This is a Questions and Answers (Q&A) matrix document for USDA Forest Service solicitation 12445127B0004, containing 72 clarifications issued to bidders between October 22 and November 16, 2026. The solicitation is an Invitation for Bid (IFB) for floor repair and replacement work at the Ashe Nursery/Extractor office located at 368 Ashe Nursery Road, Brooklyn, Mississippi 39425. The work encompasses approximately 756 square feet of subfloor replacement, 594 linear feet of joist replacement, approximately 1,000 square feet of engineered oak tongue-and-groove flooring installation, complete crawlspace encapsulation with a minimum 4-mil vapor barrier, mold remediation with post-remediation clearance testing, and installation of a dedicated dehumidifier system. The applicable Davis-Bacon wage determination is MS20260048 (Forrest County, Building classification), with the Carpenter classification applying to flooring and vapor barrier installers.

The contract period is 150 calendar days from Notice to Proceed, with work hours limited to 8:00 a.m. to 4:30 p.m. Performance and payment bonds are required if the total bid price exceeds $35,000. Bidders may submit as a prime contractor with a qualified subcontractor performing the physical work; the subcontractor's experience and qualifications support the government's responsibility determination, and Standard Form 1413 must be submitted and approved before the subcontractor begins work. The government estimates the project value at approximately $45,000. No Mississippi Certificate of Responsibility is required for bids under $50,000. Bids must be submitted via email to cynthia.granderson@usda.gov by the deadline, including a signed SF-1442, acknowledgment of all amendments, and a completed Schedule of Items. Payment will be processed within 10 business days of invoice approval; weekly payroll reports must accompany each invoice. Site visits were optional, with the November 10, 2026 visit being the only scheduled walkthrough; physical inspection is not required to submit a responsive bid. The acquisition is a Total Small Business Set-Aside.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COMMENTS MATRIX FOR USDA-FS ISSUANCES:

12445127B0004 Ashe Nursery Floor Repair/Replacement

#
Class
Component and POC Name, Phone, and E-mail
Page
Para
Comment Type (C/S)
Comments, Justification, and Originator Justification for Resolution
A/R/P

Emailed 10/22/2026

Bidder Comment: Is a site visit planned, and what is the deadline for written questions?

Resolution: See Amendment 0001

Emailed 10/22/2026

Bidder Comment: Are bid, performance and payment bonds required, and at what thresholds?

Resolution: Answered is listed on page 1 (12a)

Emailed 10/22/2026

Bidder Comment: Is a Mississippi State Board of Contractors license required at time of bid or only before performance?

Resolution: The federal government doesn’t require licensing, but you must follow your state requirements

Emailed 10//22/2026

Bidder Comment: What is the estimated magnitude of the project?

Resolution: Answered is listed on page 1 (section 10)

Emailed 10/25/2026

Bidder Comment: Please confirm the physical address of the work site. The Statement of Work refers only to the "Ashe Nursery/Extractor office," without an address. Is the work to be performed at the Ashe Seed Extractory, 368 Ashe Nursery Road, Brooklyn, MS 39425, or at another location (e.g., Wiggins, MS)?

Resolution: Yes the address is accurate

Emailed 10/25/2026

Bidder Comment: Please confirm which Davis-Bacon wage determination applies to the work site. The wage determination provided with the solicitation, MS20260047 (Building, Modification 2, dated 05/18/2026), does not list Perry or Forrest County. If the site is outside the counties it covers, please provide the applicable wage determination.

Resolution: See Amendment 0002

Emailed 10/29/2026

Bidder Comment: The solicitation includes progress payments for commercial construction and payment by electronic funds transfer, but I did not find a stated Net 30, Net 60, or Net 90 term. Can you confirm the payment timing that will apply after acceptance, and whether progress payments will be made during the work, or payment only after complete installation and acceptance?

Resolution: Payments will be processed within 10 business days after receipt of an approved invoice. Payment may be made in part or in full; however, all work must be reviewed and accepted by the COR prior to payment.

Invoices should be submitted to the COR for review and approval before being uploaded into IPP. Weekly payroll reports must be submitted with each invoice.

Emailed 10/30/2026

Bidder Comment: Could you identify the insurance schedule or minimum coverage the Forest Service requires from an onsite subcontractor under FAR 52.228-5, specifically for workers' compensation and employers' liability? If a firm is exempt from state workers' compensation requirements, does this contract require coverage anyway, or what evidence of exemption would you accept?

Resolution: If contractor is exempt from state requirements, then coverage is not required.

Emailed 10/30/2026

Bidder Comment: Please also clarify whether that documentation is needed with the bid, for a representative to attend the November 10 estimating visit, or before performance.

Resolution: No documentation is needed for the November 10th site visit.

Emailed 11/02/2026

Bidder Comment: The SOW identifies widespread microbial growth and significant moisture-related wood deterioration.

Please confirm whether professional mold remediation, antimicrobial treatment, containment procedures, or post-remediation clearance testing are required as part of the contract.

Resolution: Mold & antimicrobial treatment will need to be performed.

Emailed 11/02/2026

Bidder Comment: Service Contract Labor Standards 52.222-41 and 52.222-42 are checked with a placeholder rate entry, while the construction wage clauses and Wage Determination MS20260047 (Building) also apply. Please confirm that only MS20260047 applies to all three items and tell us which classification to use for flooring and vapor barrier installers, which it does not list.

Resolution: Confirming Wage Determination MS20260048 (Building) applies and classification Carpenter will apply to flooring and vapor barrier installers

Emailed 11/02/2026

Bidder Comment: The Statement of Work lists subfloor replacement in Office 1, Office 2, Bathroom, Hallway and Conference Room at 756 SF UNVERIFIED, with 594 LF UNVERIFIED of joists, while Line 0001 says "The room is estimated to be around a 10 x 12 room". Please confirm that the Statement of Work areas and quantities govern the bid.

Resolution: Two offices, hallway, bathroom and conference room.

Emailed 11/02/2026

Bidder Comment: The Statement of Work calls for "high traffic" commercial tongue & groove planking "throughout the office", but gives no product or area, and Line 1 names only the framing, subfloor and joists. What product and area should we price, and should the planning be priced in Line 1?

Resolution: Approximately 1000SQF of flooring needs to be replaced.

Emailed 11/02/2026

Bidder Comment: Could the Government provide the required floor joist dimensions, lumber species and grade, joist spacing, subfloor thickness, and any applicable structural drawings or installation details?

Resolution: Building was constructed in 1938; joists are most likely native rough-cut lumber to that era. Subfloor possibly 1”x6” tongue and groove planking, underneath linoleum.

Emailed 11/02/2026

Bidder Comment: SF 1442 Item 11 sets completion within 150 calendar days after notice to proceed, while the continuation sheet and Amendment 0001 give a period of performance of Tue 12/01/2026 to Wed 03/31/2027. Which governs, and does the end date move if notice to proceed is issued after Tue 12/01/2026?

Resolution: The contractor has `150 days to complete the contract regardless of the date of the award

Emailed 11/02/2026

Bidder Comment: Given the extensive deterioration described in the SOW, how should contractors address additional concealed damage discovered during demolition that exceeds the specified quantities?

Would such work be handled through the contract's changes or differing-site-conditions procedures, subject to Government authorization?

Resolution: This will be addressed if the issue is presented.

Emailed 11/02/2026

Bidder Comment: Could the Government provide the approximate crawlspace dimensions and minimum specifications for the heavy-duty vapor barrier, including thickness, installation requirements, and vent sealing details?

Resolution: Vapor barrier shall minimum 4mil thickness.

Emailed 10/28/2026

Bidder Comment: The line narrative refers to a roughly 10 by 12 foot room while the scope lists 756 square feet of subfloor and 594 linear feet of joists. Which quantities and limits should bidders price?

Resolution: See number 13

Emailed 11/0/2026

Bidder Comment: The package also states 150 days after notice to proceed and December 1 through March 31; which performance period controls?

Resolution: The Period of Performance is 150 days from NTP

Emailed 11/04/2026

Bidder Comment: May ROA bid as the prime contractor under this arrangement if the qualified subcontractor performs all physical construction work?

Resolution: Yes

Emailed 11/04/2026

Bidder Comment: Does this solicitation require ROA to perform any minimum percentage or specific portion of the work with its own employees? We noted that FAR 52.219-14 is unchecked. Please identify any applicable subcontracting limitation and how it would be calculated Resolution: No

Emailed 11/04/2026

Bidder Comment: What construction experience, qualifications, and licenses must ROA hold independently as the prime? May the proposed subcontractor’s experience and qualifications support the government’s responsibility determination?

Resolution: Yes, the proposed subcontractor’s experience and qualifications support the government’s responsibility determination

Emailed 11/04/2026

Bidder Comment: May the required on-site superintendent be the subcontractor’s employee, formally authorized to act for ROA, or must that individual be directly employed by ROA?

Emailed 11/04/2026

Bidder Comment: Must ROA identify the subcontractor or submit its qualifications, licenses, commitment letter, or subcontract agreement with the bid? Is government approval required before engaging that subcontractor?

Resolution: No, you are not required to notify the Government prior to soliciting a subcontractor. However, Standard Form 1413, Statement and Acknowledgment, must be submitted and approved before the subcontractor is authorized to commence work under the contract.

Emailed 11/06/2026

Bidder Comment: Crawlspace encapsulation (Item 2): What is the square footage of the crawlspace to be encapsulated? Is it the whole building or only the area under the 756 sf of repaired floor? What is the approximate crawlspace height, and how many foundation vents need to be sealed?

Resolution: Entire crawl space shall be encapsulated.

Emailed 11/06/2026

Bidder Comment: Floor framing (Item 1): What are the existing joist size, spacing, and span? If girders, sills, or piers turn out to be rotted beyond the

594 LF of joists, will that be handled as a change under 52.236-2/52.243-5, or should bidders include an allowance?

Resolution: This will be addressed if and when the situation arises.

Emailed 11/06/2026

Bidder Comment: Finish floor: Does the "high traffic commercial tongue & groove planking" mean a finished wood plank floor (species, thickness, prefinished or site-finished?) or T&G subfloor panels? The CLIN 0001 description calls this a historical building. Must the new flooring match the existing, and is any historic-preservation review required?

Resolution: The T&G planking shall be engineered oak species, minimum thickness ½” and minimum width of 5”. Color shall compliment existing trim.

Emailed 11/06/2026

Bidder Comment: Quantity: The CLIN 0001 description mentions "around a 10 x 12 room," while the SOW lists 756 sf of subfloor and 594 LF of joists across Office 1, Office 2, the Bathroom, the Hallway, and the Conference Room. Please confirm that the SOW quantities govern.

Resolution: Previously answered

Emailed 11/06/2026

Bidder Comment: Dehumidifier: Is there an existing receptacle in the crawlspace, or should the contractor include a new dedicated circuit? Where should the condensate drain?

Resolution: Dehumidifier shall have dedicated circuit. Condensate drain shall exit the building in a way to not reenter the crawl space or building.

Bidder Comment:

Emailed 11/06/2026

Bidder Comment: Mold and hazardous materials: Is post-remediation mold clearance testing required? Is there an asbestos or lead survey for the existing flooring or mastic?

Resolution: No surveys for asbestos or lead have been performed. Post remediation mold testing is required.

Emailed 11/06/2026

Bidder Comment: SF-1442 Item 12a is marked YES. Please confirm that performance and payment bonds (52.228-15) are required within 10 days of award, and whether an irrevocable letter of credit (52.228-14) is acceptable instead.

Emailed 11/06/2026

Bidder Comment: Please confirm the bid goes by email to cynthia.granderson@usda.gov (Item 8 shows cynthia_granderson@usda.gov) with the subject "12445127B0004_I'M THE GUY, LLC_BID". Please also confirm the required documents: the signed SF-1442 (pages 1-2), the Schedule of Items, and the signed SF-30s for Amendments 0001 and 0002.

Resolution: Bid packages shall be submitted via email to cynthia.granderson@usda.gov. To be considered responsive, offerors must submit a signed SF-1442, acknowledge all amendments issued under the solicitation, and provide a completed Schedule of Items with their bid package.

Emailed 11/06/2026

Bidder Comment: Subcontracting and licensing: We plan to use a local Mississippi contractor to perform the work. Please confirm that this is acceptable. If the bid is under $50,000, we understand no Mississippi Certificate of Responsibility is required for the prime. Is that correct?

Resolution: That is correct. However, Standard Form 1413, Statement and Acknowledgment, must be submitted and approved before the subcontractor is authorized to commence work under the contract.

Emailed 11/06/2026

Bidder Comment:

Labor standards: Amendment 0002 sets Davis-Bacon WD MS20260048 (Forrest County). The package also checks 52.222-41 (Service Contract Labor Standards) and 52.222-42. Please confirm that only the Davis-Bacon WD applies.

Resolution: The Davis-Bacon WD applies.

Emailed 11/06/2026

Bidder Comment: (150 days after NTP vs. 12/01/2026-03/31/2027) and that the work site is 368 Ashe Nursery Rd, Brooklyn, MS 39425 (Item 10 says Stone County). Will the building be occupied during the work, and what are the allowed work hours?

Resolution: the contractor has 150 days from NTP the work hours will be from 8am-4:30pm

Emailed 11/06/2026

Bidder Comment: Inspection: Item 10 says that signing the SF-1442 certifies a self-guided inspection. Our local subcontractor plans to attend the November 10 visit. If they can't, may the site be inspected on another date by arrangement with Mr. Keysor?

Resolution: No

Emailed 11/08/2026

Bidder Comment: Does attendance at the November 10 visit determine whether an offeror may submit a responsive bid? If attendance is optional, will any walkthrough photos or crawlspace measurements be issued for bidders to use?

Resolution: Attendance is optional. Photos will not be provided

Emailed 11/10/2026

Bidder Comment: The SOW identifies approximately 756 square feet of subfloor replacement and 594 linear feet of floor joist replacement. Please confirm whether the contractor's fixed-price obligation is limited to these specified quantities or whether additional deteriorated structural components discovered during construction must also be included.

Resolution: Previously answered

Emailed 11/10/2026

Bidder Comment: If demolition reveals structural deterioration exceeding the specified quantities, how will the additional work be evaluated, authorized, and compensated? Would such work be addressed through a contract modification or another Government-approved procedure?

Resolution: This will be addressed if the situation arises

Emailed 11/10/2026

Bidder Comment: If existing plumbing, electrical, or HVAC systems interfere with the installation of the required crawlspace encapsulation system, please clarify whether modifications or relocation of these systems are included in the contractor's base scope or would be handled as separately authorized work.

Resolution: Modifications or relocation of the systems is included in the base scope.

Emailed 11/10/2026

Bidder Comment: Would the Government consider revising the existing Statement of Work or issuing additional clarification based on documented inspection findings that identify conditions materially different from those currently described?

Resolution: This will be addressed if the situation arises

Emailed 11/12/2026

Bidder Comment: We understand the scheduled site visit occurred on November 10, 2026. Is attendance at that visit mandatory for bid eligibility, or may contractors arrange an independent site inspection before the November 23 bid deadline?

Resolution: The site visit was optional an independent site inspection will not be scheduled

Emailed 11/12/2026

Bidder Comment: Does signing SF 1442 require bidders to have physically inspected the property, or may a bidder submit an offer based on the provided Statement of Work and solicitation documents?

Resolution: You are not required to physically inspect the property

Emailed 11/12/2026

Bidder Comment: Could you confirm the required performance and payment bond amounts? Are both bonds required regardless of the final contract award value?

Resolution: The bonding requirement applies to contracts exceeding $35,000. Yes, both the performance bond and payment bond are required.

Emailed 11/12/2026

Bidder Comment: Wage Determination: Amendment 0002 references wage determination MS20260048 for Forrest County. Could you confirm that this is the correct wage determination for the Ashe Nursery worksite in Brooklyn, Mississippi?

Resolution: Yes it is.

Emailed 11/10/2026

Bidder Comment: HVAC piping and wiring under the house

During the walkthrough we noticed a significant amount of piping and wiring under the house related to the old HVAC systems. We also saw a new HVAC system outside the project house, and we were told that the old in-floor systems would be abandoned or removed during the project.

Does the copper piping and wiring under the house need to be replaced as part of this project? Or is the new air handling system on the premises currently in operation, with the old system completely unused at this time? We want to make sure we understand whether replacing that wiring and copper piping falls within our scope so our bid is accurate.

Resolution: The new air handling system on the premises is operational. The old in floor system shall be removed.

Emailed 11/10/2026

Bidder Comment: Attachment 001, Schedule of Items

The scope of work mentions having each item priced in the schedule of items, but Attachment 001 lists only three items, which encompass the whole project. Are these three the only items that need a price, or does a detailed breakdown need to be included for each of the three items listed on Attachment 001?

Resolution: A breakdown is not required only the schedule of items attached to the solicitation

Bidder Comment: State licensing / Certificate of Responsibility: The Government's estimate is approximately $45,000. Please confirm that a Mississippi Certificate of Responsibility is not required for a bid below $50,000, and that no other state license is required for this project.

Resolution: No other license is required.

Emailed 11/11/2026

Bidder Comment: Bonds: Are bid, performance, or payment bonds required for this solicitation? If so, at what amounts?

Resolution: Yes, if your total bid price exceeds $35,000 your required to provide payment and performance

Emailed 11/11/2026

Bidder Comment: Finished flooring material: The SOW requires the contractor to prepare and install "high traffic" commercial tongue & groove planking throughout the office. Will the Government furnish that planking material, or is the contractor responsible for purchasing it? If the contractor supplies it, please provide the required product specification: material/species, thickness, width, and finish.

Resolution: Contractor shall furnish the flooring, engineered hardwood of oak species, minimum ½” thickness and minimum 5” width. Color shall complement the interior trim.

Emailed 11/11/2026

Bidder Comment: Wage determination: Please confirm that the applicable Davis-Bacon wage determination is Forrest County, MS20260048, as corrected by Amendment 0002.

Emailed 11/11/2026

Bidder Comment: Site conditions during performance: Will the building be occupied during the work? What are the permitted work days and hours, and are there protection requirements for the rest of the historic building?

Resolution: Occupancy will be minimal. Working hours and days are negotiable to accommodate.

Emailed 11/11/2026

Bidder Comment: Period of performance: Within the December 1, 2026 – March 31, 2027 window, how many calendar days will the contractor have to complete the work once started?

Resolution: The contractor will have 150 days from NTP

Emailed 11/11/2026

Bidder Comment: Measurements: Does the Government have a room-by-room breakdown of the 756 Sq Ft of subfloor replacement (Office 1, Office 2, bathroom, hallway, conference room), or any drawings or measurements available to bidders?

Resolution: Drawings have not been located to date.

Emailed 11/11/2026

Bidder Comment: Subfloor and joist specifications: What material and thickness are required for the new subfloor, and what size, species, and spacing are required for the 594 linear feet of replacement floor joists?

Resolution: Industry standard size and species to meet or exceed local and federal building codes.

Emailed 11/11/2026

Bidder Comment: Bathroom work: The bathroom is one of the affected areas. Will the contractor be required to remove and reset the toilet and other fixtures and to disconnect/reconnect plumbing in order to replace the subfloor there?

Resolution: Yes, contractor will be required to remove and reset the toilet, fixtures and disconnect/ reconnect plumbing.

Emailed 11/11/2026

Bidder Comment: Mold / microbial growth: The SOW documents widespread microbial growth. Are there any specific remediation, containment, worker-protection (PPE), or disposal requirements for the affected material?

Resolution: Mold and microbial growth shall be remediated.

Emailed 11/11/2026

Bidder Comment: Crawlspace encapsulation area: The encapsulation covers both repaired and unaffected areas. What is the total crawlspace area to be encapsulated, where are the access points, and is there an electrical source and drainage available for the permanent dehumidifier?

Resolution: There is 1 access point into the crawl space. The dehumidifiers shall be on a dedicated circuit. Drainage shall exit the crawl space in a way not to reenter the crawl space.

Emailed 11/11/2026

Bidder Comment: Furniture and contents / disposal: Will USDA remove furniture and contents from the work areas before work begins, or is that the contractor's responsibility? May the contractor place a dumpster on site, and who is responsible for disposal of the demolished material?

Resolution: Contractor may have a dumpster on site. Contractor is responsible for the disposal of said dumpster.

Emailed 10/29/2026

Bidder Comment: The solicitation includes progress payments for commercial construction and payment by electronic funds transfer, but I did not find a stated Net 30, Net 60, or Net 90 term. Can you confirm the payment timing that will apply after acceptance, and whether progress payments will be made during the work, or payment only after complete installation and acceptance?

Resolution: Payments will be processed within 10 business days after receipt of an approved invoice. Payment may be made in part or in full; however, all work must be reviewed and accepted by the COR prior to payment.

Invoices should be submitted to the COR for review and approval before being uploaded into IPP. Weekly payroll reports must be submitted with each invoice.

Emailed 11/16/2026

Bidder Comment: Will structure be empty of contents prior to work beginning?

Resolution: Yes, contractor shall provide a closed and lockable storage container. Building occupants will remove contents to place in the storage container before work begins.

Emailed 11/16/2026

Bidder Comment: If not, will contractor be responsible for providing storage unit/labor to remove contents from dwelling?

Resolution: See above question, item #62.

Emailed 11/16/2026

Bidder Comment: What type of flooring is being requested on reconstruction? Is Vinyl plank acceptable instead of sheet linoleum?

Resolution: Contractor shall furnish the flooring, engineered hardwood of oak species, minimum ½” thickness and minimum 5” width. Color shall complement the interior trim.

Emailed 11/16/2026

Bidder Comment: What millage of vapor barrier will be required?

Resolution: Minimum 4mil.

Emailed 11/16/2026

Bidder Comment: Where is vapor barrier expected to be installed? Ground, below subfloor, or between subfloor and top flooring?

Resolution: Below the subfloor.

Emailed 11/16/2026

Bidder Comment: Due to the existence of microbial growth, will remediation protocol be required for its removal? Also, will PRV air clearance sampling be required?

Resolution: Remediation protocol will be required.

Emailed 11/16/2026

Bidder Comment: What method of sealing off crawlspace vents is expected? Also, should they be sealed in front of vent (exterior) or from behind vent (in crawlspace)?

Resolution: Sealed in front of the vent.

Emailed 11/16/2026

Bidder Comment: Is there a specific dehumidifier (model/specs) expected to be installed in the crawlspace?

Resolution: Commonly available model, adequately sized for the crawl space.

Emailed 11/16/2026

Bidder Comment: What is the expectation of salvaging baseboard/floor trim in regards to stain matching pieces that cannot be removed in one piece? How close of a stain match is expected? Will there be an allowance for breakage?

Resolution: Salvage as much as possible of baseboard and trim. Replacement pieces and stain shall be matched as best possible.

Emailed 11/16/2026

Bidder Comment: What is the expectation for replacement of subfloor planking below load bearing walls?

Resolution: Replace as needed.

Emailed 11/13/2026

Bidder Comment:

Resolution:

Bidder Comment:

Bidder Comment:

Bidder Comment:

PAGE

SD FORM 818, JAN 09

PREVIOUS EDITION IS OBSOLETE

File details come from the government source that posted it. Updated .