122828 OR Attachment A.pdf
PDF 354 KB Posted
- Attached to
- Generator Purchase, Removal and Installation
- Solicitation number
- 122828 OR
- Issued by
- Cedar County, Nebraska
About this file
This is a Generator Acceptance Test Form and procurement procedure document issued by the State of Nebraska, Department of Administrative Services, Materiel Division, State Purchasing Bureau. The solicitation seeks a qualified bidder to provide generator purchase, removal, and installation services. The document establishes comprehensive technical specifications for standby emergency generators, including engine requirements, remote monitoring capabilities, and transfer switch/controller functionality. The acceptance test form serves as the quality assurance mechanism for installed equipment, requiring technicians to complete pre-start inspections, conduct 60-minute load tests recording voltage, frequency, load percentage, oil pressure, and water temperature, and verify critical safety parameters including emergency stop functionality, remote start capability via automatic transfer switch signals, fault reset procedures, and automatic mode controller positioning.
The procurement procedure encompasses detailed requirements for vendor registration, ethics compliance, bid submission protocols, evaluation committee processes, and contract terms and conditions. Key administrative requirements include Secretary of State/Tax Commissioner registration, Foreign Adversary Contracting Prohibition Act certification, employee work eligibility verification, and compliance with civil rights and equal opportunity employment laws. The contract incorporates nonnegotiable provisions regarding advance payment prohibition, tax treatment, invoice requirements, funding contingency clauses, and audit rights. Vendors must provide appropriate insurance coverage, maintain state property according to site regulations, and comply with Nebraska Technology Access Standards and disaster recovery requirements. The document emphasizes that all work must meet manufacturer specifications and that completed acceptance test forms must be submitted to the Public Safety Communications Department manager.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 122828 OR ADDENDUM TWO FINAL.docx | DOCX document | |
| 122828 OR ADDENDUM ONE.docx | DOCX document | |
| 122828 OR Attachment B.xlsx | XLSX spreadsheet | |
| 122828 OR ITB FINAL BMS 6-5-26.docx | DOCX document | |
| 122828 OR COST SHEET FINAL.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
• Site Location/Name: __________________________
• Purchase Order: __________________________
• Date of Test: __________________________
Removed Asset
• Property of State of Nebraska Tag Number: __________________________
• Manufacturer: __________________________
• Model: __________________________
• Serial Number: __________________________
Installed Asset
• Property of State of Nebraska Tag Number: __________________________
• Manufacturer: __________________________
• Model: __________________________
• Serial Number: __________________________
Section 2: Pre-Start Inspection Checklist
Check all that apply. If "Fail," provide a remediation note.
Inspection Point Pass Fail Notes/Comments Coolant Level/Concentration ☐ ☐ Oil Level/Quality ☐ ☐ Fuel Level (100% Full) ☐ ☐ Battery Voltage (>12.6V) ☐ ☐ Belts & Hoses Tension/Wear ☐ ☐ Block Heater Functioning ☐ ☐ Battery Heater Functioning ☐ ☐ Remote Monitoring Functioning ☐ ☐
Section 3: Load Test Data (60-Minute Run)
Time Voltage (L-L) Frequency (Hz) Load (%) Oil PSI Water Temp Start 15 Min 30 Min 45 Min 60 Min
122828 OR ATTACHMENT A
GENERATOR ACCEPTANCE TEST FORM DOCUMENT
Section 1: Site Demographics
Section 4: Control System & Safety Verification
Verify the following safety parameters trigger correctly:
• [ ] Emergency Stop: Unit shuts down immediately when pushed.
• [ ] Remote Start: Unit engages via ATS signal.
• [ ] Fault Reset: Alarms clear properly on the control panel.
• [ ] Automatic Mode: Controller left in "AUTO" position after test.
Section 5: Final Sign-Off
Technician Certification:
I certify the above tests were performed according to manufacturer specifications.
• Signature: __________________________ Date: __________
Submit the completed “Generator Acceptance Test Form Document” to the Public Safety Communications Department manager.
