RFQ 12441923Q0087 Amd 0001.pdf

PDF 685 KB Posted

Attached to
ORD Scull Shoals Security Fence Construction Federal contract opportunity
Solicitation number
12441923Q0087
Issued by
Department of Agriculture Forest Service

About this file

This solicitation from the Department of Agriculture Forest Service is seeking proposals for the construction of new security fencing at the Scull Shoals Historic Site located in the Chattahoochee-Oconee National Forest in Georgia. Key requirements include the removal and replacement of existing parking lot wheel stops and a warehouse perimeter fence, with proposed upgrades to tubular steel posts and rails. Offerors must provide all labor, equipment, materials, and incidentals to complete the project in accordance with specifications within a 30-day performance period following notice to proceed. Pricing is solicited for fixed-price line items encompassing mobilization, temporary traffic control, fencing components, gate installation, footings, and final clean-up. Proposals are due by the specified date and time, with evaluation weighting technical approach, experience on similar projects, and past performance references.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

12441923Q0087 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

WASHINGTON DC 20250-0001

1400 INDEPENDENCE AVE SW MS-1138

SPOC EAST

USDA FOREST SERVICE

06/26/20230001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/22/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

LIST OF CHANGES:

The purpose of this amendment is to:

1) Revise item 13b of the SF1442 to reflect a bid guarantee is not required.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

EVONNE A. HUGGINS

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

1100055

USDA FOREST SERVICE

SPOC EAST

1400 INDEPENDENCE AVE SW MS-1138

WASHINGTON DC 20250-0001

Michael Winstead

Contract Specialist michael.winstead@usda.gov

MICHAEL WINSTEAD 864-399-6465

106/22/2023

12441923Q0087

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

Attachment 1 - RFQ 12441923Q0087 Schedule of Items

Attachment 2 - Scull Shoals Maps

Attachment 3 - Continuous Fence Details

Attachment 4 - Scull Shoals Project Figures 1-10

Attachment 5 - DBA WD GA20230021

Attachment 6 - Government Furnished Information (For Reference Only)

11. The Contractor shall begin performance

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 30 calendar days and complete it within ________________ ________________ calendar days after receiving

07/07/2023

NSN 7540-01-155-3212

x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 4-85)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

X

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USDA FOREST SERVICE

SPOC EAST

1400 INDEPENDENCE AVE SW MS-1138

WASHINGTON DC 20250-0001

EVONNE A. HUGGINS

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

STANDARD FORM 1442 (REV. 4-85) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 37

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

12441923Q0087

Delivery: 30 Days After Notice to Proceed

Delivery Location Code: 435H

CHATTAHOOCHEE-OCONEE NATIONAL FORES

1755 CLEVELAND HWY

GAINESVILLE GA 30501 US

0001 ORD Scull Shoals Security Fence Construction

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation No: 12441923Q0087 ORD Scull Shoals Security Fence Construction

Table of Contents

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS*

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATION

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 TECHNICAL SPECIFICATIONS

C-5 Submittals

C-6 Personal Protective Equipment (PPE)

C-7 Basic First Aid

C-8 Final Clean-Up

C-9 Safety

C-10 Landscape Preservation

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

F.2 OTHER REQUIREMENTS

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

G.2 OTHER REQUIREMENTS

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

H.2 Loss, Damage, or Destruction

H.3 Incidental Payment Items

H. 4 Conformity With Drawings and Specifications

H.5 Samples, Tests, Cited Specifications

H.6 Barricades, Warning Signs, and Other Devices

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR

RESPONDENTS

L.1 PROVISIONS

L.2 QUOTE PREPARATION INSTRUCTIONS:

