Attachment 1 - Statement of Work - Elkhorn Trail Bridge (10 Pages).pdf

PDF 349 KB Posted

Attached to
Elkhorn Trail Bridge
Solicitation number
1240LP27Q0002
Issued by

About this file

This is a Statement of Work (SOW) for the design, manufacture, and delivery of a prefabricated fiber-reinforced polymer (FRP) trail bridge for the USDA Forest Service, Hahns Peak/Bears Ears Ranger District in Colorado. The supplier must deliver an 85-foot single-span, 5-foot clear width FRP side-truss pedestrian/ATV/stock trail bridge designed for the Elkhorn Trail crossing over the Little Snake River near Hahns Peak Village, Colorado. The bridge must be designed by Load and Resistance Factor Design (LRFD) methodology with stamped drawings and calculations from a Colorado-licensed engineer, submitted 30 days prior to fabrication for approval by Forest Service Regional engineering. The delivery location is the Columbine Parking Area (40.8711°N, 106.9390°W) at approximately 8,000 feet elevation, subject to severe winter conditions with snow typical from November through May.

The supplier must comply with AASHTO LRFD Guide Specifications for FRP Pedestrian Bridges (2nd Edition, 2025), ASCE Pre-Standard for LRFD of Pultruded FRP Structures (2010), ASCE 7 Standards, and USDA Forest Service Trail Fundamentals standards. The manufacturer must demonstrate minimum five years' experience in FRP trail bridge systems, hold ISO 9001:2015 accreditation, provide a 15-year material warranty, and furnish examples of at least five installations in service for three years minimum. All bridge components, fasteners, railings, deck elements, and accessories must be supplied by the same manufacturer. The supplier bears responsibility for transportation coordination, weight calculations for helicopter or ground delivery, all permits and licenses, environmental protection, waste management, and liability for any property damage. Delivery must occur between May 15, 2027 and June 30, 2027 (weather dependent), with work hours restricted to 8:00 AM to 4:30 PM Mountain Daylight Time, Monday through Friday, excluding weekends and federal holidays. The supplier must provide 48-hour advance notice of personnel arrival and 14 days' advance notice of any public access disruptions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEDICINE BOW-ROUTT NATIONAL FOREST &

THUNDER BASIN NATIONAL GRASSLAND

HAHNS PEAK/BEARS EARS RANGER DISTRICT

LITTLE SNAKE RIVER – ELKHORN

TRAIL BRIDGE

STATEMENT OF WORK

April 16, 2026

Contents Project and Summary

General Information

1.0 Background

2.0 Location, Site Conditions, and Weather

3.0 Use of Premises

4.0 Scope of Work

Supplier Requirements

5.0 General Requirements

6.0 Products

7.0 Execution

Additional Requirements

8.0 Deliverables/Performance Period

9.0 Travel, Meals, & Lodging

10.0 Security and Safety Requirements/Hours of Operation

11.0 Emergency Response

12.0 Definitions

Attachments

Project and Summary Hahns Peak/Bears Ears Ranger District, Little Snake River - Elkhorn Trail Bridge.

This project consists of supplying a new trail bridge for the Elkhorn Trail crossing over the Little Snake River located on the Hahns Peak/Bears Ears Ranger District near Hahns Peak Village, CO. This work includes supplying a new 85.0-ft long, 5-ft clear width, single-span fiber-reinforced polymer (FRP) side truss pedestrian/ATV/stock trail bridge to a location near the project site. The design of the new bridge with respect to the river channel and trail crossing is attached to the appendices. The Supplier shall be responsible for providing designs of the new bridge stamped by a licensed engineer in the state of Colorado and approved by the USDA Forest Service Regional (or equivalent) structural engineering team. The replacement bridge shall have a color approved by Forest Service leadership.

Any damage to Forest Service property/infrastructure resulting from the delivery shall be the Supplier’s responsibility. All work shall adhere to industry standards, code requirements, and manufacturer recommendations.

Specifications and requirements are summarized in the body of this statement of work and attached plans. However, a more comprehensive list of specifications can be found in Appendix V. Where conflicting information occurs, the correct specification or requirement will be determined by the CO. The order of precedence for conflicting information is that this statement of work (SOW) has the highest priority, then the plans, then the specifications.

General Information

1.0 Background

Within the Medicine Bow-Routt National Forest & Thunder Basin National Grassland (MBRTB), on the northern end of the Hahns Peak/Bears Ears Ranger District, the 15.8-mile-long Elkhorn Trail runs from National Forest System Road (NFSR) 500.1D, “Little Red,” to the state line between Colorado and Wyoming. The existing trail bridge is physically located at mile marker 9.8 from the southern trailhead. The delivery location for the components of the new bridge will be the following:

- 40.8711°N, 106.9390°W – Columbine Parking Area

2.0 Location, Site Conditions, and Weather

The altitude of the delivery location is approximately 8,000 feet above mean sea level. The area experiences snowfall and rain and extremely cold temperatures, with snow on the ground typically from November through May.

3.0 Use of Premises

3.1 Use of Site: The Contracting Officers Representative (COR) will designate a material delivery area with flagging.

Limit delivery to areas indicated. Do not disturb portions of delivery site beyond areas in which the Work is indicated.

3.1.1 Limits: Confine delivery operations to the project site and defined delivery area.

3.1.2 Roads and Entrances: Keep roads and parking areas serving the delivery site always clear and available to the public, Government employees, and emergency vehicles. Do not use unauthorized areas for parking or unloading.

A. Schedule deliveries to minimize use of parking areas and roads.

B. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

3.2 Occupancy Requirements

3.2.1 Supplier (including supplier employees and subcontractors) shall always conduct their operations to ensure the least inconvenience to the public and employees.

3.2.2 Confine storage of materials to areas approved by the Contracting Officer (CO).

3.2.3 Preservation of Natural Features: Confine all operations to delivery limits. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

A. Provide temporary barriers to protect existing trees and plants and root zones at delivery site, if deemed necessary by COR.

4.0 Scope of Work

4.1 The Supplier shall:

4.1.1 Design, manufacture, and deliver all components to construct an 85-foot single span prefabricated fiber-reinforced polymer (FRP) side-truss trail bridge for pedestrian, bicycle, ATV, and pack & saddle use, in addition to specifications provided by the attached Trail Management Objectives (TMOs). The supplier is responsible for coordinating the weight of the various bridge components for transport by helicopter or acquiring overload permits for forest bridges used for ground transportation, if needed.

4.1.2 Perform all work in compliance with the contract documents and design bridge in accordance with attached TMOs for NFS Trail #1149.1 - Elkhorn. Work includes but is not limited to fabrication and delivery of a new bridge as per this statement of work and the attached plans/specs.

4.1.3 Acquire prior notification and approval from the COR and CO for any detours or disruptions to public access. The Supplier must obtain this approval for a minimum of 14 days prior to any disruptive action.

4.1.4 Design the bridge by Load and Resistance Factor Design (LRFD) with the loading described in the project drawings, as described in the specifications. Stamped drawings and calculations are to be provided 30 days prior to planned fabrication for approval. The drawings must be stamped by an engineer licensed in the state of Colorado. Electronic submittals are permitted.

Supplier Requirements

5.0 General Requirements

5.1 General

5.1.1 This project requires the Supplier to supply all labor, materials, equipment, tools, transportation, freight and delivery, and all necessary licenses and permits required to complete the project in accordance with the provisions of this contract/statement of work (SOW). This project will be completed under a single supply contract and shall be performed in accordance with all applicable OSHA and U.S. Forest Service safety regulations. The Supplier shall be responsible for obtaining all Local, State and Federal permits as necessary.

5.1.2 The Supplier will provide all components required for a complete trail bridge system, to include all substructure-superstructure interface components, superstructure elements, railings, deck, associated fasteners, closures, sealants, fillers, and any other required items.

5.1.3 The Supplier shall take necessary safety measures to protect employees and the public during transportation/unloading.

5.2 Quality Assurance

5.2.1 Applicable Standards Not Listed in the Little Snake River – Elkhorn Trail Bridge Project Specifications or

Elkhorn Trail Bridge Replacement Plans A. AASHTO LRFD Guide Specifications for the Design of FRP Pedestrian Bridges, 2nd Edition, 2025;

B. ASCE Pre-Standard for Load & Resistance Factor Design (LRFD) of Pultruded Fiber Reinforced Polymer

(FRP) Structures, 2010;

C. All other loading/structural design criteria shall meet or exceed ASCE 7 Standards;

D. USDA FS 1623–3801–MTDC Trail Fundamentals and Trail Management Objectives, 2016 E. All applicable Federal, State, and County Codes and regulations.

