This document is a Question & Answer amendment for Solicitation 1240BJ24Q0011 - Primrose Trail Structures Construction, issued by the U.S. Department of Agriculture Forest Service.

The amendment clarifies that contractors will not be required to provide temporary crossings for trail traffic during construction, and the trail can be closed to through traffic. It also states that if the conceptual boardwalk design requires significant changes that impact the pricing, a contract modification will be executed. The solicitation is for the construction of Primrose Trail structures on the Tongass National Forest. The cut-off for pre-bid questions is August 26, 2024 by 5:00 PM AKDT, and offerors must respond as described in Sections L and M of the solicitation. Proposals that fail to provide a complete technical response may be rejected.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question & Answer

1240BJ24Q0011 – Primrose Trail Structures Construction, Amendment 1

Question Response

Did this change the solicitation?

1. We will not be required to provide temporary crossings for trail traffic at any of the locations during construction, and the trail can be closed to through traffic.

Yes this is correct.

No

2. The boardwalk is drawn as conceptual and requires a third party engineers stamp. Can I assume if this causes any significant changes in design/materials/etc. from what is currently drawn, that pricing can be adjusted accordingly?

Yes, if there is a substantial change from what is shown on the a modification will be executed.

No