The provided document is an Attachment 4 - Project Specific Submittal Log for the federal contract opportunity to replace Boiler 3 at the Eastern Regional Research Center (ERRC) in Wyndmoor, PA. The submittal log lists the required project submittals such as the boiler, burner, piping, shop drawings, qualification data, welding certificates, and operation/maintenance data. It specifies the submittal date, specification number, drawing number, submittal type, and status for each item.

The related federal contract opportunity is Solicitation Number 12305B24R0028 for the ERRC Boiler 3 Replacement project. The solicitation is anticipated to be issued around May 15, 2024 as a Firm Fixed-Price contract under a Total Small Business Set-Aside. The anticipated construction magnitude is between $250,000 and $500,000. The solicitation will be a Request for Proposal (RFP) and requires the contractor to be registered in the System for Award Management (SAM) database. The general scope includes demolition and removal of the existing 400HP dual-fuel boiler and provision/installation of a new 250HP natural gas/oil boiler, including piping, electrical, exhaust, and controls integration with the ERRC's Siemens building automation system.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

SUBMITTAL LOGStatus
Pending
Project NameReplace ERRC Boiler 3Award Date
Address600 East Mermaid LaneProject Number
CityWyndmoorStatePAZip19038Contract Number
Line Item NumberSubmittal NumberSubmittal DateSpecification Number Dwg NumberSpecification NameItem DescriptionType Of SubmittalStatusDate Approved/RejectedResubmittal Due DateRemarks
PIC
RNEOI
OSSR&N
DTSTTMF
UDRCAIO
CRUHTRFSRMR
TACEEEIAEAM
WTDMPCMCNA
DIIUEOAPOUT
ANOLNRTLRAI
TGNETTEEDLO
ASSSSSSSSSN
235249BOILER
1SUBMITTALSA.1 BoilerX
2A.2 Burner and ControlsX
3A.3 Piping and AncilliariesX
4A.3 Shop DrawingsX
5C. Qualification Data: InstallerX
6D. Welding CertificatesX
7E. Field quality-control test reportsX
8F. Operation and Maintenance Data
9
10
11A.1 Steel Pipe and FittingsX
12A.2 High Temperature-Direct Buried Insulated PipeX
13B. Shop DrawingsXx
14QUALITY ASSURANCEA.1 Steel Support Welding (Processes and Operators)X
15A.2 Pipe Welding (Processes and Operators)X
16A.3 ASME Compliance (materials, products, and installation)X
17AS-BUILT DRAWINGSProvide electronic drawings to Government.X
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55

File details come from the government source that posted it. Updated .