Attachment 5 - Consolidated List of RFI Questions and Answers.pdf
PDF 67 KB Posted
- Attached to
- Water Tower Storage Repair & Maintenance
- Solicitation number
- 1232SA26Q0514
About this file
This is a Questions and Answers document (Amendment 0002) for federal contract 1232SA26Q0514 addressing contractor inquiries regarding a tank repair and maintenance project.
The project involves a 1979-built tank that was externally repaired around 2010 with paint removed to bare metal; interior lead content is unknown. The tank can be drained for a maximum of seven calendar days. No third-party inspector will be used, and there are no liquidated damages associated with the project. Weekend work is permissible depending on staff availability. Contractors must log in and out daily; no additional background or security checks are required. Equipment staging is available immediately behind the tank, on pavement next to the bug hut/headhouse area, and possibly on a gravel pad near the Quonset Hut. Water access for project performance is available at no charge from any hose bibb or fire hydrant outside the building, with the hose bibb near the maintenance shop being the closest option. The tank contains no antennas. Notice to proceed and work commencement are anticipated within two months of submittal approval and cost estimation. The SF 24 Bid Form should be obtained from the contractor's bonding company. Warranty period is governed by applicable contract clauses, and bidders should reference those clauses for specific terms.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1232SA26Q0514 Questions and Answers – Amendment 0002 Posting
1. Can you provide a copy of the SF 24 Bid Form that is to be used for bidding? – The contractor bonding company can provide the appropriate forms.
2. It is stated that we are to log in and out each day. Will there be other requirements for background checks or security checks? No other requirements are needed.
3. Can you please provide a copy of the March 2026 Inspection Report which has been referenced? Attachment 6 – Feb/March 2026 Inspection Report is now included.
4. If requested, will weekend work be allowed? Depending on availability of staffing this could be allowed.
5. What year was the tank built? Is it known to contain lead? 1979, outside the tank the paint was taken down to bare metal when repaired around 2010. Inside the tank column is unknown.
6. Where at the site will we have access to water for use while performing the project? Will there be a charge? No charge, any hose bibb/fire hydrant outside the building can be used, Hose bibb near the maintenance shop is the closest.
7. Does the tank have any antennas? None
8. What month/date do you anticipate that a notice to proceed will be issued and work begin on the project? Once submittals are approved and estimated within two months
9. Will a third-party inspector be used? If so, who or who is being considered? No third party inspector.
10. Is there an amount for liquidated damages for this project? - There are no LDs for this project.
11. What is the warranty period for this project? – Reference applicable contract clauses.
12. How long can tank be drained for? Seven (7) calendar days
13. Can you provide information of where we can stage our equipment while onsite?
Immediately behind the tank, pavement next to the bug hut/headhouse area, and possibly next to the Quonset Hut on a gravel pad area.