Summary

This is an Invitation for Bids (IFB27-09) issued by the Incorporated County of Los Alamos, New Mexico, for the installation of electric vehicle charging infrastructure and a drain management system at the Pajarito Cliffs Site, Atomic City Transit Bus Parking Lot in Los Alamos. The project involves installing two County-furnished ChargePoint Express Plus Level 3 Direct Current Fast Chargers with ancillary electrical service, plus a comprehensive drain management system including an ice melting system, gutters, downspouts, and underground piping. The project scope encompasses civil and structural work, concrete reconstruction, pavement markings, traffic control, utility coordination, and professional construction services. The non-mandatory pre-bid conference was scheduled for November 4, 2026, at 2:00 p.m. Mountain Standard Time. Bids were due by 2:00 p.m. Mountain Daylight Time on November 17, 2026, through the County's electronic Procurement Portal (Bonfire). The contract award was anticipated for December 8, 2026, with a Notice to Proceed on December 17, 2026, and substantial completion targeted for March 16, 2027, with final completion by April 16, 2027.

Bidders must submit all costs in a single unified bid with costs for the Electric Vehicle charging infrastructure and drainage management system clearly separated for tracking and grant reporting purposes. The project is funded through two sources: the EV-DCFC infrastructure is funded by a New Mexico Department of Transportation grant, while the drainage management system is funded by Los Alamos County. The project is wholly or partially funded with Federal Transit Authority funds administered through the New Mexico Department of Transportation subrecipient grant agreements. Prospective bidders must possess and maintain active NMDOT 18.27.5 NMAC pre-qualification status and must obtain manufacturer-certified personnel through ChargePoint courses for installation, commissioning, and validation of the EV charging infrastructure. A bid security deposit of five percent of the bid amount is required, and the successful contractor must provide Performance Bond and Labor-Materials Payment Bond in the amount of one hundred percent of the contract price. Insurance requirements include comprehensive general liability coverage of $1,000,000 per occurrence with a combined single limit of $2,000,000 aggregate, motor vehicle liability, workers' compensation, and property/fire/all-risk insurance. Liquidated damages per day will be assessed for failure to meet completion deadlines, with potential incentive payments for early completion. Procurement preferences are available for local and resident businesses upon submission of valid state-issued preference certificates and applicable documentation.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOTIFICATION REGARDING SUBMISSION PROCESS AND REGISTRATION INSTRUCTIONS

The Incorporated County of Los Alamos (“County”) has recently implemented a new on-line eProcurement portal. This new platform, Euna Procurement powered by Bonfire, provides the County’s electronic Bid and Proposal process (“County’s Procurement Portal”). It is where the County will post solicitation opportunities, including Invitation for Bids (IFB), Request for Proposals (RFP), Request for Qualifications (RFQ) and Request for Information/Interest (RFI). The County’s Procurement Portal will streamline the County’s Bid process for Bid or Proposal submission, acceptance, evaluation, and award. For vendors, the County’s Procurement Portal will enhance communication, allow for fast and accurate Bids and Proposals, and provide automatic notification about projects.

Registered vendors will view and submit Bids and Proposals electronically. The past practice of submitting electronic Bids and Proposals by email or submitting paper Bids and Proposals is being phased out. If you are seeing this notification in a solicitation document, submissions will be accepted ONLY electronically through the County’s Procurement Portal for this solicitation. It is every Offeror’s responsibility to read, understand, and submit Bids and Proposals in accordance with the instructions provided in and specific to each solicitation document.

Required Action: Please register as a vendor on the County’s Procurement Portal by visiting https://losalamosnm.bonfirehub.com and click on “Register”. Registration is free and only takes a few minutes. Please be sure to select the applicable NIGP: The Institute for Public Procurement (“NIGP”) Commodity Codes for your business when you are prompted so that you can receive notification of recommended opportunities when they are sent out by the County to the NIGP Commodity Codes you have selected.

Already Have a Bonfire Vendor Account? If you already have a Bonfire vendor account and are already registered for another agency’s portal, you will still need to visit the County’s Procurement Portal at https://losalamosnm.bonfirehub.com and click on “Log In” to provide County-requested information, view open opportunities, receive opportunity notifications, and submit Bids and Proposals through the County’s Procurement Portal. You will be able to manage the multiple agencies with whom you do business through the button labelled “My Supplier Hub” in your Bonfire account.

For Bonfire Support, visit the Vendor Help Center at https://vendorsupport.gobonfire.com where you can view support articles and videos and search FAQ’s on all aspects of Bonfire. For personal assistance, you can email Support.Bonfire@eunasolutions.com . Support is available Monday to Friday from 6:00 a.m. to 6:00 p.m. Mountain Time.

INCORPORATED COUNTY OF LOS ALAMOS

BID AND SPECIFICATIONS

Los Alamos County Transit Bus EV Chargers and Bus Canopy Drain Project

INVITATION FOR BIDS NO. IFB27-09

Advertised on October 25, 2026 in the Albuquerque Journal https://losalamosnm.bonfirehub.com/ https://vendorsupport.gobonfire.com/ mailto:Support.Bonfire@eunasolutions.com

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and Bus Canopy Drain Project

Prepared by:

Matthew Valencia, Project Manager

Reviewed by:

Miguel Jimenez, Sr. Project Manager

Authorized for release by:

Eric Martinez, P.,E., Public Works Director

Remainder of this page intentionally left blank.