5.2.2 Manufacturer’s Qualifications

A. Manufacturer shall have a minimum of five years’ experience in manufacturing FRP trail bridge systems, ISO 9001:2015 accreditation, be able to provide a 15-year material warranty and provide examples of at least 5 successful installations each in service at least 3 years.

5.2.3 System Performance Requirements

A. For details on requirements, refer to Forest Service Handbook 7709.56b Section 82.2 – Design, the attached Little Snake River – Elkhorn Trail Bridge Project Specifications, and the attached Elkhorn Trail Bridge Replacement Plans

5.2.4 Design Requirements in Addition to Attached Plans/Specifications A. General

1. The bridge shall be designed by the Manufacturer as a complete system. Members and connections not indicated on the drawings shall be the responsibility of the Supplier. All components of the system shall be supplied or specified by the same manufacturer.

B. Design Loads

1. Design load applications shall be in accordance with the attached plans and specifications.

2. Reduction of live loads for deck influence areas exceeding 400 square feet is consistent with the provisions of ASCE 7-89, Minimum Design Loads for Buildings and Other Structures, and is intended to account for the reduced probability of large influence areas being simultaneously maximum loaded. For typical bridges, a single design live load value may be computed based on the full deck influence area and applied to all the main subcomponents. Designing decks for a small, concentrated load (for example 1 kip) is required to account for equestrian use, ATVs, or snowmobiles.

3. The proposed AASHTO vehicle loads are intended as default values in cases where the Operating Agency does not specify a design vehicle. The bridge shall be designed to accommodate a 50”, 1000-lb all-terrain vehicle (ATV) to conservatively represent specified weight for a design vehicle.

4. Wind design speed, ultimate: 115 miles per hour (MPH), Exposure C. A wind load of the following intensity shall be applied horizontally at right angles to the longitudinal axis of the structure. The wind load shall be applied to the projected vertical area of all superstructure elements, including exposed truss members on the leeward truss.

For trusses and arches: 75 PSF (3.59 KPa) For girders and beams: 50 PSF (2.39 KPa)

A wind overturning force shall be applied according to Article 3.15.3 of the Standard Specifications for Highway Bridges;

5. Thermal effects: Bridge components shall be free to move in response to the expansion and contraction forces resulting from temperature variation.

6. The load combinations, i.e., allowable stress percentages for service load design and load factors for load factor design as specified in table 3.22.1A of the Standard Specifications for Highway Bridges, shall be used with the following modifications:

Wind on live load, WL, shall equal zero Longitudinal force, LF, shall equal zero

C. Design Details

1. Connections - Under this specification, bolted connections shall be used for all main and secondary members. Use only galvanized or stainless-steel bolts based on approval by the owner.

Adhesive bonding can be used in conjunction with bolted connections for all main members and secondary members. Non-structural members can be either bolted/screwed or adhesively bonded. Adhesive bonding alone is not acceptable due to the lack of testing done to date in this area. Adhesive bonding can be used in conjunction with bolted connections for all main members and secondary members to provide additional redundancy within the bridge system.

2. Half-Through Truss Spans

a. The vertical truss members of the floor beams and their connections in half-through truss spans shall be proportioned to resist a lateral force applied at the top of the truss verticals that is not less than 0.01/K times the average design compressive force in the two adjacent top chord members where K is the design effective length factor for the individual top chord members supported between the truss verticals. In no case shall the value for 0.01/K be less than 0.003 when determining the minimum lateral force, regardless of the K-value used to determine the compressive capacity of the top chord.

This lateral force shall be applied concurrently with these members' primary forces. End posts shall be designed as a simple cantilever to carry its applied axial load combined with a lateral load of 1.0% of the axial load, applied at the upper end.

b. The top chord shall be considered as a column with elastic lateral supports at the panel points. The critical buckling force of the column so determined shall be based on using not less than 2.0 times the maximum design group loading in any panel in the topchord.1 Maximum design group loading is based on the design loads (not sustained) specified in Design Loads in this Specification.

c. For sustained snow loads (duration of load a minimum of 3 days) greater than 65 PSF (3.11 KPa), the critical buckling force of the column so determined shall be based on using not less than 3.0 times the maximum design group loading in any panel in the top chord. This increased factor will account for any adverse viscoelastic behavior (creep buckling) that potentially could occur in the bridge system.

5.2.5 Submittal Requirements

A. Installation Drawings

1. Submit completed bridge design drawings and assembly/installation details by the manufacturer to MBRTB Engineering for review. Do not proceed with manufacture prior to review and MBRTB Engineering approval of drawings.

2. Product Data: Provide electronic submittals for the following materials:

a. Components of Bridge Superstructure, Deck, Rails, and Accessories

b. Fasteners

3. Design drawings and installation details shall show methods of installation, elevations and plans of bridge, sections and details, specified loads, sealants, and interfaces with all materials not supplied by the system manufacturer, as well as proposed identification of component parts and their finishes.

B. Color Samples

1. Submit color photos for all proposed finishes.

5.2.6 Product Delivery, Storage, and Handling

A. Delivery

1. Deliver bridge system to job site properly packaged to provide protection against transportation damage.

B. Handling

1. Exercise care in unloading and storing bridge system to prevent bending, warping, twisting and surface damage.

C. Storage on Delivery

1. Store all material and accessories above ground on well supported platforms. Store under waterproof covering. Provide proper ventilation of bridge system to prevent condensation build-up between each panel or trim/flashing component.

5.2.7 Supplier Responsibilities and Construction Administration

A. The Supplier shall coordinate with the Contracting Officers Representative (COR) no less than seven (7) calendar days prior to the estimated project start date;

B. The Supplier shall provide the Contracting Officers Representative (COR) an estimated delivery schedule no less than seven (7) calendar days prior to the estimated delivery date;

C. The Supplier shall take precautions to protect all materials during the delivery period. The Supplier shall be responsible for any loss of or damage to the structure, accessories, and/or fixtures occurring during the performance of work specified in the contract/SOW;

D. No dumping of waste products of any type will be permitted. All waste shall be transported to an approved sanitary landfill. At the completion of the work, the Supplier shall remove its tools, construction equipment, machinery, and surplus material, and shall properly dispose of waste materials.

E. Burning will not be permitted at the delivery site(s).

5.2.8 Warranty Requirements

A. The Supplier shall warranty all parts and materials for a minimum of fifteen (15) years from the date of work completion;

B. When remediation, correction or replacement is required, transportation charges and responsibility for the parts or materials, shall be borne by the Supplier;

C. Any parts or materials thereof, furnished for the purposes of remediation, correction, or replacement under this contract/SOW, shall also be subject to the terms of this contract/SOW to the same extent as parts or material initially installed. The warranty, with respect to parts or materials thereof, shall be equal in duration to the original terms and shall run from the date of installation of the remediated, corrected, or replaced parts or materials.

6.0 Products

6.1 Materials

A. Materials are indicated on the plans and specifications provided in the Appendix.

6.2 Fabrication

6.2.1 Fabrication requirements are detailed in the plans and specifications provided in the Appendix.

6.2.2 Fabricate accessories to Manufacturer’s specified profiles.

6.2.3 Minimum Thickness of FRP:

6.2.3.1 Minimum thickness of closed structural tubular members shall be 0.25 inch (6.4 mm)

6.2.3.2 Minimum thickness of open structural FRP members shall be 0.375 inch (9.6 mm)

6.2.3.3 Plate connections also require a minimum thickness of 0.375 inch (9.6 mm)

7.0 Execution

7.1 Discrepancies

A. In event of discrepancy or unforeseen site conditions arise, notify the CO or the COR;

B. The Supplier shall not proceed with fabrication until discrepancies have been resolved.

7.2 Cleaning and Protection

7.2.1 Protect material against damage until delivery acceptance. Replace or repair to the satisfaction of the CO and COR, any material that becomes damaged prior to final acceptance.

Additional Requirements

8.0 Deliverables/Performance Period

8.1 Deliverables

8.1.1 The Supplier shall complete the bridge design, manufacture, and delivery in accordance with the specifications and requirements as directed in this contract/SOW.

8.2 Performance Period

8.2.1 The Supplier shall deliver all bridge components no earlier than May 15, 2027 and no later than June 30, 2027 (weather dependent)

9.0 Travel, Meals, & Lodging

9.1 The Supplier is responsible for all aspects of travel and billeting for its employees and subcontractors.

9.2 Meals and lodgings are commercially available in Hahns Peak Village, CO, and Encampment, WY. Meals or lodging will not be available at Forest Service facilities.