| TABLE OF CONTENTS |
| GLOSSARY OF TERMS |
| ACRONYM LIST |
| I. |
| I. |
| I. PROCUREMENT PROCEDURE |
| A. GENERAL INFORMATION |
| B. PROCURING OFFICE AND COMMUNICATION WITH STATE STAFF AND EVALUATORS |
| C. SCHEDULE OF EVENTS |
| D. WRITTEN QUESTIONS AND ANSWERS |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| E. SECRETARY OF STATE/TAX COMMISSIONER REGISTRATION REQUIREMENTS (Nonnegotiable) |
| F. ETHICS IN PUBLIC CONTRACTING |
| G. DEVIATIONS FROM THE SOLICITATION |
| H. SUBMISSION OF SOLICITATION RESPONSES |
| A. |
| A. |
| A. |
| A. |
| A. |
| I. SOLICITATION PREPARATION COSTS |
| J. FAILURE TO COMPLY WITH SOLICITATION |
| K. SOLICITATION RESPONSE CORRECTIONS |
| L. LATE SOLICITATION RESPONSES |
| M. BID OPENING |
| N. SOLICITATION REQUIREMENTS |
| O. EVALUATION COMMITTEE |
| P. EVALUATION OF SOLICITATION RESPONSES |
| Q. BEST AND FINAL OFFER |
| R. REFERENCE AND CREDIT CHECKS |
| S. AWARD |
| T. LUMP SUM OR “ALL OR NONE” SOLICITATION RESPONSES |
| U. REJECTION OF SOLICITATION RESPONSES |
| V. PRICES & COST CLARIFICATION |
| A. |
| A. |
| A. |
| W. SPECIFICATIONS |
| X. ALTERNATE/EQUIVALENT SOLICITATION RESPONSES |
| Y. SOLICITATION TABULATIONS |
| Z. DISPOSITION OF STATE OWNED ASSET(s). |
| II. TERMS AND CONDITIONS |
| A. GENERAL |
| B. NOTIFICATION |
| C. BUYER’S REPRESENTATIVE |
| D. GOVERNING LAW (Nonnegotiable) |
| E. BEGINNING OF WORK & SUSPENSION OF SERVICES |
| F. AMENDMENT |
| G. CHANGE ORDERS OR SUBSTITUTIONS |
| H. RECORD OF VENDOR PERFORMANCE |
| I. NOTICE OF POTENTIAL VENDOR BREACH |
| J. BREACH |
| K. NON-WAIVER OF BREACH |
| L. SEVERABILITY |
| M. INDEMNIFICATION |
| N. ATTORNEY'S FEES |
| O. ASSIGNMENT, SALE, OR MERGER |
| P. CONTRACTING WITH OTHER POLITICAL SUBDIVISIONS OF THE STATE OR ANOTHER STATE |
| Q. FORCE MAJEURE |
| R. CONFIDENTIALITY |
| S. EARLY TERMINATION |
| T. CONTRACT CLOSEOUT |
| U. PROHIBITED PRODUCTS |
| V. AMERICANS WITH DISABILITIES ACT |
| A. |
| A. |
| A. |
| A. |
| W. ACCEPTABLE GOODS |
| A. |
| X. DELIVERY ARO |
| A. |
| Y. ORDERS |
| Z. QUALITY |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| A. |
| AA. ANNUAL USAGE, ESTIMATED |
| III. VENDOR DUTIES |
| A. INDEPENDENT VENDOR / OBLIGATIONS |
| B. FOREIGN ADVERSARY CONTRACTING PROHIBITION ACT CERTIFICATION (Nonnegotiable) |
| C. EMPLOYEE WORK ELIGIBILITY STATUS |
| D. COMPLIANCE WITH CIVIL RIGHTS LAWS AND EQUAL OPPORTUNITY EMPLOYMENT / NONDISCRIMINATION (Nonnegotiable) |
| E. COOPERATION WITH OTHER VENDORS |
| A. |
| A. |
| A. |
| F. PRICES |
| G. PERMITS, REGULATIONS, LAWS |
| H. INSURANCE REQUIREMENTS |
| I. ANTITRUST |
| J. CONFLICT OF INTEREST |
| K. STATE PROPERTY |
| L. SITE RULES AND REGULATIONS |
| M. ADVERTISING |
| N. NEBRASKA TECHNOLOGY ACCESS STANDARDS (Nonnegotiable) |
| O. DISASTER RECOVERY/BACK UP PLAN |
| P. DRUG POLICY |
| Q. WARRANTY |
| R. TIME IS OF THE ESSENCE |
| S. USAGE REPORT |
| A. ENERGY STAR PRODUCTS |
| T. |
| U. AUTHORIZED DEALER & WARRANTY |
| I. PAYMENT |
| IV. |
| A. |
| A. PROHIBITION AGAINST ADVANCE PAYMENT (Nonnegotiable) |
| A. |
| A. |
| B. TAXES (Nonnegotiable) |
| C. INVOICES (Nonnegotiable) |
| D. INSPECTION AND APPROVAL |
| E. PAYMENT (Nonnegotiable) |
| F. LATE PAYMENT (Nonnegotiable) |
| G. SUBJECT TO FUNDING / FUNDING OUT CLAUSE FOR LOSS OF APPROPRIATIONS (Nonnegotiable) |
| H. RIGHT TO AUDIT (First Paragraph is Nonnegotiable) |
| I. TECHNICAL SPECIFICATIONS |
| I. |
| V. |
| A. VENDOR INSTRUCTIONS |
| B. NON-COMPLIANCE STATEMENT |
| A. |
| A. |
| A. |
| C. TECHNICAL SPECIFICATIONS: STANDBY EMERGENCY GENERATOR |
| D. TECHNICAL SPECIFICATION: GENERATOR ENGINE |
| A. |
| A. |
| E. TECHNICAL SPECIFICATION: REMOTE MONITORING |
| F. TECHNICAL SPECIFICATION: TRANSFER SWITCH/CONTROLLER |
File details come from the government source that posted it. Updated .