Docusign Envelope ID: D5DD1709-4EF0-84DF-826A-705CA0D6B313

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1.0 BIDDING PHASE ----------------------------------------------------------------------------------- 8

1.1 Invitation for Bids ------------------------------------------------------------------------------------------------------------------- 8

1.2 Summary of Work ------------------------------------------------------------------------------------------------------------------11

1.3 Requirements for Bidders -------------------------------------------------------------------------------------------------------14

1.3.1 Bid Evaluation Criteria ------------------------------------------------------------------------------------------------------14

1.3.2 Required Bid Response Documents -------------------------------------------------------------------------------------14

1.3.3 The Bidder’s Bid Response Documents --------------------------------------------------------------------------------14

1.3.4 Liquidated Damages for Failure to Enter into Contract ------------------------------------------------------------15

1.3.5 Conditions of Work ---------------------------------------------------------------------------------------------------------15

1.3.6 Addenda and Requests for Interpretation ----------------------------------------------------------------------------16

1.3.7 Power of Attorney -----------------------------------------------------------------------------------------------------------16

1.3.8 Obligation of Bidder --------------------------------------------------------------------------------------------------------16

1.3.9 Safety Standards and Accident Prevention ---------------------------------------------------------------------------17

1.3.10 Substitutes or Brand Name or Equal ------------------------------------------------------------------------------------17

1.3.11 Bids to Remain Subject to Acceptance ---------------------------------------------------------------------------------17

1.3.12 Withdrawal of Bids ----------------------------------------------------------------------------------------------------------17

1.3.13 Acceptance or Rejection of Bids -----------------------------------------------------------------------------------------18

1.3.14 Award --------------------------------------------------------------------------------------------------------------------------18

1.3.15 Registration of Contractors and Subcontractors --------------------------------------------------------------------18

1.3.16 Procurement Preferences -------------------------------------------------------------------------------------------------18

1.4 Notices to Contractors ------------------------------------------------------------------------------------------------------------19

1.41 Applicable Law -------------------------------------------------------------------------------------------------------------------19

1.4.2 Gross Receipts Tax ----------------------------------------------------------------------------------------------------------19

1.4.3 Minimum Wage Rates ------------------------------------------------------------------------------------------------------19

1.4.4 Work Conditions -------------------------------------------------------------------------------------------------------------19

1.4.5 Public Information ----------------------------------------------------------------------------------------------------------19

1.4.6 Performance and Labor and Material Bonds Requirements ------------------------------------------------------20

1.4.7 Davis Bacon Act (DBA) Conformance Requirements ---------------------------------------------------------------20

1.5 Bid Forms -----------------------------------------------------------------------------------------------------------------------------23

1.5.1 Bid Form -----------------------------------------------------------------------------------------------------------------------25

1.5.2 Alternates and Allowances ------------------------------------------------------------------------------------------------32

1.5.3 List of Subcontractors ------------------------------------------------------------------------------------------------------34

1.5.4 Bid Bond -----------------------------------------------------------------------------------------------------------------------35

1.5.7 Permanent Main Office Address of Company ------------------------------------------------------------------------38

1.5.8 Authorization for Verification of Information ------------------------------------------------------------------------38

1.5.9 Certificate of Contractors Registration --------------------------------------------------------------------------------39

2.0 AWARD PHASE ----------------------------------------------------------------------------------- 40

2.1 Award Forms ------------------------------------------------------------------------------------------------------------------------40

2.1.1 Notice of Award -------------------------------------------------------------------------------------------------------------40

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

2.1.2 Receipt of Notice of Award -----------------------------------------------------------------------------------------------42

2.1.3 Performance Bond ----------------------------------------------------------------------------------------------------------43

2.1.4 Payment (Labor and Materials) Bond ----------------------------------------------------------------------------------45

2.1.5 Insurance Requirement ----------------------------------------------------------------------------------------------------47

2.1.6 Contract ------------------------------------------------------------------------------------------------------------------------49

3.0 CONSTRUCTION PHASE ------------------------------------------------------------------------ 56

3.1 Construction Phase Related Forms --------------------------------------------------------------------------------------------56

3.1.1 Contractor Personnel Information --------------------------------------------------------------------------------------56

3.1.2 Notice to Proceed -----------------------------------------------------------------------------------------------------------57

3.1.3 Acceptance of Notice to Proceed ----------------------------------------------------------------------------------------58

3.1.4 Application and Certification for Payment Part 1 -------------------------------------------------------------------59

3.1.5 Application and Certification for Payment Part 2 -------------------------------------------------------------------60

3.1.6 Affidavit of Payment and Release of Liens ----------------------------------------------------------------------------61

3.1.7 Field Order --------------------------------------------------------------------------------------------------------------------63

3.1.8 Change Order -----------------------------------------------------------------------------------------------------------------64

3.2 Conditions of the Contract - General Conditions --------------------------------------------------------------------------69

3.2.1 Definitions ---------------------------------------------------------------------------------------------------------------------69