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROVISIONS

M.2 QUOTE EVALUATION

M.3 TECHNICAL EVALUATION FACTORS

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS

B.1 SCHEDULE OF ITEMS*

Item # Item Description Quantity Pay Unit

Unit Price

Total Price

1 Mobilization 1 Lump Sum

2 Temporary Traffic Control 1 Lump Sum

2 4" diameter galvanized steel continuous crossbar rails 539 LF

3 4" diameter, 5' long weld-on galvanized steel posts 111 EA

4 Removal of T-posts 35 EA

5 Removal of warehouse feature fence 1 Lump Sum

6 Removal of wood beam wheel stops 43 EA

7 5" diameter timber dome caps 44 EA

8 4" diameter galvanized steel dome caps 8 EA

9 4" diameter, 7' long weld-on galvanized steel posts 2 EA

10 6 Bar, 50" high by 12' wide heavy-duty gate (2" diameter galvanized steel) 1 EA

11 Concrete footers, 36" depth and 8" by 8" cross section (3000 psi minimum) 4.5 Cu.

Yds.

12 Treated wooden fence rails (2.5" diameter, 77- 79" long) 132 EA

13 Gate hinge kit (includes upper and lower hinges and j bolts) 1 Lump

Sum

14 Treated wooden fence posts (5" diameter, 7' long) 44 EA

15 Continuous Fence T-Posts Welding 1 Lump Sum

Total Price *In conjunction with Attachment 1 – Schedule of Items

B.2 SCHEDULE NOTES

One award will be made from this solicitation, contractors must submit pricing for all items.

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

This project is to provide construction of new security fencing for the Oconee Ranger District (ORD) in Eatonton, GA. The work will take place at the Scull Shoals Historic Site located in the Chattahoochee- Oconee National Forest (CONF).

The work shall entail the removal and replacement of the parking lot wheel-stops that currently exist and the warehouse feature perimeter fence (refer to Figure 1 in Attachment 4 – Figures 1-10 which shows work locations). The wheel-stops shall be upgraded with 4-inch galvanized steel tubing in a T-post pattern and warehouse fence shall be replaced in-kind. Also, the existing metal T-posts around the parking lot shall also be removed.

Contractor shall furnish all labor, mobilization, personnel, supervision, materials, supplies, tools, equipment, transportation, and incidentals to perform work in accordance with all terms, specifications, conditions, and provisions of this solicitation.

Period of Performance (Estimated)

Estimated Start Date: July 17, 2023 Estimated Completion Date: August 16, 2023 Contract Duration: 30 days (1 month)

C.2 PROJECT LOCATION

Work shall be performed within the Scull Shoals area located 15.5 miles southeast of Greensboro, GA;

encompassing around 45,000 acres of Forest Land. The approximate coordinates of the location are 33.733680°, -83.289299°.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

IAW with FAR 36.204(a) Disclosure of the magnitude of construction projects, the magnitude of this requirement is considered minor with an expected price range between $25,000 and $100,000.

C.4 TECHNICAL SPECIFICATIONS

Government-Furnished Information

The following documents are provided as reference via Attachment – 7 to the solicitation:

1. Cultural Resources Overview (1981)

2. Archaeological Excavations (1998)

3. Archaeological Excavations (1999)

4. Maintenance and Investigations (2011)

5. Georgia Archaeological Site Form

6. Historic Period at Scull Shoals

7. Historic Property Management Plan

8. Scull Shoals Historic Area Interpretive Plan

9. Scull Shoals Historic Photos

Disclaimer: The Forest Service expressly denies any responsibility for the accuracy or completeness of the information. The firm will not be entitled to any extra compensation on account of any inaccuracy or incompleteness of the given information, which is provided only as a convenience for firm.

CONCRETE MIXES AND MIXING

A. Concrete Mixes for footers: Prepare design mixes, proportioned according to ACI 211.1 and ACI 301, with the following properties:

1. Minimum Compressive Strength (28 Days): 3,000 psi.

2. Maximum Water-Cementitious Materials Ratio: 0.45.

3. Slump Limit: 3-5 inches.

4. Air Content: 4.5 to 7.5 percent.

B. Ready-Mixed Concrete: Comply with requirements and with ASTM C 94 and ASTM C 1116, with

2012 IBC.

Field Quality Control

• Testing and Inspecting: Contractor shall engage a qualified independent testing and inspecting agency to perform concrete testing.

