Amendment 1_1240BJ24Q011_RFI.pdf

PDF 87 KB Posted

Attached to
Primrose Trail Structures Construction Federal contract opportunity
Solicitation number
1240BJ24Q0011
Issued by
Department of Agriculture Forest Service

About this file

This document is a Question & Answer amendment for Solicitation 1240BJ24Q0011 - Primrose Trail Structures Construction, issued by the U.S. Department of Agriculture Forest Service.

The amendment clarifies that contractors will not be required to provide temporary crossings for trail traffic during construction, and the trail can be closed to through traffic. It also states that if the conceptual boardwalk design requires significant changes that impact the pricing, a contract modification will be executed. The solicitation is for the construction of Primrose Trail structures on the Tongass National Forest. The cut-off for pre-bid questions is August 26, 2024 by 5:00 PM AKDT, and offerors must respond as described in Sections L and M of the solicitation. Proposals that fail to provide a complete technical response may be rejected.

View the file

Other files for this federal contract opportunity

Other files attached to Primrose Trail Structures Construction, newest first.
File Type Posted
Amendment 1_1240BJ24Q0011_SF30.pdf PDF
Trail Design Parameters.pdf PDF
Staging Area Arieal Image.pdf PDF
PRIMROSE TRAIL STRUCTURE CONSTRUCTION DRAWINGS.pdf PDF
Specifications Primose Trail Reconstruction.pdf PDF
Primrose SOW_struct_rev_02_01.pdf PDF
Primrose Existing Conditions Photos.pdf PDF
Wage Determination AK20240002 01.05.2024.pdf PDF
1240BJ24Q0011 Solicitation Packet.pdf PDF
Primrose Work Log.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question & Answer

1240BJ24Q0011 – Primrose Trail Structures Construction, Amendment 1

Question Response

Did this change the solicitation?

1. We will not be required to provide temporary crossings for trail traffic at any of the locations during construction, and the trail can be closed to through traffic.

Yes this is correct.

No

2. The boardwalk is drawn as conceptual and requires a third party engineers stamp. Can I assume if this causes any significant changes in design/materials/etc. from what is currently drawn, that pricing can be adjusted accordingly?

Yes, if there is a substantial change from what is shown on the a modification will be executed.

No

Question & Answer

File details come from the government source that posted it. Updated .