3.2.2 Additional Instructions -----------------------------------------------------------------------------------------------------71

3.2.3 Schedules, Reports and Records -----------------------------------------------------------------------------------------73

3.2.4 Shop Drawings and Submittals -------------------------------------------------------------------------------------------76

3.2.5 Start of Various Types of Work and Management Planning ------------------------------------------------------76

3.2.6 Materials, Services and Facilities ----------------------------------------------------------------------------------------78

3.2.7 Substitutes or “Brand Name” or Equal ---------------------------------------------------------------------------------78

3.2.8 Inspection and Testing -----------------------------------------------------------------------------------------------------80

3.2.9 Correction of Work----------------------------------------------------------------------------------------------------------81

3.2.10 Patents -------------------------------------------------------------------------------------------------------------------------82

3.2.11 Surveys, Permits, and Regulations --------------------------------------------------------------------------------------82

3.2.12 Subsurface and Physical Conditions ------------------------------------------------------------------------------------83

3.2.13 Protection of Work, Property and Persons----------------------------------------------------------------------------86

3.2.14 Changes in the Work -------------------------------------------------------------------------------------------------------87

3.2.15 Suspension, Delay or Termination of Work ---------------------------------------------------------------------------90

3.2.16 Subcontracting ---------------------------------------------------------------------------------------------------------------91

3.2.17 Duties of the Contractor ---------------------------------------------------------------------------------------------------91

3.2.18 Job Site Administration ----------------------------------------------------------------------------------------------------92

3.2.19 Engineer’s Authority --------------------------------------------------------------------------------------------------------95

3.2.20 Duties, Responsibilities and Limitations -------------------------------------------------------------------------------96

3.2.21 Engineer’s Review of Work, Rejection of Work, Inspections, and Tests ---------------------------------------97

3.2.22 Limitations of Authority ---------------------------------------------------------------------------------------------------97

3.2.23 Land and Right-of-Way -----------------------------------------------------------------------------------------------------98

3.2.24 Warranty/Guaranty ---------------------------------------------------------------------------------------------------------98

3.2.25 Miscellaneous ----------------------------------------------------------------------------------------------------------------99

3.2.26 Dispute Resolution, Applicable Law, and Venue ---------------------------------------------------------------------99

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

3.2.27 Examination of Records Provisions ----------------------------------------------------------------------------------- 100

3.2.28 American with Disabilities Act Compliance ------------------------------------------------------------------------- 100

3.2.29 A. Bids and Proposals are public Records --------------------------------------------------------------------------- 100

3.2.30 Wage Rate Determination ---------------------------------------------------------------------------------------------- 100

3.3 ATTACHMENTS -------------------------------------------------------------------------------- 101

3.3.1 License Agreement for Staging Area ---------------------------------------------------------------------------------- 102

3.3.2 Wage Rate Information -------------------------------------------------------------------------------------------------- 105

3.4 TECHNICAL SPECIFICATIONS ----------------------------------------------------------------- 123

3.5 FEDERAL REQUIREMENTS -------------------------------------------------------------------- 124

LOBBYING CERTIFICATION ------------------------------------------------------------------------- 127

1. NO GOVERNMENT OBLIGATION TO THIRD PARTIES ---------------------------------- 129

2. PROGRAM FRAUD AND FALSE OR FRAUDULENT STATEMENTS OR RELATED ACTS.

3. ACCESS TO RECORDS ---------------------------------------------------------------------------- 130

4. FEDERAL CHANGES ------------------------------------------------------------------------------ 130

5. CIVIL RIGHTS -------------------------------------------------------------------------------------- 130

6. DISADVANTAGED BUSINESS ENTERPRISES ----------------------------------------------- 131

7. INCORPORATION OF FTA TERMS ------------------------------------------------------------ 132

8. ENERGY CONSERVATION ----------------------------------------------------------------------- 132

9. TERMINATION ------------------------------------------------------------------------------------ 132

10. SEAT BELT USE --------------------------------------------------------------------------------- 133

11. SAFE OPERATION OF MOTOR VEHICLES ------------------------------------------------ 133

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

12. FEDERAL TAX LIABILITY AND RECENT FELONY CONVICTIONS ------------------ 134

13. TRAFFICKING IN PERSONS ------------------------------------------------------------------ 134

14. PROHIBITION ON CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE

SERVICES OR EQUIPMENT -------------------------------------------------------------------------- 134

15. GOVERNMENTWIDE DEBARMENT AND SUSPENSION ------------------------------- 135

16. NOTIFICATION RELATED TO FRAUD, WASTE, ABUSE, OR OTHER LEGAL

MATTERS ------------------------------------------------------------------------------------------------ 135

17. LOBBYING RESTRICTIONS ------------------------------------------------------------------ 136

18. BUY AMERICA ---------------------------------------------------------------------------------- 136

19. CLEAN AIR --------------------------------------------------------------------------------------- 137

20. CLEAN WATER --------------------------------------------------------------------------------- 137

21. BREACHES AND DISPUTES ------------------------------------------------------------------ 137

22. CARGO PREFERENCE - USE OF UNITED STATES- FLAG VESSELS ------------------ 138

23. FLY AMERICA REQUIREMENTS ------------------------------------------------------------ 139

24. DAVIS-BACON AND COPELAND ANTI-KICKBACK ACTS ----------------------------- 139

25. EQUAL EMPLOYMENT OPPORTUNITY --------------------------------------------------- 146

26. CONTRACT WORK HOURS AND SAFETY STANDARDS ACT ------------------------ 148

27. BONDING REQUIREMENTS ------------------------------------------------------------------ 149

BID BOND REQUIREMENTS ------------------------------------------------------------------------- 149

PERFORMANCE BONDS ------------------------------------------------------------------------------ 149

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

PAYMENT BONDS -------------------------------------------------------------------------------------- 150

28. VETERANS PREFERENCE -------------------------------------------------------------------- 150

29. SEISMIC SAFETY ------------------------------------------------------------------------------- 150

30. RESERVED. -------------------------------------------------------------------------------------- 150

32. RECYCLED PRODUCTS ----------------------------------------------------------------------- 150

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1.0 BIDDING PHASE

1.1 Invitation for Bids

This Procurement includes installation of County furnished equipment consisting of:

Two (2) ChargePoint Express Plus Level 3 Direct Current Fast Chargers and one (1) A new 500 KVA utility XFMR 480V/3 Ph Sec as further described herein.

This is a brand name or equal specifications procurement. The designated brand names are:

• NVENT RAYCHEM

• Delta-Therm

• Britech

• Bartec And any other brand identified in the solicitation documents. The nature of the products makes use of a brand name or equal specification suitable for the procurement. The Deputy Chief Purchasing Officer has determined that essential characteristics of the brands described above are commonly known in the industry or trade. Use of the brand names are for the purpose of describing the standard quality, performance, and characteristics desired and is not intended to limit or restrict competition. Substantially equivalent products to those designated will be considered for award, the County reserves the right to obtain additional information from the bidder regarding technical and performance specifications of suggested alternates and final right to determination of equivalency shall be determined by the County.

The Incorporated County of Los Alamos (“County”) reserves the right, in its sole discretion, to accept any bid and to reject any or all bids.

Bids are invited from all responsible bidders.

1.1.1. ELECTRONIC SUBMISSIONS ONLY

A full copy of the solicitation and all associated documents can be found on the County’s Procurement Portal at https://losalamosnm.bonfirehub.com/. Only Bids submitted through the County’s Procurement Portal by the Bid Due Date stated herein, or as may be modified by addendum, will be considered. Late responses will not be considered. To register to view and download solicitation documents and submit a Bid through the County’s Procurement Portal, follow the instructions on page 1 of this solicitation.

Only Bids received through the Procurement Portal prior to 2:00 p.m. MDT, November 17, 2026 will be reviewed.

1.1.2. ADDITIONAL DOCUMENTS AND INFORMATION INCLUDED AS A PART OF THIS IFB

Additional documents are referenced in this IFB, which may include, but are not limited to, exhibits, attachments, links to documents online, and documents that are provided through the County’s Procurement Portal. Any such documents are considered to be a part hereof and constitute, along with this solicitation document and any addenda, the complete solicitation package. Documents required to be submitted as a component of Bidders’ Response will be noted as such in each individual solicitation posted on the County’s Procurement Portal, and Bidders will be unable to submit their Bids through the County’s

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

Procurement Portal until all required documents and information have been uploaded or provided by Bidders.

Please also reference “1.3.3 The Bidder’s Bid Response Documents ” below.

1.1.3. GRANT RELATED INFORMATION

This project is funded through two distinct sources:

1.1.3.1. EV-DCFC Infrastructure: New Mexico Department of Transportation grant, as described further below.

1.1.3.2. Drainage Management System: Los Alamos County funds.

Respondents must present a single, unified bid. However, costs for the EV-DCFC infrastructure and the drain management system must be clearly separated and itemized to facilitate precise expense tracking and grant reporting

1.1.4. Federal Funding. This project is wholly or partially funded with Federal Transit Authority (FTA) funds, which are administered by the New Mexico Department of Transportation through the subrecipient grant agreement M01810 and M01955 between State of New Mexico Department of Transportation and the County. As part of any response to this solicitation, Bidders shall affirm their ability to meet federal grant requirements contained herein. Bidders who cannot affirm ability to meet these requirements may be deemed non-responsive or non-responsible.

Contractor shall strictly adhere to all applicable Federal and FTA Procurement Clauses. These mandates dictate standard contractual compliance are incorporated into this IFB in Section

1.4 and Section 3.5.

Incorporated County of Los Alamos Invitation for Bids Number: IFB27-09

Los Alamos County Transit Bus EV Chargers and Bus Canopy Drain

1.1.5. Bid security in the amount of five percent (5%) of the bid must accompany the bid. Such cash, certified checks or bid bonds will be returned to all except the three finalist bidders within three days after the opening of bids. The remaining cash, checks and bid bonds will be returned promptly after the County and the accepted Bidder have executed the contract, or if no award has been made within ninety (90) days after the date of the opening of bids, upon demand of the bidder at any time thereafter, so long as Bidder has not been notified of the acceptance of Bidder’s bid. In submitting their Bid Bond, it is not mandatory that Bidders use the Bid Bond form provided in the packet. The County strongly encourages all Contractors to use this form, but if the contractor elects not to use it, the Bid Bond must be submitted on a form acceptable in the construction industry and approved by the County Project Manager in advance of the bid due date.

1.1.6. A Non-Mandatory Pre-bid Conference will be held on Wednesday, November 4, 2026 at

2:00 P.M. Mountain Standard Time (MST). The meeting link is available in the Project on the Procurement Portal.

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

This conference is held to answer questions from the prospective bidders as well as familiarize bidders with the project. Questions regarding the meaning of plans, specifications or other documents related to the project should be submitted in writing prior to the pre-bid conference.

The County will preside over the pre-bid conference and provide for the recording and distribution of minutes. The pre-bid conference will include, but not be limited to the following:

1. Discussion of schedule for procurement, progress, values for progress payments and submittals.

2. Critical work sequencing and priorities.

3. Use of construction site premises, storage areas, office areas, security, cleaning, and

County’s needs.

4. Public Information.

1.1.7. QUESTIONS

Any questions must be received in writing at least six (6) business days prior to the submission due date, unless otherwise stated herein or in an addendum. Questions must be submitted through the County’s Procurement Portal. Please follow the instructions on page one (1) of this document to register for the County’s Procurement Portal to submit written questions.

Bidders who submit questions via e-mail or by phone shall be redirected to submit written questions through the County’s Procurement Portal.

Bidders must submit in writing through the County’s Procurement Portal, as stated herein, any questions or requested clarification necessary for Bidder to provide a complete Response with all Bid response components and pricing included. Bidders are asked to refrain from including in Bids statements such as “more information available upon request,” “pricing to be determined,” or other similar statements. Such statements and failure of Bidder to seek clarification needed for Bidder to provide the requested information may result in a Bidder being found non-responsive or non-responsible. This in no way may be construed to conflict with County’s right to hold interviews and discussions for clarification with Bidders, as further described herein. Failure of any bidder to receive any addendum or interpretation shall not relieve such bidder from any obligation under its bid as submitted. All addenda so issued shall become part of the solicitation documents.

The County reserves the right to issue addenda to the solicitation documents including construction specifications and plans during the advertising period as provided in the solicitation documents. Bidders are responsible for determining if any addenda have been issued. The terms, bid and solicitation are interchangeable. Also, the defined terms contract and agreement are interchangeable.

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1.2 Summary of Work

Bid Number: IFB27-09

Los Alamos County Transit Bus EV Chargers and Bus Canopy Drain

This project is issued by and under the control of The Incorporated County of Los Alamos. The contracting office is the Public Works Department. The location of the project is in the County of Los Alamos, New Mexico.

The summary of work is as follows, but is not limited to the following:

1. Project Overview

The Incorporated County of Los Alamos is requesting bids to install Electric Vehicle charging infrastructure for two buses and a drain management system at its bus parking lot canopy structure.

The Electric Vehicle charging infrastructure consists of the installation of two (2) County-furnished ChargePoint Express Plus Level 3 Direct Current Fast Chargers (EV-DCFC) and ancillary electric service.

The drain management system consists of two parts: i) an ice melting system with ancillary electric service, gutters, and downspouts at the bus canopy. ii) underground piping to collect drain water and direct it to the storm water sewer.

2. Project Location

Pajarito Cliffs Site, Atomic City Transit Bus Parking Lot 101 Camino Entrada, Los Alamos, NM 87544

3. Project Requirements

a. Bid completeness. Respondents to this IFB should furnish all trades labor, materials, equipment, tools, bonding, insurance, construction management, and professional services required to deliver a turnkey project.

b. Bid Separation (Mandatory) This project is funded through two distinct sources:

i. EV-DCFC Infrastructure: New Mexico Department of Transportation grant.

ii. Drainage Management System: Los Alamos County funds.

Respondents must present a single, unified bid. However, costs for the EV-DCFC infrastructure and the drain management system must be clearly separated and itemized to facilitate precise expense tracking and grant reporting.

c. State pre-qualification (Mandatory)

The bidding Contractor must possess and maintain active NMDOT 18.27.5 NMAC pre-qualification status.

d. Commissioning certifications

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

The installation, commissioning, and validation of the EV-DCFC infrastructure require manufacturer-certified personnel. The certification is obtained through the completion of the following courses offered by ChargePoint:

i. Core Certification – ChargePoint AC/DC certification curriculum and pass the proctored DC Core Exam.

ii. Product Micro-credential: ChargePoint Express Plus Installation micro-credential course.

Visit https://www.chargepoint.com/partners/training-certification for additional information.

Respondents must factor the necessary time and fees into their bid proposals to complete these courses if their staff is not already certified. Respondents are responsible for confirming with ChargePoint if any additional courses or certifications are applicable to the Express Plus Level 3 EV-DCFC chargers.

4. County-Furnished Equipment & Services

The County will provide the following equipment:

a. Two (2) ChargePoint Express Plus Level 3 DC Fast Charging stations

b. A new 500 KVA utility XFMR 480V/3 Ph Sec

In addition, the County will also provide the electric utility connections and routing of primary electric service up to the utility meter.

5. Project Scope of Work

Contractor shall furnish all labor, materials, equipment, tools, and professional services required to successfully execute and complete both project components.

a. EV Charging Infrastructure Installation

i. Station Installation: Install and anchor the two (2) new commercial-grade ChargePoint Express Plus Level 3 DC Fast Charging stations.

ii. Electrical Distribution: Execute all downstream electrical distribution from the meter, including trenching, conduit placement, and wiring.

iii. Civil & Structural Work: Pour specialized structural concrete pads for charging hardware and install protective bollards to prevent vehicle impact.

iv. Utility Relocation: Safely disconnect, move, and reinstall existing block heaters to accommodate the new layout.

b. Bus Canopy Drainage & Deicing Management

i. Drainage Systems: Install commercial-grade drainage management infrastructure for the main bus canopy.

ii. Thermal Protection: Install and wire a dedicated roof deicing system along the upper roof/canopy surfaces to manage ice buildup.

c. Civil Work & Restoration https://www.chargepoint.com/partners/training-certification

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

i. Concrete Reconstruction: Reconstruct surrounding concrete sidewalks, curbs, and gutters to match and seamlessly support the modified site layout.

ii. Pavement Markings: Apply professional-grade pavement striping and markings for the designated EV charging stalls.

iii. Site Preparation: Perform all necessary clearing, grubbing, and complete removal of obstructive materials within designated work zones.

d. Project Management, Safety, & Controls

i. Mobilization: Mobilize all personnel, machinery, and equipment to the Pajarito Cliffs site.

ii. Traffic Control: Design, implement, and maintain comprehensive traffic control management, utilizing appropriate construction traffic control devices to guarantee safe vehicle and pedestrian movement throughout the construction phase.

iii. Utility Line Locates: Initiate utility line locates requests via the NM811 process to identify all existing subsurface utilities prior to excavation.

iv. Agency Coordination: Coordinate directly with the Los Alamos County Department of Public Utilities (DPU) for mandatory open-trench and pothole inspections before any conduit placement.

v. Engineering Controls: Provide all professional construction staking and engineering layout controls necessary to execute the civil designs according to approved site plans.

The construction drawings for this project as well as the manuals and specifications for the County furnished Charge Point EV-DCFC are part of this IFB. These documents are located at https://losalamosnm.egnyte.com/fl/YfTRm7tYvxy7k:

IFB Advertisement October 25, 2026 Pre-Bid Meeting November 4, 2026 Bids Due November 17, 2026 Bid Award December 8, 2026 Pre-Construction Meeting December16, 2026 Notice to Proceed December 17, 2026 Start of Construction December 17, 2026 Substantial Completion Date March 16, 2027 Final Completion Date April 16, 2027 The dates listed above are tentative and subject to change.

Work to achieve Final Completion, including all Operations and Maintenance Manuals, final Certified Payrolls, As-built drawings, Warranty Certificates, Final Inspection by the Manufacturer and approval of the Installation, and other close-out documents by April 16, 2027.

https://losalamosnm.egnyte.com/fl/YfTRm7tYvxy7k

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1.3 Requirements for Bidders

Bids must be made with the understanding and in accordance with these conditions for bidders:

1.3.1 Bid Evaluation Criteria

Bid acceptance and bid evaluation. Bids shall be unconditionally accepted without alteration or correction, except as authorized in this article. Bids shall be evaluated based on the requirements set forth in the IFB, which may include criteria to determine acceptability such as inspection, testing, quality, workmanship, delivery and suitability for a particular purpose. Those criteria that will affect the bid price and be considered in evaluation for award shall be objectively measurable, such as discounts, transportation costs, and total of life cycle costs. The IFB shall set forth the evaluation criteria to be used. Only criteria that are set forth in the IFB may be used in bid evaluation. Interviews are to be used only for the purpose of clarification. The final evaluation results shall be forwarded to the purchasing agent.

The evaluation criteria for this Bid are:

1. Accurate submission of Bid Response Documents

2. Cost

The County may make such investigations as deemed necessary to determine the ability of the Bidder, and any prospective subcontractors of the Bidder, to perform the work, and the bidder shall furnish to the County all such information and data for this purpose as the County may reasonably request. The County reserves the right to reject any bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the County that such Bidder is properly qualified to carry out the obligations of the Contract and to timely complete the work contemplated herein. Conditional bids may not be accepted in the sole discretion of the County.

When bids are received from a bidder who requests preference, and the bidder has provided evidence that the bidder qualifies for preference as described in section 1.3.16 below the following procedure shall be utilized: When bids are received, the price quoted by the qualifying vendor shall be multiplied by 0.95. After application of the preference factor, the contract shall be awarded to the lowest bidder.

If one or more scores are equal, the same procedure shall be followed with respect to the next category of offerors listed, and the next, until an offer qualifies for award. The priority of categories of offers is as follows:(1) Local business; (2) Resident business.

1.3.2 Required Bid Response Documents

The bidder shall follow the instructions described in Section 1.1 Invitation for Bids.

1.3.3 The Bidder’s Bid Response Documents

The following documents must be completed and included, the documents identified with section numbers below are available in the Procurement Portal as part of the solicitation document, the document should be submitted in this preferred order:

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1. Copy of Bidder’s State of New Mexico Contractor’s License(s) with proper classifications.

2. Bid Form (Section 1.5.1)

3. Alternatives and Allowances, if applicable (Section 1.5.2)

4. List of Subcontractors with Company Name, license number(s) and classification(s) (Section 1.5.3).

5. Bid Bond (Section 1.5.4)

6. Campaign Contribution Form (Section 1.5.5)

7. Certification – Debarment, Suspension, and other Responsibility Matters (Section

1.5.6)

8. Permanent Main Office Address of Company (Section 1.5.7) – Note requirement to provide a Certificate of Good Standing and Compliance from the New Mexico Secretary of State, if incorporated.

9. Authorization for Verification of Information (Section 1.5.8)

10. Provide proof of online registration and payment of $400.00 for Certificate of

Contractors Registration (Section 1.5.9) with New Mexico Department of Workforce Solutions.

11. Provide evidence of Bidders NMDOT 18.27.5 NMAC pre-qualification status.

12. Required Federal Forms:

a. Lobbying Certification Form

b. Buy America Certification Form

c. Acknowledgement of Addenda Form

The County may consider a bid to be non-responsive or non-responsible if the Contractor fails to include any of the items described in items 1 through 12, above.

1.3.4 Liquidated Damages for Failure to Enter into Contract

The successful Bidder, upon failure or refusal to execute and deliver the Contract and required Bonds within ten (10) calendar days after Bidder has received the Notice of Award, shall forfeit the Bidder’s Bond to the County, as liquidated damages for such failure or refusal, the bid security deposited with Bidder’s bid.

1.3.5 Conditions of Work

Each bidder must inform itself fully of the conditions relating to the construction of the Project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of its obligation to furnish all material and labor necessary to carry out the provisions of the Contract. Insofar as possible, the Contractor in carrying out the Work must employ such methods or means as will not cause any interruption of, or interference with the Work of any other contractor, or the daily operations of County offices. The Work in this Contract will be carried out during the hours of 8:00 a.m. to 5:00 p.m., Monday through Friday unless otherwise scheduled with and approved by the County. Noise Ordinance Waivers are required for work occurring between the hours 9:00 p.m. and 7:00 a.m.

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1.3.6 Addenda and Requests for Interpretation

A. No interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any bidder orally and bidders understand that no oral interpretation once made may be relied upon. Every request for such interpretation shall be in writing addressed to the Project Manager. Requests for interpretation must be received at least six (6) working days (Monday-Friday) prior by 5:00 p.m. to the date fixed for the opening of bids. Failure of any bidder to acknowledge all addenda on the Addendum Acknowledgement Form shall not relieve such bidder from any obligation under its bid as submitted and may render the bidder non-responsive. Each Bidder shall ascertain prior to submitting a Bid that the Bidder has received all Addenda issued, and the Bidder shall specifically acknowledge their receipt in the bid. All addenda so issued shall become part of the Contract documents.

B. Addenda will be e-mailed to all who are known by the County to have requested Bid Documents.

C. No Addenda will be issued later than four (4) working days prior to the date for receipt of Bids except an Addendum withdrawing the request for Bids or one which includes postponement of the date for receipt of Bids.

1.3.7 Power of Attorney

Attorneys-in-Fact who sign any required bonds must file with each bond a certified properly executed and dated copy of their power of attorney.

1.3.8 Obligation of Bidder

Complete sets of Solicitation Documents must be used in preparing Bids; neither the County nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Solicitation Documents.

The Submission of a bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of the Bid, which without exception the Bid is premised upon performing and furnishing the Work required by the Solicitation Documents. The bidder will be required to establish to the satisfaction of the County the qualifications and capability of the persons proposed to furnish and perform the Work described in the Solicitation documents. Contractor, by signing the Bid also acknowledges that the Contract Time is reasonable for the weather and climactic conditions.

Prior to the award of the Contract, the County will notify the bidder in writing if the County after due investigation has reasonable objection to a proposed person or entity, the Bidder may, at the Bidder’s option, (1) withdraw the Bid, or (2) submit a substitute person or entity acceptable to the County with an adjustment in the Base Bid or Alternate Bid to cover the difference in cost, if any, occasioned by such substitution. The County may accept the adjusted bid price. In the case that the adjusted price makes them no longer the low bidder, County reserves the right to award to the subsequent low bidder. In the event of withdrawal, bid security will not be forfeited. Persons proposed by the Bidder and to whom the County has made no reasonable objection must be used to perform the Work for which

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and they were proposed and shall not be changed except with the prior written consent of the County.

1.3.9 Safety Standards and Accident Prevention

With respect to all work performed under this contract, the Bidder shall:

A. Comply with the standard provisions of the most current versions of all applicable laws, rules and regulations that apply to the work contracted for.

B. Provide a Safety Management Plan to the County after award acceptable to the Project Manager (see Section 3).

1.3.10 Substitutes or Brand Name or Equal

During solicitation, it may be determined that a “brand name or equal” is in the County’s best interests, and in many cases is the “Basis of Design” for a particular item or system.

The Contractor may provide a substitution of a particular item or items. The Contractor shall provide proof that the proposed substitute item is equal to or exceeds the basis of design. The County reserves the right to accept or reject the substitution at its sole discretion.

All re-design and evaluation costs that may be incurred shall be paid by the Contractor.

The Contractor shall provide an alternate bid based on the original plans and specifications and shall provide separately the cost for the substituted item, which the County reserves the right to accept or reject.

The procedure for submission of any such application by Contractor and consideration by County is set forth in Section 3.

1.3.11 Bids to Remain Subject to Acceptance

All bids will remain subject to acceptance for sixty (60) calendar days after the day of the Bid Opening. The County may, it its sole discretion, release any Bid and return that Bidder’s Bid Security prior to that date. County may request an extension, agreeable to both the Bidder and County.

1.3.12 Withdrawal of Bids

A. Bidder may withdraw its bid by written notice and received by Purchasing Agent prior to bid opening.

B. After bid opening, no changes in bid prices or other provisions of bids prejudicial to the interests of the County or fair competition shall be permitted. In lieu of bid correction, a low bidder alleging a material mistake of fact may be permitted to withdraw its bid if: (1) The mistake is clearly evident on the face of the bid document;

or (2) The Bidder submits evidence which clearly and convincingly demonstrates that a mistake was made.

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1.3.13 Acceptance or Rejection of Bids

The County reserves the right to accept any bid, reject any or all bids without cause, to waive any or all technicalities in any Bid in the interest of the County and the right to reject all non-conforming, non-responsive or conditional Bids.

1.3.14 Award

Bids shall be evaluated based on the requirements set forth in the IFB, which may include criteria to determine acceptability such as inspection, testing, quality, workmanship, delivery and suitability for a particular purpose and the Contract shall be awarded on the basis of the lowest responsible and responsive bidder in accordance with Chapter 31-101

(i) of the Los Alamos Code of Ordinances.

1.3.15 Registration of Contractors and Subcontractors

Any bidder that submits a bid valued at more than the dollar amount required by the New Mexico Public Works Minimum Wage Act [13-4-11 through 13-4-17 NMSA 1978] and the New Mexico Subcontractors Fair Practice Act [13-4-31 through 13-4-43] for a public works project shall be registered with the labor and industrial division of the labor department.

County will not accept bids for a public works project subject to the New Mexico Public Works Minimum Wage Act from the contractor that does not provide proof of required registration for itself and its subcontractors.

1.3.16 Procurement Preferences

In accordance with Incorporated County of Los Alamos (“County”) Code Section. 31- 261(b) and NMSA 1978 Section 13-1-21 et al., if the chief purchasing officer determines preference is applicable to the solicitation, Offeror(s) must submit a written request for preference, with a valid copy of the applicable New Mexico state-issued preference certificate with its Bid to qualify for the requested preference. If requesting local preference, Offeror(s) must also submit with its Bid a current valid Los Alamos County Business License and must maintain its principal office and place of business in Los Alamos County to qualify for Local Business preference. County reserves the right, for any reason, to (1) verify the accuracy and validity of any information and documents submitted by Offerors prior to applying any preference factors; and (2) deny any request for preference if Offeror(s) have not met applicable requirements to qualify for any requested preference. Bidders requesting preference shall submit the Request for Preference form included with this solicitation as well as the required documents described above.

IFB27-09 Incorporated County of Los Alamos Los Alamos County Transit Bus EV Chargers and

1.4 Notices to Contractors

1.41 Applicable Law

Work shall be performed in accordance with applicable federal, state and local laws (Los Alamos County Code of Ordinances, Section 31.2 Procurement Code).

1.4.2 Gross Receipts Tax

All bids submitted are to exclude the applicable gross receipts taxes. County will pay the applicable taxes to the Contractor including any increase in the applicable taxes becoming effective after the execution date of the contract. The applicable gross receipts taxes will be shown as a separate amount on each payment application made under the contract.

The Contractor is responsible for payment to the State of New Mexico for all gross receipt’s taxes collected.

1.4.3 Minimum Wage Rates

Pursuant to the New Mexico Public Works Minimum Wage Act, Section 13-4-11 through 13-4-17 NMSA 1978 (comp.) all certified payrolls submitted must contain required information as stated on the pertinent information sheet of the Wage Rate Decision issued on said project.

The Contractor, Sub-contractor and all tiers shall provide the Statement of Intent to Pay Prevailing Wages form to County’s Project Manager.

1.4.4 Work Conditions

This contract will be performed in and adjacent to Los Alamos County for the contract duration specified in the Contract. The Contractor shall be aware of the conditions that may normally exist within the project area during performance of the work. Those conditions may include but are not limited to:

• Extended freezing temperatures,

• Intense rainfall events,

• Snowfall and snow accumulation,

• Limited direct sunlight.

Delays due to normal weather conditions are not eligible for time extensions and/or additional compensation. Contractor is required to protect their work and the project from normal weather events. Unusual weather-related time extensions may be awarded by the County pursuant to an approved change order at the County’s sole discretion. Please refer to Section 2, Contract Articles 2 and 3.

1.4.5 Public Information

The Contractor is required to be an active participant in the execution of the Public Information and Involvement Plan (PIIP) to be developed by the County. County retains edit and approval rights to any documents being released to the public and requires two

(2) working days advance notice to allow for said edit/approval.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .