner posts, gate posts and end braces to be replaced that are currently in standing water shall be deferred and bypassed. Unused materials purchased by the gov from the contractor will become government property and be transferred to the government upon project completion.

7. Is a traffic plan required for all three locations?

Yes. Contractor will be responsible for Traffic control planning and implementation including obtaining any/all necessary permitting and documentation with SCDOT as required. Plan does not need to be submitted to bid on the project. Awardee may generate Traffic Control plan and obtain permitting after receiving the contract award.

See SCDOT’s Traffic Control Devices and Work zone Traffic Control information on their website. https://www.scdot.org/business/access-management.html.

8. Our subcontracting partner was present for the site visit but was not permitted to enter due to not obtaining approval prior. Will another site visit be available?

Another site visit can be scheduled for June 23rd, 2025 at 9AM but you will need to request another visitor badge for anyone interested. Please fill out the badge request form and return it to Jeremy.prince@usda.gov NO LATER THAN JUNE 18, 2025 3PM EST. If you need the form please email Jeremy to obtain the form. Any badge requests submitted after this time will not be processed in time for a site visit.

9. Do we need to supply our own bathroom facilities for our crew?

Portable toilets will not be provided by the gov.

10. Can USG identify specific permits required to perform the project?

Site Use, Site Clearance, Environmental Evaluation Checklist, and GPR / Cable location services will be/have been done by the government. Contractor will need to apply for necessary traffic control permits as required by SCDOT in order to perform the work.

11. What are the points of egress to the job site?

Via public roads, primarily SC HWY 125 (Augusta HWY) and/or US HWY 278. (All workers still need to have an SRS site Badge to work on the project.)

https://www.scdot.org/business/access-management.html mailto:Jeremy.prince@usda.gov

12. Will the site visit sign in sheet be provided?

There was not a sign in sheet for the site visit on June 9, 2025.