C-5 Submittals

Submittals shall include the following unless otherwise required:

1. Date and revision dates.

2. Project name and contract number.

3. Names of Contractor, subcontractor, supplier, and manufacturer.

4. Referenced by contract clause.

5. Field dimensions and relation to adjacent structures.

6. Applicable standards such as ASTM or Federal Specifications.

7. Contractor's stamp, initial or signature, certifying the review of submittal, verification of field measurements and compliance with contract documents. Provide all submittals within 7 calendar days of contract award unless otherwise required by the specification.

The following submittals are required for this contract as appointed by Contracting Officer (CO):

Title Referenced by Contract Clause or Specification No.

Time of Government Approval After Submittal

Designated Point of Contact (POC) Required Before Work Commence Safety Plan, including Blasting Plan

Accident prevention clause [FAR 52.236-13] 7 Days

Hazardous Spill Plan Required 7 Days Fire Plan and Certification that your Fire Tools and Equipment are fully operational Required Before Work Commence

Proposed Progress Schedule

Schedules for construction contracts [FAR 52.236-15] Before Work Commence

Designation of Representative

Superintendence by the contractor [FAR 52.236-6] Pre-work meeting

Drug Free Workplace Policy Drug-free workplace [FAR 52.223-6] Before Work Commence

Payroll Record WH347 Certified Payrolls submitted weekly

Payrolls And Basic Records [FAR 52.222-8] Attach w/ invoicing

Product and Material Certifications and Literature Required 7 Days Contractor Quality Control Plan Required 7 Days

Concrete mix design Required [ACI 211.1 and ACI 301] 7 Days

Concrete Inspector/Tester Required 7 Days

SF1413 Statement and Acknowledgment

When using subcontractors [52.222-11 Subcontracts (Labor Standards)] Within 14 days after award

MATERIAL CERTIFICATIONS SUBMITTAL

The following certificates shall be submitted on this report . See AGAR section 452.236-76 for timely submittal and approval by Contracting Officer.

The following material certifications and/or testing reports shall be submitted on this project:

Title Referenced by Specification No.

Material Certifications of all fencing materials, nails, posts, concrete, gate(s), braces etc. Per manufacture and supplier

C-6 Personal Protective Equipment (PPE)

1. The contractor will train all employees in the safe operation and use of equipment that is to be used in the performance of this contract.

2. Personal protective equipment, including personal protective equipment for eyes, face, head, hands, and extremities shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards or processes encountered in a manner capable of causing injury or impairment in the function of any part of the body.

3. Defective or damaged personal protective equipment shall not be used.

4. The contractor shall assure that each employee wears foot protection that provides adequate traction, ankle support, and enclosed toe area.

5. The contractor shall provide, at no cost to the employee, and assure that each employee who works in an area where there is potential for head injury from falling objects or flying objects wears a hard hat that meets the minimum requirements of American National Standards Institute (ANSI) standard Z89.1-1997.

6. The contractor shall provide, at no cost to the employee, eye protection where there is potential for eye injury due to flying objects. This eye protection must meet the minimum requirements of ANSI standard Z87.1-2003.

7. The contractor shall provide, at no cost to the employee, hearing protection where there is a potential for hearing loss due to high intensity noise.

C-7 Basic First Aid

1. Basic first aid supplies shall be maintained, available and under the charge of the person using motorized equipment. The supplies shall include supplies that are commonly found in a standard First Aid Kit, such as the type found for camping use or carried in motor.

C-8 Final Clean-Up

Before final acceptance of work, all areas occupied by the Contractor in connection with the work shall be cleaned of all contractor’s rubbish, excess materials, temporary structures, and equipment, tools, and all parts of the work area shall be left in a neat and presentable condition.

C-9 Safety

Before work commence the Contractor shall present a Safety Plan that addresses the hazards associated with the requirements of project and per OSHA standards.

C-10 Landscape Preservation

(a) The Contractor shall confine operations to within the clearing limits or other areas designated in contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Material, which falls outside of these limits, shall be retrieved, disposed of, or incorporated in the work as directed by the Contracting Officer.

(b) Operation shall be scheduled and conducted to minimize erosion of soils and to prevent silting and muddying of streams, rivers, irrigation systems, and impoundments (lakes, reservoirs, etc.).

Pollutants such as fuels, lubricants, bitumen, raw sewage, and other harmful materials shall not be discharged into or near rivers, streams, and impoundments or into natural or manmade channels leading thereto. Wash water or wastewater from concrete or aggregate operations shall not be allowed to enter live streams prior to treatment by filtration, settling, or other means sufficient to reduce the sediment content to not more than that of the stream into which it is discharged.

Mechanized equipment shall not be operated in live streams without written approval by the Contracting Officer.

452.211-73 Attachments to Statement of Work/Specifications (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

SECTION D--PACKAGING AND MARKING

D.1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D.2 PROJECT LABELING FOR OFFICIAL CORRESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.242-14 Suspension of Work (APR 1984)

52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 days after receipt of NTP. The time stated for completion shall include final cleanup of the premises.

F.2 OTHER REQUIREMENTS

N/A

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 CLAUSES

452.215-73 Post Award Conference (NOV 1996) A post award conference with the successful offeror is required. It will be scheduled and held within 5 days after the date of contract award. The conference will be held at the work site.

G.2 OTHER REQUIREMENTS

N/A

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 CLAUSES

452.236-77 Emergency Response (NOV 1996)

(a) Contractor’s Responsibility for Fire Fighting.

(1) The Contractor, under the provisions of FAR clause 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work.

(2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor’s agents or employees.

(b) Contractor’s Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor’s Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to firefighting). An equitable adjustment for the temporary use of employees and equipment will be made under the Changes Clause, FAR 52.243-4.

452.237-74 Key Personnel (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel. Note: Individuals serving in more than one of the roles listed below may be listed more than once:

Role/Function Name

Project Manager

Individual with the authority to obligate the contractor financially and sign contract documents on behalf of the contractor as needed.

Quality Control:

Any other key individuals the contractor deems necessary to complete the project successfully (e.g., Lead Engineer, Site Leads, etc.). Please use space below table to list additional personnel as needed.

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H.2 Loss, Damage, or Destruction

(a) Equipment furnished with operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

All claims arising under this clause will be submitted to the Contracting Officer.

H.3 Incidental Payment Items

The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.

H. 4 Conformity With Drawings and Specifications

Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground.

"Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.

H.5 Samples, Tests, Cited Specifications

Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.

H.6 Barricades, Warning Signs, and Other Devices

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness.

Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) FAR and AGAR Deviations to clauses may be viewed at: Policies & Regulations | USDA

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) 52.204-13 System for Award Management Maintenance (OCT 2018) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services or Equipment (NOV 2021) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (NOV 2021) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.222-3 Convict Labor (JUN 2003) 52.222-6 Construction Wage Rate Requirement (AUG 2018) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (JUL 2021) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY

2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (APR 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) 52.222-50 Combating Trafficking in Persons (NOV 2021) 52.222-55 Minimum Wages for Contractor Workers under Executive Order 14026 (JAN 2022) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar https://www.usda.gov/da/ocp/ppd/policies-regulations

52.222-62 Paid Sick Leave under Executive Order 13706 (JAN 2022) 52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) 52.225-13 Restrictions on Certain Foreign Purchases (FEB 2021) 52.226-1 Utilization of Indian Organizations and Indian-Owned Economic Enterprises (June 2000) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes (MAY 2014) Alt 1 (DEC 1991) 52.233-3 Protest after Award (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004) 52.236-2 Differing Site Conditions (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984) 52.236-5 Material and Workmanship (APR 1984) 52.236-7 Permits and Responsibilities (NOV 1991) 52.236-17 Layout of Work (APR 1984) 52.243-5 Changes and Changed Conditions (APR 1984) 52.244-6 Subcontracts for Commercial Products and Commercial Services (MAR 2023) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (APR 1984) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991) 452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996) 452.236-72 Use of Premises (NOV 1996) 452.236-73 Archaeological or Historic Sites (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution (NOV 1996) 452.236-76 Samples and Certificates (FEB 1988) 452.236-77 Emergency Response (NOV 1996)

52.225-9 Buy American Act-Construction Materials (OCT 2022)

(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety https://www.acquisition.gov/far/part-2#FAR_2_101 systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.

supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together.

Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the https://www.acquisition.gov/far/part-25#FAR_25_105 manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. Chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None .

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.

(A) For domestic construction material that is not a critical item or does not contain critical components.

(1) The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;

(2) For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.

(B) For domestic construction material that is a critical item or contains critical components.

(1) The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.

(2) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/part-12#FAR_12_505 offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.

(3) The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1) (i)Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison Construction Material Description Unit of Measure Quantity Price (Dollars)* Item1

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______ Item 2

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued)].

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] (End of clause)

52.228-11 Individual Surety - Pledge of Assets (FEB 2021) (DEVIATION APR 2020)

(a) The Contractor shall obtain from each person acting as an individual surety on a performance bond or a payment bond -

(1)A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203-1; and

(2) Standard Form 28, Affidavit of Individual Surety, [except that the words “being duly sworn, depose and say” on the Standard Form 28 are replaced with the word “affirm” and the Standard Form 28 is not required to be sworn and notarized in block 12].

(b)The Contracting Officer may release a portion of the security interest on the individual surety's assets based upon substantial performance of the Contractor's obligations under its performance bond. The security interest in support of a performance bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 (40 U.S.C. 3131). Until completion of any warranty period, or for 1 year following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (b)(1) of this clause. Until completion of any warranty period, or for 90 days following final payment, whichever is later.

(c) A surety's assets pledged in support of a payment bond may be released to a subcontractor or supplier upon Government receipt of a Federal district court judgment, or a sworn statement by the subcontractor or supplier that the claim is correct along with a notarized authorization of the release by the surety stating that it approves of such release. The security interest on the individual surety's assets in support of a payment bond shall be maintained—

(1) Contracts for the construction, alteration, or repair of any public building or public work of the Federal Government exceeding $150,000 which require performance and payment bonds (40 U.S.C.

3131). For 1 year following final payment, or until resolution of all pending claims filed against the payment bond during the 1-year period following final payment, whichever is later.

(2) Contracts subject to alternative payment protection (see FAR 28.102-1(b)(1)). For the full contract performance period plus 1 year.

(3) Other contracts not subject to the requirements of paragraph (c)(1) of this clause. For 90 days following final payment.

(d)The Contracting Officer may allow the Contractor to substitute an individual surety, for a performance or payment bond, after contract award. The Contractor shall comply with the requirements of paragraph

(a) of this clause within the timeframe established by the Contracting Officer.

52.228-13 Alternative Payment Protections (JUL 2000)

(a) The Contractor shall submit one of the following payment protections

(i) A payment bond,

(ii) An irrevocable letter of credit (ILC).

(b) The amount of the payment protection shall be 20 percent of the contract price.

(c) The submission of the payment protection is required within 10 days of contract award.

(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.

https://www.usda.gov/sites/default/files/documents/far-class-deviation-eliminate-hard-copy.pdf https://www.acquisition.gov/far/part-28#FAR_28_203_1

(e) Except for escrow agreements and payment bonds, which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.

(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.

52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) (DEVIATION MAY 2023) (a)Definitions.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .