12-13. 45th Lamar Project Manual.pdf

PDF 1 MB Posted

Attached to
SW 45th Avenue and S. Lamar Street Storm Drain Improvements
Solicitation number
BVB 411-26 YM
Issued by
Nueces County, Texas

About this file

Summary of SW 45th Avenue and S. Lamar Street Storm Drain Improvements

This is a project manual and contract document for the City of Amarillo, Texas, detailing storm drain improvements at SW 45th Avenue and S. Lamar Street (Project No. 560208, Bid No. 411-26 YM). The scope encompasses site preparation, demolition, grading, utilities installation, and pavement work necessary to construct storm drain improvements including excavation, embedment, backfill, installation of reinforced concrete pipe ranging from 24 inches to 60 inches in diameter, concrete box culverts (8 feet by 3 feet), junction boxes, storm curb inlets, chain link fencing, concrete curb and gutter, driveways, medians, pavement markings, and miscellaneous concrete structures. The project includes 48 distinct pay items with estimated quantities including 2,099 square yards of cut and restore asphalt paving, 374 linear feet of 54-inch reinforced concrete pipe, 271 linear feet of concrete box culvert, and various utility and drainage components. The contract requires a pre-construction conference with the contractor to establish schedules, and the contractor must begin work within ten calendar days of receiving notice to proceed. The project demands compliance with TxDOT specifications, City of Amarillo standards, and all applicable federal and state regulations including OSHA requirements for excavation safety and environmental controls.

Payment terms are structured as a lump sum contract with mobilization limited to no more than 5 percent of the total construction contract amount, with partial payments released upon achieving milestones such as when 1 percent of adjusted construction cost is earned (50 percent of mobilization paid), 5 percent earned (75 percent paid), and 10 percent earned (90 percent paid), with final payment upon project completion. The contractor must provide a performance bond and payment bond within ten calendar days of contract acceptance, along with certificates of insurance. Monthly progress payment requests must include updated project schedules, and the contractor is responsible for all material testing, with failed tests charged to the contractor and deducted from progress payments. The contract includes a five-year warranty on sealant installations and one-year warranties on grout work, and the contractor bears all costs associated with remediation of non-conforming work, including coring and structural analysis if required.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT DOCUMENTS AND TECHNICAL SPECIFICATIONS

FOR

SW 45TH AVE AND S LAMAR ST

STORM DRAIN IMPROVEMENTS

FOR

THE CITY OF AMARILLO, TEXAS

BID NO. 411-26 YM

PROJECT NO. 560208

APRIL 7, 2026

KIMLEY-HORN AND ASSOCIATES, INC.

TBPE F-928

04/07/2026

TABLE OF CONTENTS

1. COVER PAGE

2. TABLE OF CONTENTS

3. SPECIAL CONDITIONS

4. SPECIAL PROVISIONS

5. CONTRACTOR’S PROPOSAL

6. RELEVANT TxDOT SPECIFICATIONS

Item 100 Preparing Right of Way Item 104 Removing Concrete Item 105 Removing Treated and Untreated Base and Asphalt Pavement Item 160 Topsoil Item 164 Seeding for Erosion Control Item 166 Fertilizer Item 168 Vegetative Watering Item 247 Flexible Base Item 316 Seal Coat Item 400 Cut and Restore Asphalt Pavement Item 401 Flowable Fill Item 402 Trench Excavation Protection Item 432 Riprap Item 462 Concrete Box Culverts and Drains Item 464 Reinforced Concrete Pipe Item 465 Junction Boxes, Manholes, and Inlets Item 467 Safety End Treatment Item 496 Removing Structures Item 502 Barricades, Signs, and Traffic Handling Item 506 Temporary Erosion, Sedimentation, and Environmental Controls Item 529 Concrete Curb and Gutter Item 530 Concrete Driveways Item 536 Concrete Median Item 550 Chain Link Fence Item 666 Retroreflectorized Pavement Markings Item 677 Eliminate Existing Pavement Markings and Markers Item 3076 Dense-Graded Hot-Mix Asphalt

7. CITY OF AMARILLO STANDARDS AND SPECIFICATIONS

8. SUPPLEMENTARY DETAILED SPECIFICATIONS

9. REFERENCES

TxDOT Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (2024)

City of Amarillo Standards and Specifications

SPECIAL CONDITIONS

JOB #: 560208 BID #: 411-26 YM

SW 45TH AVE AND S LAMAR ST

STORM DRAIN IMPROVMENTS

for City of Amarillo

Note: Where there is a conflict between the Uniform General Conditions and the Special Conditions, the terms and conditions of the Special Conditions take precedent.

1. Article 1 Definitions: delete paragraph 1.29 Weekend/Holiday Work in its entirety.

2. Article 1 Definitions: replace paragraph 1.31 “Working Day/Work Day” with the following:

“Working Day/Work Day” a calendar day, including Saturdays and Sundays, and legal holidays observed by the Owner. Legal holidays are those holidays for which City Hall is closed.

3. Article 3. General Responsibilities of Owner & Contractor, Paragraph 3.3.2 Contractor’s Superintendent: Add the phrase “at all times when work is being performed” after “who will be present” in the first sentence.

4. Article 3. General Responsibilities of Owner & Contractor, Paragraph 3.4.1: Add “not” after “standards of the Project are”.

5. Article 3 General Responsibilities of Owner & Contractor: delete paragraph 3.6.2, 3.6.2.1, 3.6.2.2, ,3.6.2.3, 3.6.2.4, and 3.6.3 in their entirety.

6. Article 5. Contract Documents, Section 5.1 Drawings & Specifications: Replace Paragraph 5.1.1 Copies Furnished with the following:

An electronic version of the Drawings and Specifications will be made available to the Contractor. Hard copies can be printed by the Contractor. The City will not provide hard copies.

7. Article 5. Contract Documents, Paragraph 5.1.5 Estimated Quantities: Revise the last sentence of Paragraph 5.1.5.1 to read as follows:

“The Owner will pay for in-place quantities authorized by the Engineer unless plan quantity measurement is slated somewhere in the specifications or plans.”

8. Article 5. Contract Documents, Paragraphs 5.1.9 Lines and Grades, Paragraph 5.1.9.1:

Delete the phrase “Engineer furnished” from the last sentence.

9. Article 8 Project Scheduling Requirements: 8.3 Work Progress Schedule:

The Initial Work Progress Schedule is required to be submitted at the pre-construction meeting.

10. Article 8 Project Scheduling Requirements: 8.3.2 Schedule Updates: Updates to the project schedule are required on a monthly basis with the pay request submittal. Pay requests will not be reviewed until an updated schedule has been received.

11. Article 9 Payments: revise the third sentence in paragraph 9.3.1 Pay Estimate to say the following:

Once each month an itemized request for payment shall be submitted by the Contractor and a pay estimate processed by the ODR. Contractor’s submitted request for payment shall include an estimate of the amount of work performed, labor furnished materials on hand, and materials incorporated into the work, using the itemized bid proposal. An updated project schedule shall also be submitted with the request for payment. After evaluating the Contractor’s request for payment, the ODR will process a pay estimate that will include the following:

12. Article 10 Determining the Price of a Change Order: replace paragraph 10.8.1.1 with the following:

“Contractor shall provide written response to new price request within fifteen (15) calendar days of receipt.”

SPECIAL PROVISIONS

JOB # 560208

BID # 411-26 YM

SW 45TH AVE AND S LAMAR ST

STORM DRAIN IMPROVEMENTS

for City of Amarillo

Note: Where there is a conflict between the referenced Standard Specifications and these Special Provisions, the terms and conditions of these Special Provisions take precedent.

1. General Construction Notes

a. All construction work shall conform primarily to the most recent edition of the

TxDOT Standard Specifications for Construction and Maintenance of Highways, Streets, and Bridges (2024).

For items not addressed in the TxDOT Specifications, the City of Amarillo Standard Specifications shall govern. The City of Amarillo Standard Specifications are available on the Capital Projects and Development Engineering Department page of Amarillo.gov. In the event of a conflict where both TxDOT and City of Amarillo specifications apply, the TxDOT requirements shall govern unless otherwise directed by the Engineer. If an item is not addressed in either, the Supplementary Specifications shall apply.

Refer to Plan Sheet 4 – Quantity Summaries and Section 01025 Measurement and Payment for TxDOT, City, and Supplementary items. Measurement and Payment specified in Section 01025 Measurement and Payment shall govern over TxDOT and City of Amarillo specifications.

b. Removal of Construction Debris:

Asphalt, concrete, structural steel, dirt, brush, brick and debris to be removed from the project will not be allowed to dump at the City landfill facility. Other debris can be taken to the landfill at no charge if the Contractor has a current permit from the Public Works Division of the City of Amarillo.

c. All property disturbed and /or damaged by the Contractor outside the limits of the project shall be repaired, at the Contractor’s expense, to the adjacent property owner’s and the City Engineer’s satisfaction.

d. The Contractor shall be responsible for the verification of the location and depth of all utilities, pipes and sprinkler systems along the project route. The Contractor shall uncover lines at the request of the Engineer to verify possible elevation conflicts or other purposes at the Contractor’s expense. In addition, the Contractor shall, at his expense, protect and repair or pay the appropriate utility to repair, as determined by the affected utility, all utility lines and pipes which may be encountered and/or damaged during the course of the work.

e. The Contractor shall be responsible for any damages to public water or sewer systems. Damage to the operating stem or nut of a water valve will require the replacement of the entire valve. The Contractor shall make provisions to correct such damage at no additional cost to the City of Amarillo.

f. It shall be the responsibility of the Contractor to field verify all measurements, and notify the Engineer of any discrepancies immediately.

g. The Contractor shall be responsible for any coordination required for utility adjustments. The Contractor shall take all precautions necessary to protect utilities from damage due to traffic or vehicles and must ensure that the utilities are not an obstacle to traffic where damage can occur to vehicles.

Utilities Division, Water, and Wastewater:

Contact Fidencio Pena, (806) 378-6827, to coordinate approval of sanitary sewer manhole lid adjustments if required.

Contact Brian Brown, (806) 378-6826 to coordinate approval of water valve adjustments if required.

Traffic Field Operations:

Contact Ronnie Okerson, (806) 378-6802, to coordinate traffic signal timing changes and pull box adjustments.

Drainage Utility:

Contact Thaddeus Diaz, (806) 378-6909, for coordination with existing storm sewer system and for access to Bennett Lake.

h. Traffic control is the responsibility of the Contractor. The traffic control sheets provided in the plan set detail the general plan for construction phasing and traffic management. The Contractor shall submit any proposed traffic control modifications to the City and Engineer for approval prior to installation. The Contractor shall notify the City and Engineer in writing fourteen (14) days in advance of any traffic closures or changes to existing traffic conditions.

Any road closures shall be limited to the shortest time possible to minimize traffic disruptions. The Contractor shall notify all emergency services a minimum of 24 hours prior to any road closure.

i. The City of Amarillo, through its Texas Pollutant Discharge Elimination System (TPDES) Permit for storm water issued by the Texas Commission on Environmental Quality, is required to control the discharge of pollutants from construction sites that contribute runoff to its Municipal Separate Storm Sewer System (MS4). Additionally, City Ordinance Sec. 18-3-95, Storm Water Pollution

Prevention Plan, regulates storm water discharge from sites not meeting the size criteria to require an individual TPDES permit.

The Contractor shall implement sediment and erosion control measures in compliance with the City’s Storm Water Pollution Prevention Ordinance and all applicable State and Federal requirements prior to the start of construction;

including the development of a Storm Water Pollution Prevention Plan (SWPPP) as required.

The Contractor shall maintain the SWPPP, as required, on the project site at all times and shall inform the City Engineer or his representative of any condition that required a revision in the SWPPP. The Contractor shall maintain and post a copy of the Construction Site Notice, as required, on the project site.

j. The Contractor shall ensure that all water main valves and sanitary sewer manholes are accessible to the City at all times.

k. For curb and gutter, sidewalk, valley gutter, and other concrete removal, the Contractor shall saw cut at existing joints wherever possible.

l. All accessible routes, curb ramps, and pads shall meet the requirements of both the current United States Department of Justice “ADA Standards for Accessible Design” and the current Texas Department of Licensing and Regulation (TDLR) “Texas Accessibility Standards” (TAS).

m. Salvage of any material shown on plans for reuse is at the discretion of the

Contractor. Salvage valve is not part of this contract and will not be reimbursed in any manner if actual quantities do not match anticipated quantities.

n. The City is utilizing web-based project management software. The Contractor is required to use this software for the duration of the project. Documents submitted, tracked, and reviewed through the software system include submittals, pay requests, RFI’s, and other project correspondence. Access to the software will be provided at no cost to the Contractor. All other costs associated with utilizing the web-based project management software shall be included in the price bid for other items.

o. All work required to complete the project for which there is not a specific bid item shall be considered incidental to the bid item with which it is related.

p. Anything not specified by the TxDOT specifications shall be in accordance with the City specifications.

2. Modifications to the City Standard Specifications

a. City Subsection 6.01 Water Facilities General Construction Standards: X Construction Staking: Revise the first sentence to read as follows:

The Contractor shall be responsible for all construction staking on this project.

TO THE CITY OF AMARILLO,

AMARILLO, TEXAS

LADIES AND GENTLEMEN,

ITEM

NO.

NAME OF PAY ITEM

ESTIMATED

QUANTITY

UNIT

UNIT BID

PRICE

AMOUNT BID

1. MOBILIZATION 1 LS $ _________ $ _______________

2. TRAFFIC CONTROL 1 LS $ _________ $ _______________

3. EROSION CONTROL 1 LS $ _________ $ _______________

4. PREPARING ROW 4.5 STA $ _________ $ _______________

5. REMOV CONC (RIPRAP) 981 SY $ _________ $ _______________

6. REMOV CONC (MEDIANS) 33 SY $ _________ $ _______________

7. REMOV CONC (CURB & GUTTER) 54 LF $ _________ $ _______________

8. RMV (10") TRT/UNTRT BASE & ASPH PAV 103 SY $ _________ $ _______________

9. FLOWABLE BACKFILL 39 CY $ _________ $ _______________

10. REMOV STR (INLET) 5 EA $ _________ $ _______________

11. REMOVE STR (JUNCTION BOX) 2 EA $ _________ $ _______________

12. CHAIN LINK FENCE (REMOVE) 80 LF $ _________ $ _______________

13. ASPH (AC-10) 4191 GAL $ _________ $ _______________

14. AGGR (TY-PB, GR-4)(SAC-A) 146 CY $ _________ $ _______________

15. CUT & RESTORE ASPH PAVING 2099 SY $ _________ $ _______________

16. CONC CURB & GUTTER (TY II) 27 LF $ _________ $ _______________

17. DRIVEWAYS (CONC) 54 SY $ _________ $ _______________

18. CONC MEDIAN 32 SY $ _________ $ _______________

BID FORM

JOB #: 560208 BID #: 411-26 YM

BEST VALUE BID FOR SW 45TH AVE AND S LAMAR ST

STORM DRAIN IMPROVEMENTS

THE UNDERSIGNED BIDDER HEREBY DECLARES HE/SHE WILL DO ALL THE WORK AND PROVIDE ALL NECESSARY SUPERINTENDENCE, LABOR, TOOLS, EQUIPMENT, MACHINERY, AND APPARTAUS, AND WHATSOEVER ELSE MAY BE NECESSARY TO COMPLETE ALL OF THE WORK COVERED BY THIS PROPOSAL WITH THE TIME STATED, IN STRICT ACCORDANCE WITH THE CONTRACT DOCUMENTS AND THE REQUIREMENTS PERTAINING THERETO FOR

THE FOLLOWING PRICES TO WIT:

REMOVAL ITEMS

ROADWAY ITEMS

(CONTINUE TO NEXT PAGE)

ITEM

NO.

NAME OF PAY ITEM

ESTIMATED

QUANTITY

UNIT

UNIT BID

PRICE

AMOUNT BID

19. TRENCH EXCAVATION PROTECTION 1624 LF $ _________ $ _______________

20. RIPRAP (CONC)(5 IN) 114 CY $ _________ $ _______________

21. RIPRAP (CONC)(6 IN) 110 CY $ _________ $ _______________

22. RIPRAP (STONE PROTECTION)(12 IN) 168 CY $ _________ $ _______________

23. CONC BOX CULV (8 FT X 3 FT) 271 LF $ _________ $ _______________

24. RC PIPE (CL III)(24 IN) 103 LF $ _________ $ _______________

25. RC PIPE (CL III)(30 IN) 88 LF $ _________ $ _______________

26. RC PIPE (CL III)(36 IN) 53 LF $ _________ $ _______________

27. RC PIPE (CL III)(42 IN) 286 LF $ _________ $ _______________

28. RC PIPE (CL III)(48 IN) 249 LF $ _________ $ _______________

29. RC PIPE (CL III)(54 IN) 374 LF $ _________ $ _______________

30. RC PIPE (CL III)(60 IN) 164 LF $ _________ $ _______________

31. CITY B-15 STORM CURB INLET 4 EA $ _________ $ _______________

32. CITY B-30 STORM CURB INLET 5 EA $ _________ $ _______________

33. JCTBOX(COMPL)(PJB)(5FTX5FT) 1 EA $ _________ $ _______________

34. JCTBOX(COMPL)(PJB)(6FTX6FT) 5 EA $ _________ $ _______________

35. 7FT X 6FT JUNCTION BOX (COMPL) 1 EA $ _________ $ _______________

36. 10FT X 7FT JUNCTION BOX (COMPL) 1 EA $ _________ $ _______________

37. SET (TY I)(S= 8 FT)(HW= 4 FT)(4:1)(C) 1 EA $ _________ $ _______________

38. CHAIN LINK FENCE (INSTALL) (6') 80 LF $ _________ $ _______________

39. GATE 1 LS $ _________ $ _______________

40. REMOVE 6" WATER LINE 36 LF $ _________ $ _______________

41. WATER MAIN PIPE (PVC)(C900)(6 IN) & FITTINGS 42 LF $ _________ $ _______________

42. EXISTING SANITARY SEWER BYPASS 1 LS $ _________ $ _______________

UTILITY ITEMS

(CONTINUE TO NEXT PAGE)

DRAINAGE ITEMS

ITEM

NO.

NAME OF PAY ITEM

ESTIMATED

QUANTITY

UNIT

UNIT BID

PRICE

AMOUNT BID

43. REF PAV MRK TY II (W) 4" (BRK) 1039 LF $ _________ $ _______________

44. REF PAV MRK TY II (Y) 4" (BRK) 97 LF $ _________ $ _______________

45. REF PAV MRK TY II (Y) 4" (SLD) 3744 LF $ _________ $ _______________

46. REF PAV MRK TY I (W) 12" (SLD) 101 LF $ _________ $ _______________

47. REF PAV MRK TY I (W) 24" (SLD) 36 LF $ _________ $ _______________

48. REF PAV MRK TY I (W) ARROW (LT) 1 EA $ _________ $ _______________

TOTAL BID - PROJECT NO. _____________ $ _______________

PAVEMENT MARKING ITEMS

CONTRACTOR'S PROPOSAL

The undersigned hereby declares that he has visited each site and has carefully examined the Contract Documents relating to the work covered by the bid.

Work order proposal form(s) is/are made up of individual items of materials supplied or services performed for a completed project(s). A unit price is an amount stated in the bid as a price per unit of measurement for such items. The summation of total amount bid for each item is the total cost of the project and the contract amount per project combination instructions. The City will check bid extensions and summation. Mathematical errors will be corrected by the City.

A summation proposal which may consist of more than one proposal is not made up of individual items but will consist of one all inclusive item as a lump sum for the completed project.

The summation item and the project total will be the same.

Upon notice of the acceptance of this bid, the undersigned will execute the formal contract and will deliver the Performance Bond and Payment Bond, and Certificate of Insurance within ten

(10) calendar days. The bid security attached, without endorsement, in the sum of not less than five percent (5%) of the total bid is to be forfeited to the City of Amarillo, Texas in the event the contract and Bonds and Certification of Insurance are not executed within the time above set forth.

The undersigned agrees to begin work within ten (10) calendar days of receipt of a notice to proceed with a crew comparable to the size of the project(s) and will proceed continuously until the final completion of the project(s).

Number of Calendar Days Required for Final Completion:_________TOTAL WORKING DAYS

Job #:560208: SW 45th Ave and S Lamar St Storm Drain Improvements

Bid #: 411-26 YM

The undersigned hereby Respectfully submitted, acknowledges the receipt of the following addenda.

Name of Business Addenda #1 Issued __________ (Date) Addenda #2 Issued __________ (Date) By _________________________________ Addenda #3 Issued __________ (Date) Authorized Representative-Signed Date Addenda #4 Issued __________ (Date) Addenda #5 Issued __________ (Date) ____________________________________ Authorized Representative-Typed or printed

Business Address- City & State

Telephone Fax

Email

SUPPLEMENTARY DETAILED SPECIFICATIONS

DIVISION 1 – GENERAL REQUIREMENTS

City of Amarillo, Texas SECTION 01010 SW 45th Ave and S Lamar St Summary of Work Storm Drain Improvements Page 1 of 4 KHA No. 061210025 April 2026

PART I – GENERAL

1.1 Work covered by Contract Documents for SW 45th Ave and S Lamar St Storm Drain Improvements, Amarillo, TX.

A. This project shall consist of all work, complete and in place, including but not limited to site preparation, demolition, traffic control, grading, utilities, and paving, necessary to construct the storm drain improvements in Amarillo, Texas.

B. All work shall comply with the Texas Accessibility Standards (TAS) of the Architectural Barriers Act Article 9102, Texas Civil Statutes, effective April 1, 1994. This standard is prepared and administered by the Texas Department of Licensing and Regulations, Policies and Standards Division, Architectural Barriers Section, PO Box 12157, Austin, Texas 78711, 920 Colorado, Fourth Floor, Austin, Texas 78701, (512) 463-3211.

C. Contractor’s Duties

1. Provide and pay for:

a. Labor, materials, and equipment.

b. Tools, construction, equipment, and machinery.

c. Other facilities and services necessary for proper execution and completion of work.

2. Owner is exempt from sales tax on products permanently incorporated into the work.

Follow instructions issued by State Comptroller’s Office for purchase of such products free of tax.

3. Secure as necessary for proper execution and conditions of work:

a. License/Business Registration; paid by Contractor.

b. Permits/Approvals required by governing entities; paid by Contractor.

4. Comply with codes, ordinances, rules, regulations, orders, and other legal requirements of public authorities which bear on performance of work.

5. Promptly submit written notice to Owner of observed variances of Contract Documents from legal requirements.

6. Enforce strict discipline and good order among employees. Do not employ on work:

a. Unfit persons.

b. Persons not skilled in assigned task.

7. Checking Dimensions at Site:

a. Verify measurements as necessary before ordering any materials or doing any work.

b. Report any discrepancies to Owner for instructions before proceeding.

8. Approval of Working Conditions:

a. Notify the Owner of any unsatisfactory condition before beginning to perform work.

b. Beginning of work by Contractor shall constitute his acceptance of substrate and surface conditions.

9. Under no condition shall a portion of work proceed prior to preparatory work having been completed, cured, dried, or otherwise made satisfactory to receive such related work.

10. The Contractor shall establish and maintain his own grades, lines, levels, and bench marks. Verify all grades, lines, levels, and dimensions shown on drawings and report in writing any observed errors or inconsistencies to the Owner before beginning work.

Establish his own basic lines and grades in conformity with Owner’s permanent bench marks and coordinate systems for the construction area.

Storm Drain Improvements Page 2 of 4

11. It is the intent of this project that all items of work include the materials, standards, trades, procedures, etc., customarily associated with the items of work, whether or not such materials, standards, trades, procedures, etc., are expressly stated. In case of ambiguity, unclearness, or conflict in these Construction Documents, the matter shall be promptly submitted in writing for determination by the Owner. The Owner will render in writing a clarification reasonably inferable from these Documents and consistent with the intent of this proposed work.

12. Contractor shall employ only experienced and qualified workers and subcontractors.

1.2 Contracts

A. Perform work under Lump Sum Contract

1.3 Conditions of the Contract

A. The following Special Conditions also shall govern the work under each Section in the Technical Requirements.

1. Uninterrupted Operations. Work on this Project shall not interrupt or compromise the routine operations of the Owner unless specifically authorized by the Engineer.

2. Experienced Supervision. Employ a competent Supervisor for work on this Project, approved by the Owner, skilled in coordination of the trades involved and the type of scheduling required by a project of this nature. Replace approved Supervisor only with the permission of the Owner.

3. Contract Administration. The Engineer has the authority to act on behalf of the Owner to the extent provided for in the Contract Documents, unless otherwise modified by written instrument which will be shown to the Contractor at his request.

All instructions affecting Contract Sum, Contract Time, or Contract interpretations shall be confirmed expeditiously in writing only by owner, with copies furnished to the Owner’s designated representative and the Contractor by the party issuing the instructions.

4. Conduct of the Contractor

a. Type of Dress:

1.) Workmen must wear shirts at all times.

2.) Wearing apparel that portrays obscene or vulgar language and/or art work is prohibited.

b. Alcoholic Beverages and other Drugs:

1.) Alcoholic beverages and other drugs will not be permitted on the property of the Owner.

2.) Persons under the influence of alcoholic beverages and/or any other drug are prohibited from the Project.

c. Obscenity:

1.) The Owner reserves the right to require dismissal from the Project of any person using obscene gestures.

d. Portable Radios and Other Sound-Producing Devices:

1.) Hold the volume of portable radios or other sound-producing devices to such a level so that individuals not related to the construction are not disturbed.

2.) Do not broadcast obscenity.

1.4 Contractor Use of Premises

A. Confine operations at site to areas permitted by:

Storm Drain Improvements Page 3 of 4 KHA No. 061210025 April 2026

1. Law.

2. Ordinance.

3. Permits.

4. Contract Documents.

B. Limit use of site and premises to allow:

1. Uninterrupted Owner activity where required for Owner’s business purposes.

2. Work by Others and Work by Owner.

3. Use of site and premises by public where required for Owner’s business purposes.

C. Construction Operations:

1. Yard Operations and/or New Construction: Limited to areas noted on Drawings unless specifically approved otherwise by the Owner.

2. Protection:

a. Take over and assume responsibility for the premises necessary for each portion of the Work. Provide and maintain all protections required by governing laws, regulations, and ordinances. Be responsible for any loss or damage caused by workmen to the property of the Owner or to the work or materials installed.

Make good any loss, damage, or injury without cost to the Owner.

b. The protection of adjacent property shall include, but will not necessarily be limited to, the erection and maintenance of shoring, underpinning, and fences as necessary to protect and to support existing work to be left in place.

c. Protect against damage to all trees and all shrubs on the site which do not have to be removed for the Work. Remove or trim any tree or shrub only with the written approval of the Owner.

d. Send proper notices, make necessary arrangements, and perform other services required for the care, protection, and maintenance of utilities, including fire hydrants, piping, wires, and all other such items on and around the building site.

e. At no additional cost to the Owner, hold the Owner harmless from, and make good, any damage occurring as a result of the Contractor’s failure to provide required protection.

f. Provide temporary protection of the site during construction.

3. Other:

a. No fires on the site.

b. No dumping on the Owner’s property.

c. Do not unreasonably encumber site with materials or equipment.

d. Assume full responsibility for protection and safekeeping of products stored on premises.

e. Obtain and pay for use of additional storage or work areas needed for operations.

1.5 Concealed Piping and Conduit

A. Should active piping or conduit be encountered below grade or concealed by existing construction and be found at variance with the conditions indicated by the Drawings and Specifications, relocate such piping and/or conduit as directed by the Owner.

PART II – PRODUCTS

Not used.

Storm Drain Improvements Page 4 of 4 KHA No. 061210025 April 2026

PART III - EXECUTION

3.1 Cleaning Up

A. Contractor shall clean the work area at the end of each work day.

END OF SECTION 01010

City of Amarillo, Texas SECTION 01025 SW 45th Ave and S Lamar St Measurement and Payment Storm Drain Improvements Page 1 of 6

PART 1 – GENERAL

1.01 BID:

A. Required items of work and incidentals necessary for the satisfactory completion of the project shall be considered incidental to the specified work required under this Contract and shall be considered as included in the prices bid for the various bid items.

B. Work includes the furnishing of all labor, materials, equipment, tools, and related items for performing all operations required to complete the project satisfactorily in place, as specified by the Contract Documents.

1.02 MEASUREMENT AND PAYMENT:

A. Item No. 1 Mobilization, Bonding, and Insurance –

a. The cost for mobilization shall be limited to no more than 5% of the Contract amount for construction items (materials and labor) bid for this project.

b. Mobilization shall include costs associated with move-in related equipment and labor, bid bond, performance and construction bonds and insurance related for this project. This would include the establishment and removal of offices, plants and facilities, movement of personnel, equipment, and supplies to and from the project or the vicinity of the project site to begin work or complete work on Contract Items. This Item will be measured by the lump sum as the work progresses.

c. Payment. Partial payments of the lump sum bid for mobilization will be as follows. The adjusted Contract amount for construction Items as used below is defined as the total Contract amount less the lump sum for mobilization.

i. Payment will be made upon presentation of a paid invoice for the payment bond, performance bond, and required insurance. The combined payment for bonds and insurance will be no more than 10% of the mobilization lump sum.

ii. When 1% of the adjusted Contract amount for construction Items is earned, 50% of the mobilization lump sum bid will be paid. Previous payments under this Item will be deducted from this amount.

iii. When 5% of the adjusted Contract amount for construction Items is earned, 75% of the mobilization lump sum bid will be paid. Previous payments under the Item will be deducted from this amount.

iv. When 10% of the adjusted Contract amount for construction Items is earned, 90% of the mobilization lump sum bid will be paid. Previous payments under this Item will be deducted from this amount.

v. Payment for the remainder of the lump sum bid for “Mobilization” will be made on the final estimate after final acceptance of the project.

B. Item No. 2 Traffic Control – TxDOT Item 502: This pay item shall consist of all work, labor, materials, equipment, and incidentals necessary to complete the traffic control. Measurement for payment shall be on a lump sum basis.

a. Eliminate Existing Pavement Markings & Markers – TxDOT Item 677: This pay item is subsidiary to Item No. 2, Traffic Control, shown above and shall consist of all work, materials, equipment, tools, labor, incidentals, and removal methods necessary to remove existing pavement markings and raised pavement markers.

Storm Drain Improvements Page 2 of 6

A. Item No. 3 Temporary Erosion Sedimentation and Water Pollution Prevention and Control

– TxDOT Item 506 The unit price bid shall include furnishing and installing all materials, filing Notice of Intent/Termination forms, inspections, maintenance, silt fences, hay bales, sandbags, biodegradable logs, construction entrance/exit, diversion swales and any other measure and/or incidentals required for compliance with NPDES Permit. Payment will be made at the unit price bid per lump sum for the Storm Water Pollution Prevention Plan. Partial payment will be made on a pro-rata basis as a percentage of the construction contract duration. The sum of the partial payments made for stormwater pollution prevention shall not exceed 90% of the lump sum price bid for stormwater pollution prevention prior to the termination of the construction contract. No partial payment will be made for partial stormwater pollution prevention measures. Payment shall not be made for this item where the Owner determines a lack of evidence that stormwater pollution prevention measures were used, or that the measures installed do not meet the requirements of the plans. No additional payments will be allowed where stormwater pollution prevention is required because of work being remedied due to not meeting the requirements of the plans and specifications.

REMOVAL ITEMS

B. Item No. 4 Preparing Right of Way – TxDOT Item 100: This pay item shall consist of all work, including removal and trimming of designated trees and shrubs; removal and disposal of structures and obstructions; backfilling of holes; furnishing and placing concrete for plugs; and all equipment, labor, tools, and incidentals necessary to prepare the designated drainage easement for construction operations by removing and disposing of all obstructions when the removal of such obstructions is not specifically shown on the plans to be paid under other items. This item shall be measured by the 100-foot station, regardless of the width of the designated drainage easement.

C. Item No. 5 - 7 Removing Concrete – TxDOT Item 104: This pay item shall consist of all work, including breaking, loading, hauling, and salvaging or disposing of existing hydraulic cement concrete, as well as all equipment, labor, tools, and incidentals necessary to complete these operations. Measurement for payment shall be on a square yard basis for existing concrete riprap and median removal, and on a linear foot basis for existing concrete curb and gutter removal.

D. Item No. 8 Removing Treated and Untreated Base & Asphalt Pavement – TxDOT Item 105:

This pay item shall consist of all work, including breaking the material; loading, hauling, and unloading; stockpiling or disposing of material; repairing areas outside designated removal locations; and all equipment, labor, tools, and incidentals necessary to break, remove, and store or dispose of existing asphalt pavement, including surface treatments and treated or untreated base materials. Measurement for payment shall be on a square yard basis.

E. Item No. 9 Flowable Fill – TxDOT Item 401: This pay item shall consist of all work, including furnishing, hauling, and placing materials, as well as all equipment, tools, labor, and incidentals necessary to furnish and place flowable backfill for a trench, hole, or other void. Measurement for payment shall be on a cubic yard basis.

F. Item No. 10 & 11 Removing Structures – TxDOT Item 496: This pay item shall consist of all work, including demolition plan preparation; loading, hauling, disposal, and stockpiling; removal of appurtenances; excavation and backfill; and all equipment, labor, tools, and incidentals necessary to remove and either dispose of or salvage structures. Measurement for payment shall be on an

Storm Drain Improvements Page 3 of 6 each-structure basis for existing storm inlets and junction boxes.

G. Item No. 12 Chain Link Fence - TxDOT Item 550: This pay item shall consist of all work, including furnishing and installing fencing; cleaning, grading, and backfilling; removing and disposing of surplus material; and all materials, equipment, tools, labor, and incidentals necessary to furnish, install, remove, repair, or replace chain link fence and gates. Measurement for payment shall be on a linear foot basis.

ROADWAY ITEMS

H. Item No. 13 and 14 Asphalt Cement (AC-10) and Aggregate Precoated Crushed Gravel – TxDOT Item 316: This pay item shall consist of all work, including surface preparation;

furnishing, preparing, hauling, and placing materials; removing existing pavement markers and excess aggregate; rolling; cleaning up stockpiles; and all materials, equipment, labor, tools, and incidentals necessary to construct a surface treatment consisting of one or more applications of a single layer of asphalt material covered with a single layer of aggregate. Measurement for payment shall be on a gallon basis for asphalt cement (AC-10) and on a cubic yard basis for aggregate precoated crushed gravel.

I. Item No. 15 Cut and Restore Asphalt Pavement – TxDOT Item 400: This pay item shall consist of all work, including excavation, removal of obstructions, and plugging of drainage systems;

bedding and backfilling, including placing, sprinkling, and compacting material; soundings;

cleaning and filling seams; constructing and removing cofferdams; dewatering, sheeting, or bracing excavations up to and including 5 feet deep; pumps; drills; explosives; disposition of surplus material; cutting pavement and base to neat lines; and all materials, hauling, equipment, labor, tools, and incidentals necessary to excavate for the placement and construction of structures, backfill structures, and cut and restore pavement. Measurement for payment shall be on a square yard basis.

J. Item No. 16 Concrete Curb and Gutter – TxDOT Item 529: This pay item shall consist of all work, including surface preparation of the curb foundation, and all equipment, labor, materials, tools, and incidentals necessary to construct hydraulic cement concrete curb, gutter, and combined curb and gutter. Measurement for payment shall be on a linear foot basis.

a. City of Amarillo Section 4 Paving Subsection 4.09 applies as a supplementary item.

K. Item No. 17 Concrete Driveways – TxDOT Item 530: This pay item shall consist of all work, including furnishing and operating equipment; excavation and embankment; base and pavement materials; and all labor, materials, tools, and incidentals necessary to construct and pave driveways.

Measurement for payment shall be on a square yard basis.

a. City of Amarillo Section 4 Paving Subsection 4.11 applies as a supplementary item.

L. Item No. 18 Concrete Median – TxDOT Item 536: This pay item shall consist of all work, including preparing foundation surfaces; furnishing and operating equipment; constructing curbs and gutters used as part of the concrete median or directional island; and all labor, materials, tools, and incidentals necessary to construct cast-in-place concrete medians and directional islands.

Measurement for payment shall be on a square yard basis.

Storm Drain Improvements Page 4 of 6

a. City of Amarillo Section 4 Paving Subsection 4.10 applies as a supplementary item.

DRAINAGE ITEMS

M. Item No. 19 Trench Excavation Protection – TxDOT Item 402: This pay item shall consist of all work, including excavation and backfill required for excavation protection; furnishing, placing, and removing shoring, sheeting, or bracing; dewatering or diversion of water; jacking and jack removal; and all equipment, labor, materials, tools, and incidentals necessary to furnish and place excavation protection for trenches 5 feet or greater in depth for pipe, box culvert, electrical or telephone conduit, duct, or other utility installation. Measurement for payment shall be on a linear foot basis.

N. Item No. 20 - 22 Riprap – TxDOT Item 432: This pay item shall consist of all work, including furnishing, hauling, and placing riprap, filter fabric, expansion joint material, concrete and reinforcing steel, grout and mortar, scales, and all equipment, labor, tools, and incidentals necessary to furnish and place concrete, stone, cement-stabilized, or special riprap. Measurement for payment shall be on a cubic yard basis.

a. City of Amarillo Section 4 Paving Subsection 4.12 applies as a supplementary item.

O. Item No. 23 Concrete Box Culvert – TxDOT Item 462: This pay item shall consist of all work, including constructing, furnishing, and transporting sections; preparation and shaping of the bed and backfill material between box sections; jointing of sections and jointing material; cutting sections on skew or slope; connections to new or existing structures; breaking back, removing, and disposing of portions of existing structures and replacing portions of existing structures as required to make connections; concrete and reinforcing steel; and all equipment, labor, materials, tools, and incidentals necessary to furnish, construct, and install concrete box culverts and drains.

Measurement for payment shall be on a linear foot basis.

a. City of Amarillo Section 5 Storm Water Subsection 5.07 applies as a supplementary item.

P. Item No. 24, 25, 26, 27, 28, 29, & 30 Reinforced Concrete Pipe Class III – TxDOT Item 464:

This pay item shall consist of all work, including constructing, furnishing, transporting, placing, and joining pipes; shaping the bed; cutting pipes on skew or slope; connecting to new or existing structures; breaking back, removing, and disposing of portions of existing structures; replacing portions of existing structures; cutting pipe ends on skew or slope; and all equipment, labor, tools, and incidentals necessary to furnish and install reinforced concrete pipe, materials for precast concrete pipe culverts, or precast concrete storm drain mains, laterals, stubs, and inlet leads.

Measurement for payment shall be on a linear foot basis.

a. City of Amarillo Section 5 Storm Water Subsection 5.01 applies as a supplementary

Q. Item No. 31, 32, 33, 34, 35, and 36 Curb Opening Storm Inlet and Junction Box – TxDOT

465: This pay item shall consist of all work, including concrete, reinforcing steel, mortar, frames, grates, rings, and covers; excavation and backfill; and all other materials, tools, equipment, and labor necessary for furnishing and installing manhole rings and lids, foundation and floor

Storm Drain Improvements Page 5 of 6 construction, testing, backfill, and excavation, as well as any and all work required to construct junction boxes, manholes, and inlets, complete in place or to the stage detailed, including furnishing and installing frames, grates, rings, and covers. Measurement for payment shall be on a per-structure basis.

a. City of Amarillo Section 5 Storm Water Subsection 5.05 applies as a supplementary

R. Item No. 37 Safety End Treatment for Box Culvert – TxDOT Item 467: This pay item shall consist of all work, including constructing, furnishing, transporting, and installing end treatments;

pipe runners or pipe runner assemblies connecting to existing structures; breaking back, removing, and disposing of portions of existing structures; removing and disposing of existing pipe runners or pipe runner assemblies; replacing portions of existing structures as required to make connections;

excavation and backfill; furnishing concrete, reinforcing steel, CMP or RCP, and pipe runners; and concrete riprap, nuts, bolts, plates, angles, equipment, labor, tools, and incidentals necessary to furnish, construct, and install safety end treatments for drainage structures, or to install or replace pipe runners or pipe runner assemblies on existing drainage structures. Measurement for payment shall be on a per-structure basis.

a. City of Amarillo Section 5 Paving Subsection 5.06 applies as a supplementary item.

S. Item No. 38 Chain Link Fence - TxDOT Item 550: This pay item shall consist of all work, including furnishing and installing fencing; cleaning, grading, and backfilling; removing and disposing of surplus material; and all materials, equipment, tools, labor, and incidentals necessary to furnish, install, remove, repair, or replace chain link fence and gates. Measurement for payment shall be on a linear foot basis.

T. Item No. 39 Gate – This pay item shall consist of all work, labor, equipment, and materials necessary for installation as shown in the plans and details. Measurement for payment shall be on a lump sump basis.

UTILITY ITEMS

A. Item No. 40 & 41 Water Mains – City Section 6: This pay item shall consist of all work, including excavation and backfill required for excavation protection; furnishing, placing, and removing shoring, sheeting, or bracing; dewatering or diversion of water; hauling, placing, and installing materials; inspecting and testing; disconnecting and reconnecting existing water meters; and all other materials, labor, equipment, tools, and incidentals necessary to construct water mains of the sizes, materials, and dimensions shown on the plans, including pipe, joints, and connections to new and existing pipes; casing; valves; fittings; fire hydrants; meters; and blocking, as required to complete the work. Measurement for payment shall be on a linear foot basis.

B. Item No. 42 Existing Sanitary Sewer Main Bypass – The bypass pumping required to make connections shall consist of all work, labor, equipment, materials, and incidentals necessary to design, install, operate, monitor, and remove a temporary bypass pumping system. The Contractor shall prepare and submit an operational plan and a bypass pumping plan, as a shop drawing, a minimum of seven (7) days prior to the start of construction. The operational plan shall include, at a minimum, the Contractor’s sequence of construction required to maintain continuous flow in the existing

Storm Drain Improvements Page 6 of 6 sanitary sewer while a section of pipe is removed for installation of the box culverts and subsequently reconnected. The bypass system shall be capable of conveying all sewer flows around the work area during construction. Measurement and payment shall be on a lump-sum basis. Refer to Plan Sheet 58

– Storm Outfall Plan & Profile for the referenced note and Section 02750 – Bypass Pumping of Existing Sewer Systems for specifications.

PAVEMENT MARKING ITEMS

C. Item No. 43, 44, 45, 46, 47, & 48 Reflectorized Pavement Markings– TxDOT Item 666: This pay item shall consist of furnishing and placing retroreflectorized or non-retroreflectorized (shadow) pavement markings, including all materials, equipment, labor, tools, application of pavement markings, and incidentals necessary to complete the work. Measurement for payment will be made on a linear foot basis for stripes and on an each basis for arrows.

PART 2 - PRODUCTS - Not Applicable

PART 3 - EXECUTION - Not Applicable

END OF SECTION

City of Amarillo, Texas SECTION 01050 SW 45th Ave and S Lamar St Field Engineering Storm Drain Improvements Page 1 of 2 KHA No. 061210025 April 2026

1.01 DESCRIPTION:

A. Work included: Provide such field engineering services, which is defined as engineering services to be provided by the Contractor to complete the construction according to the plans and specifications, as are required for proper completion of the Work including, but not necessarily limited to:

1. Establishing and maintaining lines and levels;

2. Structural design of shores, forms, and similar items provided by the Contractor as part of their means and methods of construction.

B. Related Work:

1. Documents affecting work of this Section include, but are not necessarily limited to, General Conditions, General Construction Notes, Detailed Specifications, and Sections in Division 1 of the Supplementary Detailed Specifications.

2. Additional requirements for field engineering also may be described in other Sections of these

Specifications.

1.02 QUALITY ASSURANCE:

A. Use adequate numbers of skilled workmen who are thoroughly trained and experienced in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for proper performance of the work of this Section.

1.03 SUBMITTALS:

A. Comply with pertinent provisions of Section 01340 – Shop Drawings, Product Data, and Samples.

B. Upon request of the Engineer or Owner, submit:

1. Data demonstrating qualifications of persons proposed to be engaged for field engineering services.

2. Documentation verifying accuracy of field engineering work.

3. Certification, signed by the Contractor's retained field engineer, certifying that elevations and locations of improvements are in conformance or non-conformance with requirements of the Contract Documents.

1.04 PROCEDURES:

A. In addition to procedures directed by the Contractor for proper performance of the Contractor's responsibilities:

City of Amarillo, Texas SECTION 01050 SW 45th Ave and S Lamar St Field Engineering Storm Drain Improvements Page 2 of 2 KHA No. 061210025

1. Locate and protect control points before starting work on the site.

2. Preserve permanent reference points during progress of the Work.

3. Do not change or relocate reference points or items of the Work without specific approval from the Engineer.

4. Promptly advise the Engineer and Owner when a reference point is lost or destroyed, or requires relocation because of other changes in the Work.

a. Upon direction of the Engineer or Owner, require the field engineer to replace reference stakes or markers.

b. Locate such replacements according to the original Survey Control.

City of Amarillo, Texas SECTION 01090 SW 45th Ave and S Lamar St Definitions and Standards Storm Drain Improvements Page 1 of 4 KHA No. 061210025 April 2026

1.01 RELATED DOCUMENTS:

A. Plans and general provisions of Contract, including General Conditions and General Construction Notes and other Detailed and Supplementary Detailed Specification sections, apply to work of this section.

1.02 DESCRIPTION OF REQUIREMENTS:

A. General: This section specifies procedural and administrative requirements for compliance with governing regulations and codes and standards imposed upon the Work. These requirements include obtaining permits, licenses, inspections, releases, and similar documentation, as well as payments, statements and similar requirements associated with regulations, codes and standards.

1. The term "Regulations" is defined to include laws, statutes, ordinances, and lawful orders issued by governing authorities, as well as those rules, conventions and agreements within the construction industry which effectively control the performance of the work regardless of whether they are lawfully imposed by governing authority or not.

B. Governing Regulations: Refer to Division 1 – General Conditions and General Construction

Notes for requirements related to compliance with governing regulations.

1.03 DEFINITIONS:

A. General Explanation: Certain terms used in the contract documents are defined in this article.

Definitions and explanations contained in this section are not necessarily complete but are general for the Work to the extent that they are not stated more explicitly in another element of the contract documents.

B. General Requirements: Provisions and requirements of other Division-1 sections apply to the entire work of the Contract and, where so indicated, to other elements which are included in the project.

C. Indicated: The term "indicated" is a cross-reference to graphic representations notes or schedules on the plans, to other paragraphs or schedules in the specifications, and to similar means of recording requirements in contract documents. Where terms such as "shown", "noted", "scheduled", and "specified" are used in lieu of "indicated", it is for the purpose of helping the reader locate the cross-reference, and no limitation of location is intended except as specifically noted.

D. Directed, Requested, etc.: Terms such as "directed", "requested", "authorized", "selected", "approved", "required", "accepted", and "permitted" mean "directed by the Engineer", "requested by the Engineer", and similar phrases. However, no such implied meaning will be interpreted to extend the Engineer's responsibility into the Contractor's area of construction supervision.

E. Approve: Where used in conjunction with the Engineer's response to submittals, requests, applications, inquiries, reports and claims by the Contractor, the term…