9.3 Camping on Government property is strictly prohibited without prior authorization.

10.0 Security and Safety Requirements/Hours of Operation

10.1 Security and Safety Requirements

10.1.1 It shall be the Supplier’s responsibility to provide for safety within the delivery area. This includes protection for employees, subcontractor personnel, government personnel and the public.

10.1.2 Access: The Supplier shall notify the COR and the Hahns Peak/Bears Ears Ranger District 48 hours in advance (or as soon as possible) when Supplier personnel (including subcontractors) are to arrive.

10.1.3 Weapons: No weapons of any kind are allowed at the delivery site either in vehicles or on persons.

10.2 Delivery Sequence

10.2.1 This project shall be completed within the time frame established by the terms of this contract and according to the approved Schedule of Work.

10.2.2 Hours of Operation: The Supplier shall deliver products during regularly scheduled work hours of 0800 (8:00 AM) to 1630 (4:30 PM) Mountain Daylight Time (MDT), Monday through Friday, excluding weekends and observed Federal holidays.

10.2.3 All work shall be scheduled and carried out in such a manner as to minimize conflicts with and disturbance of adjacent landowners. Activities shall be scheduled to minimize disturbance of traffic along NFSR 550.1. All warning signs, barricading, and other necessary items shall conform to the following references:

A. Little Snake River – Elkhorn Trail Bridge Replacement Specifications: Traffic Control Signs B. “Manual of Uniform Traffic Control Devices” (MUTCD); Federal Highway Administration; 2003.

10.2.4 The Supplier shall notify the CO 48 hours prior to any traffic interruptions.

11.0 Emergency Response

11.1 Supplier's Responsibility for Fire Fighting.

11.1.1 The Supplier, under the provisions of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish all fires on the delivery site.

11.1.2 The Supplier may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Supplier or the Supplier's agents or employees.

12.0 Definitions

12.1 Contracting Officer (CO): The Contracting Officer is the Government official with the authority to enter, administer, and/or terminate contracts, and make related determinations and findings (Acquisition.gov). The contracting officer has the final say in any perceived discrepancies within the contract.

12.2 Contracting Officers Representative (COR): The Contracting Officers Representative is an individual designated and authorized in writing by the Contracting Officer to perform specific technical and administrative functions (Acquisition.gov).

12.3 Statement of Work (SOW): The SOW details what the Supplier must do in the performance of the contract.

Documentation developed under the contract, for example, is specified in the SOW. Security assurance requirements, which detail many aspects of the processes the Supplier follows and what evidence must be provided to assure the organization that the processes have been conducted correctly and completely, may also be specified in the SOW.

12.4 Acceptance: Acceptance means the act of an authorized representative of the Government by which the Government assumes for itself, or as an agent of another, ownership of existing supplies, or approves specific services as partial or complete performance of the contract.

12.5 Supplies: Supplies means the end items furnished by the Supplier and related services required under this contract.

12.6 Defect: Defect means any condition or characteristic in any supplies or services furnished by the Supplier under the contract that is not in compliance with the requirements of the contract.

12.7 Lump Sum Quantity (LSQ): One complete unit of work, which may consist of one or more work items necessary to complete the task. In addition to LSQ, payments shall be by units defined and determined according to U.S. Standard measure.

12.8 Square Foot. A 1-foot by 1-foot area. Make longitudinal and transverse measurements for area computations horizontally. Do not make deductions from the area computation for individual exclusions having an area of 1 square foot or less.

12.9 Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

12.10 Each: One complete unit, which may consist of one or more parts.

12.11 Linear Foot: Linear feet measured horizontally.

Attachments

ATTACHMENT NO. TITLE

1. Appendix I: Vicinity Map – Little Snake River – Elkhorn Trail Bridge Project

2. Appendix II: Little Snake River – Elkhorn Trail Bridge Plans

3. Appendix III: Little Snake River – Elkhorn Trail Bridge Project Specifications

4. Appendix IV: ASCE Design Hazards Report

Project and Summary
General Information
1.0 Background
2.0 Location, Site Conditions, and Weather
3.0 Use of Premises
4.0 Scope of Work
Supplier Requirements
5.0 General Requirements
6.0 Products
7.0 Execution
Additional Requirements
8.0 Deliverables/Performance Period
9.0 Travel, Meals, & Lodging
10.0 Security and Safety Requirements/Hours of Operation
11.0 Emergency Response
12.0 Definitions