12. DMAFB Installation Failure Action Plan.pdf

PDF 74 KB Posted

Attached to
Repair and Construct Primary Electric Distribution
Solicitation number
FA487724B0001
Issued by

About this file

This document outlines a failure action plan and federal contract opportunity for electrical distribution repair and construction work at Davis-Monthan Air Force Base in Arizona. The failure action plan details procedures for replacing faulty equipment, such as relay and current transformer failures, during two planned outage phases for the project. It also addresses transferring loads and isolating affected circuits during work. The related federal contract opportunity involves designing and constructing a switch house facility and upgrading electrical systems to current codes. Interested offerors must submit an entry authorization letter by March 15, 2024 to be considered for the work. The Air Force is seeking a contractor to complete the repair, construction, and demolition activities described in the attached specifications and drawings. Compliance with all required design standards is mandatory.

View the file

Other files

File Type Posted
Solicitation Amendment FA487724B00010003 SF 30.pdf PDF
Solicitation Amendment - FA487724B00010003.pdf PDF
23. Wage Determination - AZ20240040.pdf PDF
Solicitation - FA487724B0001.pdf PDF
Solicitation Amendment FA487724B00010002 SF 30.pdf PDF
22. Sign-In Sheet (3-26).pdf PDF
21. FBNV190002 RFI ANSWERS.xlsx XLSX spreadsheet
9. DMAFB Electrical Distribution - Drawing Set - 100 pct - REV 1.pdf PDF
8. DMAFB Electrical Dist - Design Analysis - 100 percent - REV 1.pdf PDF
6. 5015-21-3104 DMAFB Substation Specs - REV 1.pdf PDF
3. 5015-21-3104 DMAFB Substation - 100% Elec Calc Package - REV 1.pdf PDF
Solicitation - FA487724B0001.pdf PDF
7. DMAFB Electrical Dist - Cx Plan REV 1.pdf PDF
4. 5015-21-3104 DMAFB Substation - 100% Structural Calcs - REV 1.pdf PDF
Solicitation Amendment FA487724B00010001.pdf PDF
2. 5015-21-3104 DMAFB Cutsheets -100pct - REV 1.pdf PDF
Solicitation - FA487724B0001.pdf PDF
6. 5015-21-3104 DMAFB Substation Specs 1.19.2024.pdf PDF
7. DMAFB Electrical Dist - Cx Plan.pdf PDF
8. DMAFB Electrical Dist - Design Analysis - 100 percent.pdf PDF
10. E-101 E-HOUSE PLAN.pdf PDF
16. Cybersecurity of Facility-Related Control Systems (01-18-2017).pdf PDF
1. Specifications Package FBNV190002.pdf PDF
2. 5015-21-3104 DMAFB Cutsheets -100pct.pdf PDF
3. 5015-21-3104 DMAFB Substation - 100% Elec Calc Package.pdf PDF
13. Contractor Environmental Guide (15 May 2019).pdf PDF
14. DMAFB Design Compatibility Guidelines 2017.pdf PDF
17. AF Form 3052 (Blank) - FBNV190002.xlsx XLSX spreadsheet
20. Section B - Price Fill-In.pdf PDF
5. 5015-21-3104 DMAFB Substation P&C Report - 100%.pdf PDF
9. DMAFB Electrical Distribution - Drawing Set - 100 pct.pdf PDF
19. Template of Contractor EAL.xlsx XLSX spreadsheet
4. 5015-21-3104 DMAFB Substation - 100% Structural Calcs.pdf PDF
11. E-601 SINGLE LINE DIAGRAM.pdf PDF
15. 355 CS Base Design Guide 2021.pdf PDF
18. AF Form 66 FBNV190002.xlsx XLSX spreadsheet
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Failure Action Plan Phase 1 outage – full bus outage on Saturday and Sunday. Main relay needs to be operational at end of this outage to reduce arc flash hazard to safe conditions during phase 2 work.

Main relay equipment failure – All relays supplied to DMAFB are Identical hardware. If a relay fails it will be replaced with one of the relays intended for the spare circuit and sent back to SEL for repair. Per SEL’s Warranty, the relay will be repaired or replaced and returned in time to be installed on one of the last days of install.

CT failure – New CT’s to be installed are split-core style and thus do not require disturbing existing incoming cable connections to install/remove. If one were found to be defective, CT’s would be shorted at shorting blocks, Failed CT would be removed and replacement ordered, Substation would be re-energized with main relay not in operation. Remainder of Install would need to be rescheduled for after replacement CT arrives.

Control Fuse failure – SEL is utilizing existing Control power circuits and it is SEL’s understanding that DMAFB electric shop has spare fuses on hand. If not, fuse from spare section could be used, when possible, while replacement fuse is sourced and procured.

Phase 2 outage – One circuit at a time is taken out of service for install. Loads to be transferred to other lines before taking circuit out of service.

Feeder Relay equipment failure – All relays supplied to DMAFB are Identical hardware. Relay will be replaced with relay intended for one of the spare circuits and sent back to SEL for repair.

Control Fuse failure – SEL is utilizing existing Control power circuits and it is SEL’s understanding that DMAFB electric shop has spare fuses on hand. If not, Loads have already been transferred to other circuits for isolation and installation. Affected circuit will remain isolated while replacement fuses are sourced and procured.

Bus Trip – All installation personnel stop work. Assist DMAFB staff to Investigate and resolve source of trip. Once source of trip is resolved, re-energize bus.

Failure Action Plan
Phase 1 outage – full bus outage on Saturday and Sunday. Main relay needs to be operational at end of this outage to reduce arc flash hazard to safe conditions during phase 2 work.
Phase 2 outage – One circuit at a time is taken out of service for install. Loads to be transferred to other lines before taking circuit out of service.

File details come from the government source that posted it. Updated .